CN201688844U - Inverted vertical device for providing vertical reference for construction of high-rise building - Google Patents

Inverted vertical device for providing vertical reference for construction of high-rise building Download PDF

Info

Publication number
CN201688844U
CN201688844U CN2010201812009U CN201020181200U CN201688844U CN 201688844 U CN201688844 U CN 201688844U CN 2010201812009 U CN2010201812009 U CN 2010201812009U CN 201020181200 U CN201020181200 U CN 201020181200U CN 201688844 U CN201688844 U CN 201688844U
Authority
CN
China
Prior art keywords
vertical
construction
floating
steel lining
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201812009U
Other languages
Chinese (zh)
Inventor
晏春波
朱武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN2010201812009U priority Critical patent/CN201688844U/en
Application granted granted Critical
Publication of CN201688844U publication Critical patent/CN201688844U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an inverted vertical device for providing a vertical reference for construction of a high-rise building, comprising a vertical body, wherein the lower end of the vertical body is fixed with an anchorage point, and the upper end thereof is connected with a floating body in a floating barrel which is arranged on a bracket and is provided with a floating barrel cover; and the vertical body is a steel wire with the diameter being 1mm, and the buoyancy force thereof is more than 40kg. The inverted vertical device for providing the vertical reference for construction of the high-rise building solves the problem of being difficult to provide the vertical reference in the construction of the high-rise building, thus guaranteeing the constructional quality, and especially solves the difficult problem of guaranteeing the verticality of a shaft steel lining in the construction process in the construction of the shaft steel lining of a ship lift in a hydropower station, thus also guaranteeing the roundness and accuracy , good construction efficiency and good quality of the shaft steel lining simultaneously; the design of the floating barrel cover can avoid the influence of wind power on the floating body in the floating barrel, thus further guaranteeing the accuracy of the construction; and by the specification limit of the vertical body and the floating body, the vertical body has enough effective vertical.

