CN201778479U - Detachable high-altitude working platform - Google Patents

Detachable high-altitude working platform Download PDF

Info

Publication number
CN201778479U
CN201778479U CN2010202759362U CN201020275936U CN201778479U CN 201778479 U CN201778479 U CN 201778479U CN 2010202759362 U CN2010202759362 U CN 2010202759362U CN 201020275936 U CN201020275936 U CN 201020275936U CN 201778479 U CN201778479 U CN 201778479U
Authority
CN
China
Prior art keywords
platform
guardrail
transverse
longitudinal
spandrel girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202759362U
Other languages
Chinese (zh)
Inventor
崔阁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mcc13 Construction Co ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN2010202759362U priority Critical patent/CN201778479U/en
Application granted granted Critical
Publication of CN201778479U publication Critical patent/CN201778479U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to a working platform, in particular to a high-altitude working platform. A detachable high-altitude working platform comprises a supporting platform arranged around a steel column and a guardrail around the platform; the platform consists of longitudinal and transverse supporting beams connected in a cross way; the guardrail consists of upright rods at four corners and transverse rods among the upright rods; the longitudinal and the transverse supporting beams are connected by bolts; the longitudinal and the transverse supporting beams are connected with the upright rods of the guardrail by bolts; and the upright rods of the guardrail are connected with the transverse rods of the guardrail by bolts. In the utility model, not only is a stable working environment supplied to workers, but also the detachable high-altitude working platform can be detached when not in use, and is convenient to store and transport.

Description

A kind of work high above the ground distachable platform
Technical field
The utility model relates to job platform, relates in particular to a kind of aerial work platform.
Background technology
When the steel column in high-rise stiffness structure lifted, the operating personnel carried out the butt joint of steel column and fixes and welding operation in the high-altitude, and is dangerous higher, stable job platform need be set to guarantee operating personnel's safety; Welding wind speed in high-altitude can't guarantee welding quality when big, need take effective draught exclusion device, to guarantee the quality of welding.
Adopted the mode of setting up the scaffold job platform in the past, and needed the lease scaffold, and need accredited scaffolder to pacify, tear open operation, cost is bigger more greatly and economically for danger.
Given this, people have adopted the shaped steel material a kind of aerial work platform, for the operating personnel provides a stable working environment, but this prefabricated platform by volume is bigger, preserves very trouble of transportation.
Summary of the invention
The utility model is intended to address the aforementioned drawbacks, and a kind of work high above the ground distachable platform is provided.The utility model not only provides stable operating environment for the operating personnel, and the time spent can not dismantled convenient preservation transportation.
The utility model is achieved in that a kind of work high above the ground distachable platform, a bearing platform and a platform guardrail all around that is arranged on around the steel column, it is characterized in that, described platform is made up of the longitudinal and transverse spandrel girder that right-angled intersection connects, described guardrail is made of four jiaos vertical rod and the cross bar between vertical rod, between the described longitudinal and transverse spandrel girder, in length and breadth spandrel girder and the end is gone along with sb. to guard him between the beam, the end is gone along with sb. to guard him between the beam and the guardrail vertical rod between, all connect between guardrail vertical rod and the guardrail cross bar with bolt.。
Described a kind of work high above the ground distachable platform, described steel column pass the bearing platform that longitudinal and transverse spandrel girder is formed, and have the gap between described longitudinal and transverse spandrel girder and the steel column, insert bquster in the gap.
Described a kind of work high above the ground distachable platform, described longitudinal and transverse spandrel girder is provided with at least one group of bolt connecting hole.
Described a kind of work high above the ground distachable platform is equipped with landing slab on the described bearing platform.
Described a kind of work high above the ground distachable platform, described guardrail is provided with the flameproof fabric that keeps out the wind.
The utility model connects by dismountable bolt, forms a job platform, and this platform is from heavy and light, and convenient fixing is easy to dismounting, can reuse, and can effectively protect the work high above the ground personal security and create good welding surroundings.
Description of drawings
Below, in conjunction with the accompanying drawings the utility model is further described:
Fig. 1 is a schematic diagram of the present utility model;
Fig. 2 is the upward view of Fig. 1.
The specific embodiment
As depicted in figs. 1 and 2, a kind of work high above the ground distachable platform, it comprises that one is arranged on bearing platform around the steel column and guardrail all around, it comprises, going along with sb. to guard him beam 3 in setting all around after described platform is connected by longitudinal and transverse spandrel girder 1,2 right-angled intersections constitutes, described guardrail comprises that four jiaos guardrail vertical rod 4 and the guardrail cross bar between vertical rod 5 constitute, between the described spandrel girder in length and breadth 1,2, spandrel girder 1, the 2 and end is gone along with sb. to guard him between the beam 3, fence the vertical rod 4 and end is gone along with sb. to guard him between the beam 3, all connect with bolt between fence vertical rod 4 and the fence cross bar 5 in length and breadth.
The docking port position operated by rotary motion of high-rise steel structure post has the bracket that connects with concrete beam reinforcing in floor face position about 1.2 meters positions on the floor face.Before first segment steel column lifting, earlier the steel column column cap is sling with crane, this job platform is installed on the steel column bracket under the docking port.After the lifting of first segment steel column, on platform, lay landing slab, can carry out the butt joint fixed operation of the second joint steel column; After the flameproof fabric that keeps out the wind being set all around, can carry out the high-altitude weld job.
During installation, earlier longitudinal and transverse spandrel girder 1,2 is installed, bolt connects, and it is fixing to squeeze into bquster 6.The mounting platform fence 3 then, and bolt is firm.Guardrail vertical rod 4 and guardrail cross bar 5 are installed afterwards, and bolt firmly this operating platform of back promptly installs.
This platform is from heavy and light, and convenient fixing is easy to dismounting, can reuse, and can effectively protect the work high above the ground personal security and create good welding surroundings.
Perforate on the described longitudinal and transverse spandrel girder 1,2 can be adopted the mode of many groups perforate, can effectively regulate the spandrel girder spacing, to be applicable to the steel column of different cross section form and cross-sectional sizes.

