CN201774771U - Rack-mounted standard cabinet with internal circulating air duct - Google Patents

Rack-mounted standard cabinet with internal circulating air duct Download PDF

Info

Publication number
CN201774771U
CN201774771U CN2010202557750U CN201020255775U CN201774771U CN 201774771 U CN201774771 U CN 201774771U CN 2010202557750 U CN2010202557750 U CN 2010202557750U CN 201020255775 U CN201020255775 U CN 201020255775U CN 201774771 U CN201774771 U CN 201774771U
Authority
CN
China
Prior art keywords
air
cabinet
door
rack
inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202557750U
Other languages
Chinese (zh)
Inventor
钟亚呋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Sino-Device Technology Inc.
Original Assignee
钟亚呋
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 钟亚呋 filed Critical 钟亚呋
Priority to CN2010202557750U priority Critical patent/CN201774771U/en
Application granted granted Critical
Publication of CN201774771U publication Critical patent/CN201774771U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a rack-mounted standard cabinet with an internal circulating air duct, which comprises a cabinet body; a cavity is arranged in the cabinet body; an opening is formed on one side of the cabinet body; a cabinet door and a cabinet lock are mounted at the opening of the cabinet body; a ventilating duct is arranged in the cabinet body in the vertical direction; an air inlet and an air outlet are respectively formed at the upper end and the lower end of the ventilating duct; an air conditioner indoor unit is arranged in the cabinet body; an air conditioner indoor unit-air conditioner outdoor unit connecting pipe, an air-conditioning outlet and an air-conditioning inlet are respectively mounted on the air conditioner indoor unit; an air conditioner indoor unit is connected with an air conditioner outdoor unit through the connecting pipe; the air-conditioning outlet is communicated with the air inlet; a pipeline feeding hole is formed on the cabinet body; and a packing material is filled in the pipeline feeding hole after the mounting of pipelines. The utility model has the benefits that the rack-mounted standard cabinet can overcome the defects existing in the known technology, the internal temperature control device and the circulating air duct are respectively adopted, the independent machine room is not required to be arranged independently, and the defects of the conventional structure with the machine room and the rack-mounted standard cabinet in small and medium applications are overcome; and the rack-mounted standard cabinet has the dustproof effect and can be used for fully protecting the equipment in the cabinet.

