CN201722617U - Mobile operation platform for overall connection and construction of split box girder - Google Patents

Mobile operation platform for overall connection and construction of split box girder Download PDF

Info

Publication number
CN201722617U
CN201722617U CN2010202170339U CN201020217033U CN201722617U CN 201722617 U CN201722617 U CN 201722617U CN 2010202170339 U CN2010202170339 U CN 2010202170339U CN 201020217033 U CN201020217033 U CN 201020217033U CN 201722617 U CN201722617 U CN 201722617U
Authority
CN
China
Prior art keywords
truss
construction
sub
girder
truss girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202170339U
Other languages
Chinese (zh)
Inventor
李开顺
向兴
李志刚
汪德才
诸利民
熊泽伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 2nd Engineering Co Ltd
Original Assignee
China Railway Erju Co Ltd
China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd, China Railway No 2 Engineering Group Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CN2010202170339U priority Critical patent/CN201722617U/en
Application granted granted Critical
Publication of CN201722617U publication Critical patent/CN201722617U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a mobile operation platform for the overall connection and construction of a split box girder, relates to the field of bridge construction equipment and aims to provide a mobile operation platform which smoothly carries out the horizontal connection and construction of a box girder when in split box girder construction, has high operation efficiency and low danger, which comprises a main truss girder, an auxiliary truss girder, a side truss girder and reinforcing ribs, wherein the main truss girder and the auxiliary truss girder are connected through the side truss girder; the horizontal middle part of the main truss girder is broken into two parts which are symmetric left and right; one side of the main truss girder which is towards to the auxiliary truss girder is provided with at least one pair of wheels out of shape which are arranged symmetrically left and right; the horizontal middle part of the auxiliary truss girder is broken into two parts which are hinged together; the side truss girder is provided with the reinforcing ribs which are respectively connected with the main truss girder and the auxiliary truss girder; and after the platform is hinged, a constructor can complete the horizontal connection and construction of the box girder on the platform.