Description

Be used to provide the reversed pendulum device of high-building construction vertical reference
Technical field
The utility model relates to a kind of building deformation monitoring device, particularly a kind of reversed pendulum device that is used to provide the high-building construction vertical reference.
Background technology
Reversed pendulum is widely used in monitoring the displacement of dam, the dam foundation, nuclear power station, bridge, overhead railway and bridge pier as the reference installation of building deformation monitoring.But the reversed pendulum device is applied as the construction survey service then beyond example, especially for providing on the high-building construction vertical reference.High-rise is because it is highly high, the bad assurance of construction vertical reference is especially in the vertical shaft steel lining construction of power station ship lift, because the vertical shaft steel lining is the circular metal structure, its verticality, circularity, precision are difficult to control in the construction, and operating efficiency is low, construction quality is difficult to be guaranteed.
Summary of the invention
Technical problem to be solved in the utility model provides the reversed pendulum device that a kind of simple in structure being used to provides the high-building construction vertical reference, the problem that vertical reference is difficult to provide in the high-building construction has been provided, guaranteed construction quality, particularly in vertical shaft steel lining construction at the power station ship lift, solved a difficult problem that guarantees vertical shaft steel lining verticality in the work progress, also guaranteed that the circularity of vertical shaft steel lining and precision, operating efficiency height, quality are good simultaneously.
In order to solve the problems of the technologies described above, the technical solution of the utility model is: a kind of reversed pendulum device that is used to provide the high-building construction vertical reference, comprise the vertical line body, and vertical line body lower end and anchor point are fixed, the interior buoyancy aid of vertical line body upper end and floating drum is connected, and floating drum is rack-mount.
Floating drum is provided with the floating drum lid.
The vertical line body is the steel wire of diameter 〉=1mm, the buoyancy>40Kg of buoyancy aid.
The reversed pendulum device that is used to provide the high-building construction vertical reference that the utility model provides, because vertical line body lower end and anchor point are fixed, the interior buoyancy aid of vertical line body upper end and rack-mount floating drum is connected, vertical line body lower end is fixed by anchor point, vertical line body upper end is strained by buoyancy aid, promptly become the vertical reference of high-building construction by the reversed pendulum of anchor point tension, simple in structure, installation rate is fast, low cost of manufacture, and the precision height of construction, the vertical line body just can be worked under the situation of the sleeve pipe that do not need protection, simplify the structure, accelerated construction speed, guaranteed construction quality, especially be applied in the vertical shaft steel lining construction of power station ship lift of metal construction, solve a difficult problem that guarantees vertical shaft steel lining verticality in the work progress, also guaranteed the circularity and the precision of vertical shaft steel lining simultaneously, the operating efficiency height, construction quality is good; The design of floating drum lid makes floating drum become the integral body of a sealing, can avoid the influence of wind-force to buoyancy aid in the floating drum, has further guaranteed the precision of construction; The vertical line body adopts the buoyancy of the steel wire of diameter 〉=1mm and buoyancy aid should be greater than 40Kg, and it is enough effectively vertical to have guaranteed that the vertical line body has.
In the construction of certain power station ship lift vertical shaft steel lining, ship lift vertical shaft steel lining inwall measurement point is to the distance R=3.25m of reference center's line, Δ R in the same section of designing requirement≤± 5mm, in the actual measurement process, Δ R≤± 5mm account for the sum 99.65%, illustrate and adopt the utility model to carry out the construction of vertical shaft steel lining, method is selected rationally, and installation quality is good.
Description of drawings
The utility model is described in further detail below in conjunction with drawings and Examples:
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is the synoptic diagram that the utility model is applied to power station ship lift vertical shaft steel lining construction.
Embodiment
As shown in Figure 1, the utility model comprises vertical line body 4, and vertical line body 4 lower ends and anchor point 5 is fixing, and vertical line body 4 upper ends and floating drum 1 interior buoyancy aid 2 is connected, and floating drum 1 is installed on the support 3.
Floating drum 1 is provided with floating drum lid 6.
Vertical line body 4 is the steel wire of diameter 〉=1mm, the buoyancy>40Kg of buoyancy aid 2.
As shown in Figure 2, the utility model is applied to high-story architecture construction, and is as follows as the process in the power station ship lift vertical shaft steel lining 7:
1, the anchor point of vertical shaft end liner is correct fixing: before the anchor point location, axis to vertical shaft steel lining 7 is measured by the requirement of fourth class system point, determines axis, builds and after grouting finishes at vertical shaft end liner second stage concrete, at vertical shaft end liner center, anchor point is accurately located.After each setting-out is finished, must check the relation of the relative size between the layout point, and compare with previous layout point, guarantee the setting-out achievement accurately and reliably, every survey tolerance is all for installation shaft line and elevation basic point.
2, the utility model is installed, vertical line body 4 lower ends and anchor point 5 are fixing, support 3 is installed on the diameter of vertical shaft steel lining 7, vertical line body 4 is by 2 tensions of the buoyancy aid in the floating drum 1 of upper end, promptly become the construction and installation benchmark of vertical shaft steel lining 7, in the construction, along with the rising of vertical shaft steel lining 7 height, the length of lengthen anchor point 5 and 2 vertical line bodies of buoyancy aid.
During metric data, near some construction vibrations as far as possible reducing in the measurement process are in order to avoid influential to measuring in the construction.

Claims (3)

1. reversed pendulum device that is used to provide the high-building construction vertical reference, comprise vertical line body (4), it is characterized in that: vertical line body (4) lower end and anchor point (5) are fixing, the interior buoyancy aid (2) of vertical line body (4) upper end and floating drum (1) is connected, and floating drum (1) is installed on the support (3).
2. the reversed pendulum device that is used to provide the high-building construction vertical reference according to claim 1 is characterized in that: floating drum (1) is provided with floating drum lid (6).
3. the reversed pendulum device that is used to provide the high-building construction vertical reference according to claim 1 and 2 is characterized in that: vertical line body (4) is the steel wire of diameter 〉=1mm, the buoyancy>40Kg of buoyancy aid (2).
CN2010201812009U 2010-05-06 2010-05-06 Inverted vertical device for providing vertical reference for construction of high-rise building Expired - Fee Related CN201688844U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201812009U CN201688844U (en) 2010-05-06 2010-05-06 Inverted vertical device for providing vertical reference for construction of high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201812009U CN201688844U (en) 2010-05-06 2010-05-06 Inverted vertical device for providing vertical reference for construction of high-rise building

Publications (1)

Publication Number Publication Date
CN201688844U true CN201688844U (en) 2010-12-29

Family

ID=43377124

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201812009U Expired - Fee Related CN201688844U (en) 2010-05-06 2010-05-06 Inverted vertical device for providing vertical reference for construction of high-rise building

Country Status (1)