Description

The rack standard cabinet of built-in circulation air path
Technical field
The utility model relates to the network cabinet field, specifically is a kind of rack standard cabinet of built-in circulation air path.
Background technology
Current, the common feature of rack standard cabinet is exactly the built-in frame of rack, separate ventilation in the rack, and the heat that the cabinet inner electronic equipment produces mainly reaches outside the cabinet by the circulation of rack inner air and outer air.In use, this rack has only played the effect of frame, but can't realize the function of cooling by self, and people must build one to air themperature, humidity, the very strict machine room of cleannes requirement for this reason.Such machine room not only involves great expense, and when ambient temperature is higher, also needs to expend the electronic equipment that a large amount of energy just can keep in the rack standard cabinet the whole equipment room refrigeration and runs well, and causes energy waste.Simultaneously, existing rack standard cabinet does not all have dust prevention.When using in machine room, the indoor dust of machine room can bring to outside cabinet in the cabinet the equipment with air-flow, influences the useful life of electronic equipment, and long-time dust accumulation causes electronic equipment to damage easily.And,, at this moment adopt the mode of machine room+rack standard cabinet if electronic equipments such as several station servers, switch are only arranged in some middle-size and small-size application scenarios, will cause very big waste.
Summary of the invention
The purpose of this utility model is to provide the rack standard cabinet of built-in circulation air path; it adopts closed structure; have built-in attemperating unit and circulation air path; can realize automatic temperature-controlled and the dustproof function; need not to set up separately machine room; greatly reduce maintenance cost, equipment in the rack is played a very good protection.
The utility model for achieving the above object, be achieved through the following technical solutions: the rack standard cabinet of built-in circulation air path, comprise cabinet, in the cabinet is cavity, cabinet one side opening, at the cabinet opening part cabinet door and cabinet lock are installed, on the vertical direction air pipe is set in the cabinet, air pipe is provided with air inlet and air outlet respectively in two ends up and down, air-conditioning internal machine is set in the cabinet, inside and outside machine tube connector installs an air-conditioner on the air-conditioning internal machine, air-conditioner air outlet and air-conditioning air inlet, air-conditioning internal machine is connected with outdoor machine of air-conditioner by the inside and outside machine tube connector of air-conditioning, air-conditioner air outlet communicates with air inlet, offers the pipeline inlet on the cabinet, and the pipeline inlet installs the back at pipeline filler is installed.
At cabinet and cabinet door contact site sealing strip is set.
The sidewall of described cabinet is dismountable movable side plate, and air pipe is installed in movable side plate inboard, between movable side plate and cabinet sealing strip is set.
Described air inlet is positioned at the cabinet top, and described air outlet is positioned at bottom of cabinet bulk.
Described filler is spontaneous bubble foam pointing.
Described cabinet sidewall is offered the first emergency ventilation mouth and the second emergency ventilation mouth respectively in two ends up and down, first promptly seals with air inlet and is communicated with, the second emergency ventilation mouth is positioned at the air outlet place, the first emergency ventilation mouth is positioned at an end of cabinet inboard first rotating shaft is installed, first air door that can the enclosed ventilation pipeline after install rotating in first rotating shaft, the second emergency ventilation mouth is positioned at an end of cabinet inboard second rotating shaft is installed, second air door is installed in second rotating shaft, the air door linkage is installed on first air door and second air door, air damper controller is installed in the cabinet, and the air door linkage is connected with air damper controller.
Described air door linkage is air door interlock backguy, and the reduction torsion spring that can make air door sealing emergency ventilation mouth is installed in first rotating shaft and second rotating shaft.
Described air damper controller is an air door control electromagnet.
On the described first emergency ventilation mouth and the first air door contact-making surface sealing strip is set, on the air pipe inlet and the first air door contact-making surface sealing strip is set, on the second emergency ventilation mouth and the second air door contact-making surface sealing strip is set.
The beneficial effects of the utility model are: can solve the deficiency that exists in the known technology, adopt built-in attemperating unit and circulation air path, need not to set up separately independent machine room, overcome the deficiency of existing " machine room+rack standard cabinet " mode, greatly reduce maintenance cost in some middle-size and small-size application scenarios; Integral body is enclosed construction, can play dustproof effect, equipment in the rack that adequately protects, the useful life of prolongation equipment; Rational in infrastructure, cooling efficient height, maintenance cost is low, and energy resource consumption is low; Be provided with promptly into and out of the air port, (have a power failure as the short time in order in case of emergency, the interior equipment of cabinet this moment is powered by UPS, so that run without interruption), utilize outside cold air to cooperate and continue temperature control with inner blower fan, structure is practical succinct, need not additionally to increase the temperature control blower fan, the fail safe that raising equipment uses; The utility model can be concentrated electronic equipment, temperature control device to be placed in the same dustproof cabinet space, just can satisfy the requirement of important electronic equipment to every working environment parameters such as temperature, humidity, cleannes with very low maintenance cost.