Description

A kind of split type box girder integral connects the mobile operation platform of construction
Technical field
The utility model relates to the bridge construction equipment, especially relates to a kind of mobile operation platform that is used for the split type box girder construction of inter-city passenger rail.
Background technology
Present domestic inter-city passenger rail bridge main beam is generally whole opening box girder, adopts job practices whole opening prefabricated, that set up.Along with the high speed development of China's inter-city passenger rail, box-beam structure and job practices are also maked rapid progress.New a kind of new combined beam structure---the split type case beam of concrete that rises of in recent years domestic bridge circle has all reached its intended purposes and has obtained good evaluation through practice in multinomial engineering and check.
Split type case beam has following design feature: first, split type case beam is the prefabricated simply supported beam of post stressed concrete, adopt many packing lists solely prefabricated, set up installation separately, be mainly the two packing list chamber beams of two-wire, two-wire three packing list chamber beams, two-wire four packing list chamber beams, three-way five packing list chamber beams and four lines, seven packing list chamber beams; The second, cross the needs of striding in order to satisfy the bridge formation machine, split type case beam tabula shelves connecting reinforcement or steel plate all to be welded, wet seam connecting reinforcement welding 20% forms interim overall structure, reaches the bridge formation machine and crosses and stride the box girder integral rigidity requirement; The 3rd, in order to alleviate case beam deadweight and to increase transverse integral, between each case beam, establish tabula retaining, wet seam, the mode by construction tabula retaining, wet seam connects pore-forming, forms one and strides complete case beam.
Yet, in construction, need both to have satisfied the bridge formation machine and cross the requirement of striding, guarantee whole the promoting comprehensively of construction that connect again, adopt common job platform to be difficult to finish smoothly the case beam and laterally connect construction; Secondly, it is work high above the ground entirely that split type box girder integral connects construction, and difficulty of construction and potential safety hazard are big.
The utility model content
The purpose of this utility model is: provide a kind of when split type box girder construction, finish the case beam smoothly and laterally connect construction, operating efficiency height and dangerous low mobile operation platform.
The purpose of this utility model is achieved in that
A kind of split type box girder integral connects the mobile operation platform of construction, comprise that main truss is set a roof beam in place, sub-truss beam, side girder truss and reinforcing rib, wherein main truss is set a roof beam in place and is connected by the side girder truss with the sub-truss beam, main truss is set a roof beam in place and is broken into symmetrical two parts in its lateral middle, main truss is set a roof beam in place and is being provided with at least one pair of out of shape wheel towards sub-truss beam one side left and right symmetrically, the sub-truss beam is broken into two parts and pin joint together in its lateral middle, and the side girder truss is provided with respectively the reinforcing rib of setting a roof beam in place and being connected with the sub-truss beam with main truss.
The bottom of described side girder truss is provided with the horizontal brace summer with sub-truss Liangping row, the free end of described sub-truss beam is hinged with vertical brace summer, and horizontal brace summer is fixedlyed connected with vertical support beam end, builds a new support platform, can when construction, reduce consuming time and stroke; Described main truss is set a roof beam in place and is provided with mass at the middle part open end, has avoided the staff in climbing from the side or during load-carrying, operating platform unbalance stress and toppling; Described out of shape the wheel is arranged on the mass, makes out of shape the wheel can better press close to the target guide rail; Described main truss is set a roof beam in place, at least one beam is provided with ladder out of shape in sub-truss beam or the side girder truss, and described ladder out of shape is provided with out of shape, has increased the safety factor of construction.
The utility model utilizes truss structure and out of shape the wheel, simultaneously the sub-truss beam is broken into two parts and pin joint together in its lateral middle, platform is after hinged, the constructor can be on platform, finishes the case beam is laterally connected construction, has improved split type box beam erection efficient simultaneously, and reduced labour intensity, form pipelining, guarantee the lateral stability behind the split type box beam erection, guarantee the quality and the safety of split type box beam erection.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Wherein: 1 main truss is set a roof beam in place; 2 side girder trusses; 3 sub-truss beams; 4 out of shape wheels; 5 locking pins; 6 reinforcing ribs; 7 horizontal brace summers; 8 vertical brace summers; 9 mass; 10 ladders out of shape; 11 out of shape.
The specific embodiment
Below in conjunction with example and contrast accompanying drawing the utility model is described in further detail.
The mobile operation platform agent structure is a truss structure, be divided into symmetrical two parts, comprise by main truss and set a roof beam in place 1, sub-truss beam 3, the support body that side girder truss 2 and reinforcing rib 6 are formed, what support body adopted is the 14# i iron, main truss set a roof beam in place 1 with sub-truss beam 3 be separately fixed at side girder truss 2 on, following two ends, main truss is set a roof beam in place and 1 is broken into symmetrical two parts in its lateral middle, main truss is set a roof beam in place and all is fixed with the mass 9 that weight is 1.25t near 1 two ends that disconnect at the middle part, stressed in order to balance whole construction platform, mass 9 and main truss are set a roof beam in place and 1 are amounted to three pairs about being provided with and out of shapely take turns 4, frange plate on its position and the case beam is corresponding with crashproof wall displacement, with the frange plate on the case beam and crashproof wall as passage out of shape.The end welding of the bottom of side girder truss 2 and the horizontal brace summer 7 parallel with sub-truss beam 3, horizontal brace summer 7 is fixed together with vertical brace summer 8 ends, the end of the vertical brace summer 8 that the free end of sub-truss beam 3 and homonymy girder truss 2 are parallel is hinged, see on the whole, form re-entrant angle from outside to inside, in when construction, the staff can stand in horizontal brace summer 7 above construct, shortened the stroke of work.Sub-truss beam 3 is broken into two parts in its lateral middle, pin joint is together removably by locking pin 5 in end after the disconnection, when pin is taken apart, matching pair girder truss 3 is hinged with vertical brace summer 8, realize the rotation of sub-truss beam 3 around the hinged place, side girder truss 2 is provided with respectively and main truss 1 reinforcing rib 6 that is connected with sub-truss beam 3 of setting a roof beam in place.Sub-truss beam 3 and side girder truss 2 are provided with out of shape terraced 10, so that constructor's climbing also is provided with out of shape 11 on out of shape terraced 10, provide safer job platform.
Operating principle of the present utility model is:
Mobile operation platform is divided into two parts of left and right symmetry, packs into from the both sides of split type case beam during installation, out of shapely takes turns 4 and places on the frange plate of split type case beam and the crashproof wall as walking row of channels, connects with pin in the middle of the truss.With truss under the counterweigh and construction operation load.Adopt manpower to promote mobile operation platform during construction and move, carry out work such as the installation of reinforcing bar welding that split type box girder integral connects construction, template and dismounting along the axis of split type case beam.

Claims (6)