Country Link
CN (1) CN201688844U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102759344A (en) * 2012-08-13 2012-10-31 中国水电顾问集团中南勘测设计研究院 Drooping-down buoyancy leveling device
CN102798378A (en) * 2012-08-13 2012-11-28 中国水电顾问集团中南勘测设计研究院 Inverting buoyancy adjusting device
CN103968813A (en) * 2014-04-25 2014-08-06 中交第二航务工程局有限公司 Deepwater high-precision anti-rotating inverted measuring device
CN113607125A (en) * 2021-08-04 2021-11-05 中国电建集团昆明勘测设计研究院有限公司 Monitoring system for monitoring tension of inverted plumb measuring line and using method
CN114737549A (en) * 2021-09-08 2022-07-12 华能澜沧江水电股份有限公司 Hydraulic ship elevator tower and vertical shaft steel lining pipe group integrated construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102759344A (en) * 2012-08-13 2012-10-31 中国水电顾问集团中南勘测设计研究院 Drooping-down buoyancy leveling device
CN102798378A (en) * 2012-08-13 2012-11-28 中国水电顾问集团中南勘测设计研究院 Inverting buoyancy adjusting device
CN102759344B (en) * 2012-08-13 2014-04-02 中国水电顾问集团中南勘测设计研究院 Drooping-down buoyancy leveling device
CN102798378B (en) * 2012-08-13 2014-07-09 中国水电顾问集团中南勘测设计研究院 Inverting buoyancy adjusting device
CN103968813A (en) * 2014-04-25 2014-08-06 中交第二航务工程局有限公司 Deepwater high-precision anti-rotating inverted measuring device
CN103968813B (en) * 2014-04-25 2017-01-18 中交第二航务工程局有限公司 Deepwater high-precision anti-rotating inverted measuring device
CN113607125A (en) * 2021-08-04 2021-11-05 中国电建集团昆明勘测设计研究院有限公司 Monitoring system for monitoring tension of inverted plumb measuring line and using method
CN113607125B (en) * 2021-08-04 2023-06-09 中国电建集团昆明勘测设计研究院有限公司 Monitoring system for monitoring tension of inverted vertical line and using method
CN114737549A (en) * 2021-09-08 2022-07-12 华能澜沧江水电股份有限公司 Hydraulic ship elevator tower and vertical shaft steel lining pipe group integrated construction method

Similar Documents

Publication Publication Date Title
CN201688844U (en) Inverted vertical device for providing vertical reference for construction of high-rise building
CN101736698B (en) Accurate positioning method for cable-stayed bridge pylon cable guide pipe
CN102490003B (en) Method for installing telescopic full-rotating rudder propeller device
CN102433880A (en) Simply-support guide frame of sinking steel protecting barrel and construction method for sinking steel protecting barrel
CN202119434U (en) Positioning device for cableway pipe of cable-stayed bridge
CN202881856U (en) Concrete pouring support prepressing device
CN103087731B (en) A kind of Laser measurement installation method of coke dry quenching furnace furnace shell
JP2009057713A (en) Wind power generation hybrid tower, and its construction method
CN102493471B (en) Suspending installation construction process method of structural foot margin anchor bolt
CN106436576A (en) Constructing method of main tower of cable-stayed bridge through circumferential prestressing force
CN105339654A (en) Wind turbine foundation
CN201850511U (en) Rapid stay cable sleeve lofting positioner
CN201560398U (en) Inner steel mould for accurately positioning tower column cable sleeves of cable-stayed bridge
CN204112222U (en) The bracing or strutting arrangement of main rope of suspension bridge anchoring prestress pipeline
CN202866304U (en) Reverse-building-method steel pipe column bottom locating device
CN204455847U (en) The marine positioning guiding device of the prefabricated pier of large-tonnage
CN102505864A (en) Method for assembling fixed ends of scaffold of large-volume triangular variable-section tubular truss structure
US9115700B2 (en) Foundation for wind turbine
CN103334380B (en) The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod
CN112112186B (en) Installation method of split jacket foundation on offshore converter station
CN204780899U (en) Anchor rope centering support device
CN203569558U (en) Bored pile reinforcement cage locating device
CN209923971U (en) Suspension connecting device for steel pipe column and steel reinforcement cage in reverse construction
CN210712562U (en) Tower crane system for construction of cast-in-situ tower column of cable-stayed bridge
CN202047528U (en) Concrete protection layer thickness controller

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101229

Termination date: 20190506