Claims (5)

1. work high above the ground distachable platform, it comprises that is arranged on a steel column bearing platform and a platform guardrail all around on every side, it is characterized in that, described platform is made up of the longitudinal and transverse spandrel girder that right-angled intersection connects, described guardrail is made of four jiaos vertical rod and the cross bar between vertical rod, between the described longitudinal and transverse spandrel girder, in length and breadth spandrel girder and the end is gone along with sb. to guard him between the beam, the end is gone along with sb. to guard him between the beam and the guardrail vertical rod between, all connect between guardrail vertical rod and the guardrail cross bar with bolt.
2. a kind of work high above the ground distachable platform according to claim 1 is characterized in that, described steel column passes the bearing platform that longitudinal and transverse spandrel girder is formed, and has the gap between described longitudinal and transverse spandrel girder and the steel column, inserts bquster in the gap.
3. a kind of work high above the ground distachable platform according to claim 1 is characterized in that described longitudinal and transverse spandrel girder is provided with at least one group of bolt connecting hole.
4. a kind of work high above the ground distachable platform according to claim 1 is characterized in that, is equipped with landing slab on the described bearing platform.
5. a kind of work high above the ground distachable platform according to claim 1 is characterized in that described guardrail is provided with the flameproof fabric that keeps out the wind.
CN2010202759362U 2010-07-29 2010-07-29 Detachable high-altitude working platform Expired - Fee Related CN201778479U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202759362U CN201778479U (en) 2010-07-29 2010-07-29 Detachable high-altitude working platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202759362U CN201778479U (en) 2010-07-29 2010-07-29 Detachable high-altitude working platform

Publications (1)

Publication Number Publication Date
CN201778479U true CN201778479U (en) 2011-03-30

Family

ID=43791693

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202759362U Expired - Fee Related CN201778479U (en) 2010-07-29 2010-07-29 Detachable high-altitude working platform

Country Status (1)

Country Link
CN (1) CN201778479U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625584A (en) * 2018-05-09 2018-10-09 五冶集团上海有限公司 A kind of tower body equipment temporary platform and its assemble method
CN110029804A (en) * 2019-04-10 2019-07-19 中铁建设集团有限公司 A kind of sizing steel operating platform
CN110778093A (en) * 2019-10-17 2020-02-11 五冶集团上海有限公司 Platform for installing instrument of coke oven diffusing pipe
CN111456424A (en) * 2020-03-24 2020-07-28 中国五冶集团有限公司 High formwork structure
CN114457994A (en) * 2022-01-10 2022-05-10 中建四局第六建设有限公司 Turnover steel cover shed vertical member protection construction platform and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625584A (en) * 2018-05-09 2018-10-09 五冶集团上海有限公司 A kind of tower body equipment temporary platform and its assemble method
CN110029804A (en) * 2019-04-10 2019-07-19 中铁建设集团有限公司 A kind of sizing steel operating platform
CN110778093A (en) * 2019-10-17 2020-02-11 五冶集团上海有限公司 Platform for installing instrument of coke oven diffusing pipe
CN111456424A (en) * 2020-03-24 2020-07-28 中国五冶集团有限公司 High formwork structure
CN114457994A (en) * 2022-01-10 2022-05-10 中建四局第六建设有限公司 Turnover steel cover shed vertical member protection construction platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN206328678U (en) Steel box-girder chooses arm and steel guard rail installs dual-purpose type Mobile operating platform
CN201778479U (en) Detachable high-altitude working platform
CN201843074U (en) Parallel moving bin for overhauling ramp bridge of overpass
CN205025072U (en) A construction platform device for high altitude construction
CN202706503U (en) Electric lifting discharging platform for main building construction
CN206859068U (en) A kind of Cable-stayed Bridge Pylon sill segmental timbering structure
CN105298107B (en) A kind of high carriage of High Large Cantilever structure
CN102912996B (en) Steel tube concrete column high-altitude construction safety protection system
CN104790644B (en) Extending and contracting sliding support frame for roof decorative bottom boards
CN215564558U (en) Retractable platform of unloading of encorbelmenting
CN202247713U (en) Combined protective shed frame
CN108547225A (en) A kind of assembly moving type security construction of prevention work job platform and construction method and application
CN209244220U (en) A kind of double cage security protection hanging cages for girder steel high altitude operation
CN202954552U (en) Steel tube concrete column high-altitude construction safety protection system
CN103774838A (en) Assembly type safe operation platform for elevator shaft construction and use method thereof
CN102425123B (en) Combined type protection shed frame and construction method thereof
CN106758862A (en) Lattice tubular tower and frame pacifies, tears platform open
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN206329024U (en) Hanging large-span steel-reinforced concrete structure construction steel platform
CN205474862U (en) Wet seam template operation platform of portable case roof beam
CN207878284U (en) Bailey beam cable saddle hoisting bracket
CN211947968U (en) Integral assembling type construction platform for high-altitude pier column construction
CN101967902A (en) Basic guide rail for helicopter assembly transmission line iron tower leg section
CN204038917U (en) Detachable external hanging type operating platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110330

Termination date: 20180729

CF01 Termination of patent right due to non-payment of annual fee