1. a split type box girder integral connects the mobile operation platform of constructing, it is characterized in that: comprise main truss set a roof beam in place (1), sub-truss beam (3), side girder truss (2) and reinforcing rib (6), wherein main truss set a roof beam in place (1) be connected by side girder truss (2) with sub-truss beam (3), main truss set a roof beam in place (1) be broken into symmetrical two parts in its lateral middle, main truss set a roof beam in place (1) be provided with at least one pair of out of shape wheel (4) towards sub-truss beam (3) one side left and right symmetricallies, sub-truss beam (3) is broken into two parts and pin joint together in its lateral middle, and side girder truss (2) is provided with the reinforcing rib (6) that set a roof beam in place with main truss respectively (1) is connected with sub-truss beam (3).
2. split type box girder integral according to claim 1 connects the mobile operation platform of construction, it is characterized in that: the bottom of described side girder truss (2) is provided with the horizontal brace summer (7) parallel with sub-truss beam (3), the free end of described sub-truss beam (3) is hinged with vertical brace summer (8), and horizontal brace summer (7) is fixedlyed connected with vertical brace summer (8) end.
3. split type box girder integral according to claim 1 connects the mobile operation platform of construction, it is characterized in that: described main truss set a roof beam in place (1) be provided with mass (9) at the middle part open end.
4. split type box girder integral according to claim 3 connects the mobile operation platform of construction, it is characterized in that: also be provided with out of shape wheel the (4) on the described mass (9).
5. split type box girder integral according to claim 1 connects the mobile operation platform of construction, it is characterized in that: described main truss is set a roof beam in place (1), at least one beam is provided with ladder out of shape (10) in sub-truss beam (3) or the side girder truss (2).
6. split type box girder integral according to claim 5 connects the mobile operation platform of construction, and it is characterized in that: described ladder out of shape (10) is provided with out of shape (11).
CN2010202170339U 2010-06-07 2010-06-07 Mobile operation platform for overall connection and construction of split box girder Expired - Lifetime CN201722617U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202170339U CN201722617U (en) 2010-06-07 2010-06-07 Mobile operation platform for overall connection and construction of split box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202170339U CN201722617U (en) 2010-06-07 2010-06-07 Mobile operation platform for overall connection and construction of split box girder

Publications (1)

Publication Number Publication Date
CN201722617U true CN201722617U (en) 2011-01-26

Family

ID=43490932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202170339U Expired - Lifetime CN201722617U (en) 2010-06-07 2010-06-07 Mobile operation platform for overall connection and construction of split box girder

Country Status (1)

Country Link
CN (1) CN201722617U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900023A (en) * 2012-10-31 2013-01-30 武船重型工程股份有限公司 Combined operating platform
CN106836639A (en) * 2017-04-11 2017-06-13 南京工业大学 FRP box-shaped section-concrete combined beam provided with bidirectional shear keys

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900023A (en) * 2012-10-31 2013-01-30 武船重型工程股份有限公司 Combined operating platform
CN102900023B (en) * 2012-10-31 2015-10-14 武船重型工程股份有限公司 A kind of combined type working platform
CN106836639A (en) * 2017-04-11 2017-06-13 南京工业大学 FRP box-shaped section-concrete combined beam provided with bidirectional shear keys

Similar Documents

Publication Publication Date Title
CN202466845U (en) Middle-layer node connecting structure for steel tube concrete column and steel reinforced concrete beam
CN105604182B (en) The through round steel pipe constraint reinforced column steel girder frame node of girder steel
CN108360380A (en) A kind of bridge pier column construction operation platform and its construction method
CN105926775A (en) Novel concrete-filled steel tube beam column joint
CN202755313U (en) Tunnel portal short-distance girder-erecting and tunnel-passing bridge-erecting machine
CN201722617U (en) Mobile operation platform for overall connection and construction of split box girder
CN202466844U (en) Top layer node connecting structure for concrete-filled steel tube column and steel reinforced concrete beam
CN204941569U (en) Tunnel invert trolley formwork system
CN216889750U (en) Detachable movable portal frame for improving hoisting operation safety
CN203361654U (en) Prefabricated steel frame component
CN202882375U (en) Elevator shaftway tool type scaffold operation platform
CN206111212U (en) Rock -anchored beam construction trolley car
CN206172871U (en) Movable jack -up machines
CN210975570U (en) Operation platform for construction of large-section steel-concrete composite beam
CN112502475B (en) Supporting bearing capacity conversion device and using method thereof
CN210001412U (en) Recyclable platform for quickly hoisting steel truss arch rod piece
CN104278628A (en) Light hanging basket applicable to bridge detection and maintenance operations
CN102587359B (en) Reusable reinforced concrete composite pile available for on-load segmental disassembly and construction method of reusable reinforced concrete composite pile available for on-load segmental disassembly
CN203559573U (en) Foldable suspension of suspended platform
CN201961992U (en) High-low gantry crane which is used for hoisting T beam with large span and formed by steel tube stand columns
CN207277893U (en) A kind of section steel platform formwork erecting structure for high-altitude overhanging
CN220789400U (en) Steel-concrete variable-diameter column construction device
CN210031524U (en) A operation car for construction of bridge anticollision barrier template
CN204212069U (en) Hanging basket for building construction
CN221322416U (en) Movable multifunctional operation platform device in tunnel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160105

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.

Address before: 610041 high building, No. nine Hing Road, Chengdu hi tech Development Zone, Sichuan, 6

Patentee before: China Railway Erju Co., Ltd.

Patentee before: China Railway No. 2 Engineering Group Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20180821

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: No.2 Engineering Co., Ltd. of China Railway Erju

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee before: China Railway No. 2 Engineering Group Co., Ltd.

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: No.2 Engineering Co., Ltd. of China Railway Erju

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee before: No.2 Engineering Co., Ltd. of China Railway Erju

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

CP01 Change in the name or title of a patent holder
CX01 Expiry of patent term

Granted publication date: 20110126

CX01 Expiry of patent term