Description of drawings
Accompanying drawing 1 is a structural representation of the present utility model; Accompanying drawing 2 is local structure for amplifying schematic diagrames of I portion in the accompanying drawing 1.
Label shown in the accompanying drawing: 1, the inside and outside machine tube connector of air-conditioning; 2, filler; 3, pipeline inlet; 4, cabinet door; 5, cabinet lock; 6, cabinet; 7, air-conditioning air inlet; 8, air-conditioning internal machine; 9, air-conditioner air outlet; 10, air inlet; 11, air pipe; 12, movable side plate; 13, air outlet; 14, frame; 15, first air door; 16, first rotating shaft; 17, the first emergency ventilation mouth; 18, second air door; 19, second rotating shaft; 20, the second emergency ventilation mouth; 21, air door control electromagnet; 22, air door interlock backguy.
Embodiment
Below in conjunction with specific embodiment, further set forth the utility model.Should be understood that these embodiment only to be used to the utility model is described and be not used in the restriction scope of the present utility model.Should be understood that in addition those skilled in the art can make various changes or modifications the utility model after the content of having read the utility model instruction, these equivalent form of values fall within the application's appended claims institute restricted portion equally.
The rack standard cabinet of built-in circulation air path described in the utility model, agent structure comprises cabinet 6, cabinet 6 is standard cabinets.In the described cabinet 6 is cavity, and in order to place frame 13 and various electronic equipment, cabinet 6 one side openings are installed cabinet door 4 and cabinet lock 5 at opening part.On the vertical direction air pipe 11 is set in the described cabinet 6, air pipe 11 general vertically installations on the sidewall of cabinet 6 get final product.Air pipe is provided with air inlet 10 and air outlet 13 respectively in two ends about in the of 11.Air-conditioning internal machine 8 is set in the cabinet 6, and inside and outside machine tube connector 1, air-conditioner air outlet 9 and air-conditioning air inlet 7 install an air-conditioner on the air-conditioning internal machine 8.Air-conditioning internal machine 8 is connected with outdoor machine of air-conditioner by the inside and outside machine tube connector 1 of air-conditioning, and machine tube connector 1 can enter the mouth by pipeline and 3 pass cabinet 6 and be connected with outdoor machine of air-conditioner inside and outside the air-conditioning; Also through hole can be set separately on cabinet 6, the inside and outside machine tube connector 1 of air-conditioning passes this through hole and is connected with outdoor machine of air-conditioner.The inside and outside machine tube connector 1 of air-conditioning preferably is connected with outdoor machine of air-conditioner by pipeline inlet 3, and this embodiment need not to change cabinet 6 structures, can reduce the utility model production technology, the reduction manufacturing cost.Described air-conditioner air outlet 9 communicates with air inlet 10.Air-conditioning described in the utility model can be positioned at cabinet 6 each positions, only need the air-conditioning air inlet 7 of air-conditioning internal machine 8 is got final product with the two ends that air outlet 13 is arranged on cabinet 6, preferred version is that air-conditioning internal machine 8 is set directly at an end that is provided with air inlet 10, this is simple for structure, is easy to air-conditioner air outlet 9 and is communicated with air inlet 10.Offer pipeline inlet 3 on the cabinet 6, pipeline inlet 3 installs the back at pipeline filler 2 is installed.During use, with introducings place such as circuit, pipeline pipeline inlet 3, at pipeline 3 places that enter the mouth filler 2 is set in the engineering construction final stage, described filler 2 is preferably spontaneous bubble foam pointing; When pipeline need be adjusted, can excavate filler 2 in advance, treat that the pipeline adjustment row that finishes again mends and fill out.Filler 2 also adopts plasticine or gelatin substance etc.
When the utility model uses, when needs are lowered the temperature, then air-conditioning internal machine 8 produces cold wind, cold wind is blown into air inlet 10 by air-conditioner air outlet 9, cold wind arrives the other end of cabinet 6 along air pipe 1, under the air inducing effect of air-conditioning air inlet 7, cold wind passes electronic equipment from cabinet 6 one ends and arrives air-conditioning air inlet 7, and takes the heat that electronic equipment produces to air-conditioning internal machine 8 and dispel the heat.Circulation successively, thus the heat that cabinet 6 inner electronic equipments are produced is passed to outdoor machine of air-conditioner by machine tube connector 1 inside and outside air-conditioning internal machine 8 and the air-conditioning that outdoor machine of air-conditioner is connected, realizes the purpose of lowering the temperature.When needs heated up, then air-conditioning internal machine 8 produced warm braw, and all the other steps are same as the previously described embodiments.
The utility model is further characterized in that: in order to improve the sealing of cabinet 6, prevent that dust from entering, preferably at cabinet 6 and cabinet door 4 contact sites sealing strip is set.
In the above-described embodiments, for the ease of air pipe 11 is installed, make things convenient for air inlet 10 to cooperate with air-conditioner air outlet 9, the sidewall of described cabinet 6 preferably adopts dismountable movable side plate 12, movable side plate 12 installed inside air pipes 11,6 of movable side plate 12 and cabinets are provided with sealing strip.
In the utility model, (have a power failure as the short time in order to tackle urgent emergency case, the interior equipment of cabinet this moment is powered by UPS, so that run without interruption), guarantee electronic equipment stable operation, preferably offer the first emergency ventilation mouth 17 and the second emergency ventilation mouth 20 respectively in two ends up and down at cabinet 6 sidewalls, the first emergency ventilation mouth 17 is communicated with air inlet 10, the second emergency ventilation mouth 20 is positioned at air outlet 13 places, the first emergency ventilation mouth 17 is positioned at an end of cabinet 6 inboards first rotating shaft 16 is installed, first air door 15 that can enclosed ventilation pipeline 11 after install rotating in first rotating shaft 16, the second emergency ventilation mouth 20 is positioned at an end of cabinet 6 inboards second rotating shaft 19 is installed, second air door 18 is installed in second rotating shaft 19, the air door linkage is installed on first air door 15 and second air door 18, air damper controller is installed in the cabinet 6, and the air door linkage is connected with air damper controller.
In the present embodiment, described air door linkage can be that gangbar, travelling gear, drive are electric-linked etc., optimal technical scheme is: described air door linkage is air door interlock backguy 22, and the reduction torsion spring that can make air door sealing emergency ventilation mouth is installed in first rotating shaft 16 and second rotating shaft 19.Present embodiment is simple for structure, is easy to control, adopts air door interlock backguy 22, and it is little to take up room, and can not be subjected to the restriction of air door interlock backguy 22 self structure during use.Utilize reduction torsion spring to realize that air door automatically resets easy operating.Described air damper controller preferably adopts air door control electromagnet 21, and it is rational in infrastructure, and it is little to take up room, certainly, air damper controller adopt control motor equal controller also can, but its complex structure, institute takes up space big, not as air door control electromagnet 21 suitable.
In order to guarantee the sealing between urgent air port and air door, preferably on the first emergency ventilation mouth 17 and first air door, 15 contact-making surfaces, sealing strip is set, on the second emergency ventilation mouth 20 and second air door, 18 contact-making surfaces sealing strip is set, on air pipe 11 inlets and first air door, 15 contact-making surfaces sealing strip is set.
Present embodiment in use, when operate as normal, reduction torsion spring is closed in air door on the emergency ventilation mouth, prevents that extraneous air from entering cabinet 6, realizes sealing.When being in an emergency as: meet short time power failure, outdoor machine of air-conditioner shutdown etc.; this moment, cabinet 6 interior equipment were powered by UPS; so that run without interruption; in-cabinet temperature constantly rises; when reaching temperature control warning point, 21 adhesives of emergency system control air door control electromagnet are opened first air door 15, second air door 18 simultaneously by air door interlock backguy 22; first air door 15 is opened under the back and is turned over, and closes air pipe 11 simultaneously.This moment, the interior machine fan of air-conditioning internal machine 8 worked on, the hot-air that cabinet 6 inner electronic equipments produce is sent to its air-conditioner air outlet 9 by the interior machine fan of air-conditioning internal machine 8, deliver to outside the cabinet through the first emergency ventilation mouth 17, under the air inducing effect of the air-conditioning air inlet 7 of air-conditioning internal machine 8, the outer cold wind of cabinet enters in the cabinet through the second emergency ventilation mouth 20, pass electronic equipment from cabinet 6 one ends and arrive air-conditioning air inlet 7, and the heat that electronic equipment produces is sent to air-conditioner air outlet 9 by the interior machine fan of air-conditioning internal machine 8.Circulation successively, thus the heat that cabinet 6 inner electronic equipments are produced is distributed to outside the cabinet, guarantees the normal operation of electronic equipment.
In the utility model, air inlet 10 both can be positioned at the top of cabinet 6, also can be positioned at the bottom of cabinet 6, in order to make full use of the cold wind cooling, preferably air inlet 10 was arranged on cabinet 6 tops, and air outlet 13 is arranged on cabinet 6 bottoms.Cold wind weight is bigger, and air outlet 13 is arranged on cabinet 6 bottoms, can slow down the speed that cold wind rises, and increases the time of heat exchange, fully realizes the purpose to the electronic equipment cooling.In this embodiment, preferably air-conditioning internal machine 8 is arranged on cabinet 6 tops, is communicated with air-conditioner air outlet 9 to make things convenient for air inlet 10.

Claims (9)

1. the rack standard cabinet of built-in circulation air path, comprise cabinet (6), in the cabinet (6) is cavity, cabinet (6) one side openings, at cabinet (6) opening part cabinet door (4) and cabinet lock (5) are installed, it is characterized in that: on the interior vertical direction of cabinet (6) air pipe (11) is set, air pipe (11) two ends up and down is provided with air inlet (10) and air outlet (13) respectively, air-conditioning internal machine (8) is set in the cabinet (6), inside and outside machine tube connector (1) installs an air-conditioner on the air-conditioning internal machine (8), air-conditioner air outlet (9) and air-conditioning air inlet (7), air-conditioning internal machine (8) is connected with outdoor machine of air-conditioner by the inside and outside machine tube connector (1) of air-conditioning, air-conditioner air outlet (9) communicates with air inlet (10), offer pipeline inlet (3) on the cabinet (6), pipeline inlet (3) installs the back at pipeline filler (2) is installed.
2. the rack standard cabinet of built-in circulation air path according to claim 1 is characterized in that: at cabinet (6) and cabinet door (4) contact site sealing strip is set.
3. the rack standard cabinet of built-in circulation air path according to claim 1 and 2, it is characterized in that: the sidewall of described cabinet (6) is dismountable movable side plate (12), air pipe (11) is installed in movable side plate (12) inboard, between movable side plate (12) and cabinet (6) sealing strip is set.
4. the rack standard cabinet of built-in circulation air path according to claim 3, it is characterized in that: described air inlet (10) is positioned at cabinet (6) top, and described air outlet (13) is positioned at cabinet (6) bottom.
5. the rack standard cabinet of built-in circulation air path according to claim 1, it is characterized in that: described filler (2) is spontaneous bubble foam pointing.
6. the rack standard cabinet of built-in circulation air path according to claim 1, it is characterized in that: offer the first emergency ventilation mouth (17) and the second emergency ventilation mouth (20) respectively in two ends up and down at cabinet (6) sidewall, first promptly seals (17) is communicated with air inlet (10), the second emergency ventilation mouth (20) is positioned at air outlet (13) and locates, the first emergency ventilation mouth (17) is positioned at the inboard end of cabinet (6) first rotating shaft (16) is installed, first air door (15) that can enclosed ventilation pipeline (11) after first rotating shaft (16) go up to install is rotated, the second emergency ventilation mouth (20) is positioned at the inboard end of cabinet (6) second rotating shaft (19) is installed, second rotating shaft (19) is gone up second air door (18) is installed, first air door (15) and second air door (18) are gone up the air door linkage are installed, air damper controller is installed in the cabinet (6), and the air door linkage is connected with air damper controller.
7. the rack standard cabinet of built-in circulation air path according to claim 6, it is characterized in that: the air door linkage is air door interlock backguy (22), and the reduction torsion spring that installation can make air door sealing emergency ventilation mouth is gone up in first rotating shaft (16) and second rotating shaft (19).
8. according to the rack standard cabinet of claim 6 or 7 described built-in circulation air paths, it is characterized in that: described air damper controller is an air door control electromagnet (21).
9. the rack standard cabinet of built-in circulation air path according to claim 8, it is characterized in that: on the first emergency ventilation mouth (17) and first air door (15) contact-making surface sealing strip is set, on air pipe (11) inlet and first air door (15) contact-making surface sealing strip is set, on the second emergency ventilation mouth (20) and second air door (18) contact-making surface sealing strip is set.
CN2010202557750U 2010-07-12 2010-07-12 Rack-mounted standard cabinet with internal circulating air duct Expired - Lifetime CN201774771U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202557750U CN201774771U (en) 2010-07-12 2010-07-12 Rack-mounted standard cabinet with internal circulating air duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202557750U CN201774771U (en) 2010-07-12 2010-07-12 Rack-mounted standard cabinet with internal circulating air duct

Publications (1)

Publication Number Publication Date
CN201774771U true CN201774771U (en) 2011-03-23

Family

ID=43754612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202557750U Expired - Lifetime CN201774771U (en) 2010-07-12 2010-07-12 Rack-mounted standard cabinet with internal circulating air duct

Country Status (1)

Country Link
CN (1) CN201774771U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102548287A (en) * 2012-01-18 2012-07-04 南京华设科技有限公司 Network cabinet with air conditioner arranged at top
CN103047709A (en) * 2011-10-14 2013-04-17 艾默生网络能源有限公司 Integrated temperature control device, system and method of airflow air-conditioner
CN103074480A (en) * 2011-10-26 2013-05-01 苏州新长光热能科技有限公司 Controllable internal circulation cooling system used in heat treatment furnace
CN103096683A (en) * 2011-10-31 2013-05-08 鸿富锦精密工业(深圳)有限公司 Cabinet
CN104359151A (en) * 2014-10-10 2015-02-18 深圳市共济科技有限公司 Rack-mounted air-conditioner used in cabinet-type data center

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103047709A (en) * 2011-10-14 2013-04-17 艾默生网络能源有限公司 Integrated temperature control device, system and method of airflow air-conditioner
CN103047709B (en) * 2011-10-14 2017-03-15 艾默生网络能源有限公司 Air-flow air conditioner integrated attemperating unit, system and method
CN103074480A (en) * 2011-10-26 2013-05-01 苏州新长光热能科技有限公司 Controllable internal circulation cooling system used in heat treatment furnace
CN103096683A (en) * 2011-10-31 2013-05-08 鸿富锦精密工业(深圳)有限公司 Cabinet
CN102548287A (en) * 2012-01-18 2012-07-04 南京华设科技有限公司 Network cabinet with air conditioner arranged at top
CN104359151A (en) * 2014-10-10 2015-02-18 深圳市共济科技有限公司 Rack-mounted air-conditioner used in cabinet-type data center

Similar Documents

Publication Publication Date Title
CN101216222B (en) Double-mode cooling box
CN201774771U (en) Rack-mounted standard cabinet with internal circulating air duct
CN103373366A (en) Subway vehicle air conditioning unit ventilation system
CN203980561U (en) A kind of machine room natural cooling source energy conserving system
CN106918116B (en) Control method of base station air conditioner with multiple air supply modes
CN102957103A (en) Indoor dust-free ventilation inner and outer circulation device
CN202608783U (en) Ventilation system for air conditioning units of subway vehicle
CN203052902U (en) Intelligent primary air system
CN202488007U (en) Intelligent ventilation system for main transformer room
CN201526177U (en) Energy-saving heat-insulating cabinet type communication base station machine room
CN204835303U (en) Can sealed air conditioning switch cabinet
CN201286214Y (en) Outdoor synthetic machine cabinet
CN201377948Y (en) Communication room controlling temperature with phase-change materials
CN205304041U (en) Switch board with wind channel structure
CN204123932U (en) Back-positioned type air conditioner for electric motor coach
CN202561949U (en) Base station intelligent air ventilating and energy saving system
CN203820309U (en) Integral electrical chamber structure for tower crane
CN101532714A (en) Method for controlling communication machine room by adopting phase-change material
CN103604188B (en) Domestic indoor/outdoor air circulation system
CN206283772U (en) A kind of active air-flow drainage ventilation unit
CN106940048B (en) Base station air conditioner with rotatable multi-air supply mode
CN202419829U (en) Energy-saving heat-pipe air conditioner for base station
CN201918886U (en) Heat dissipating device for frequency converter
CN201426027Y (en) Outdoor light current equipment box
CN206478791U (en) A kind of building-member type data center machine room air-conditioning

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: HUASHE SCIENCE AND TECHNOLOGY CO., LTD., NANJING

Free format text: FORMER OWNER: ZHONG YAFU

Effective date: 20111018

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 415000 CHANGDE, HUNAN PROVINCE TO: 210000 NANJING, JIANGSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20111018

Address after: 210000, 01, B, 4 floor, Nanjing international service outsourcing industry park, 301 Hanzhoung Avenue, Nanjing, Jiangsu, China

Patentee after: Nanjing Sino-device Technology Co., Ltd.

Address before: 415000 National Taxation Bureau, Wuling Avenue, Changde, Hunan

Patentee before: Zhong Yafu

C56 Change in the name or address of the patentee

Owner name: NANJING SINO-DEVICE TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: HUASHE SCIENCE AND TECHNOLOGY CO., LTD., NANJING

CP01 Change in the name or title of a patent holder

Address after: 210000, 01, B, 4 floor, Nanjing international service outsourcing industry park, 301 Hanzhoung Avenue, Nanjing, Jiangsu, China

Patentee after: Nanjing Sino-Device Technology Inc.

Address before: 210000, 01, B, 4 floor, Nanjing international service outsourcing industry park, 301 Hanzhoung Avenue, Nanjing, Jiangsu, China

Patentee before: Nanjing Sino-device Technology Co., Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110323