CN201686953U - Novel wall fence used for road - Google Patents

Novel wall fence used for road Download PDF

Info

Publication number
CN201686953U
CN201686953U CN2010202130261U CN201020213026U CN201686953U CN 201686953 U CN201686953 U CN 201686953U CN 2010202130261 U CN2010202130261 U CN 2010202130261U CN 201020213026 U CN201020213026 U CN 201020213026U CN 201686953 U CN201686953 U CN 201686953U
Authority
CN
China
Prior art keywords
cast
prefabricated
layer
fence
novel wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202130261U
Other languages
Chinese (zh)
Inventor
王思海
唐重光
吕维前
刘国忠
汪润新
陈辉龙
杨宏永
邢天民
战寿德
李文克
吴伟
王艺
任鹏
张勇
袁业帅
张金辉
李帅
王闯
屈涵
刘书鹏
柴鹏
孙华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Highway Engineering Group Co Ltd
Original Assignee
Henan Highway Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Highway Engineering Group Co Ltd filed Critical Henan Highway Engineering Group Co Ltd
Priority to CN2010202130261U priority Critical patent/CN201686953U/en
Application granted granted Critical
Publication of CN201686953U publication Critical patent/CN201686953U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a novel wall fence used for a road, which comprises an inside prefabricated layer and an outside cast-in-place layer that are solidified together, wherein the outside cast-in-place layer is formed by the cast-in-place of a framework of steel reinforcement and concrete; the inside prefabricated layer is formed by arranging prefabricated blocks side by side; and carbomer is filled in the gas between the adjacent prefabricated blocks. The novel wall fence is made by the method of combining a prefabricated fence panel and the cast-in-place and has high strength, attractive shaping and high fineness; in addition, a vibrating table is prefabricated, thereby avoiding the honeycomb and the pitted surface, reducing the porosity of the cast-in-place concrete and improving the grade strength and the compactedness of fence, so as to effectively prolong the service life of the fence and lower the maintenance cost at the later stage.

Description

Novel wall fence for highway
One. technical field: the utility model relates to a kind of highway barrier, particularly relates to a kind of novel wall fence for highway.
Two. background technology: along with the development of economic technology, China Higher level highway is more and more, various forms of bridges are also more and more, in order to adapt to expressway safety, requirement economic, practical, attractive in appearance, on highway and bridge, all design guardrail during design, the guardrail that has is the railing type waveform configuration, is made of column and horizontal Crashworthy plate, generally is used in the roadbed range section; Another guardrail is a wall type structure, and cast-in-site forms, and generally is used in bridge construction beyond the region of objective existence side.But, corrugated guardrail only is used in the roadbed range section at present, be used in the requirement that to satisfy security performance on the works, and the cast-in-site wall fence security performance of bridge construction beyond the region of objective existence side is low, road not attractive in appearance scape is inharmonious, speed of application slow, later maintenance expense height.
Three. the content of utility model:
Technical problem to be solved in the utility model is: overcome the deficiencies in the prior art, provide a kind of novel in design unique, intensity is high, safety good and the novel wall fence for highway of long service life.
The utility model is that the technical scheme that the technical solution problem is taked is:
A kind of novel wall fence for highway contains inboard preformed layer and outside cast in situs layer, and described inboard preformed layer is set in outside cast in situs layer, and described outside LIFT is formed by cage of reinforcement and concrete cast in situs.
Described inboard preformed layer is arranged side by side by prefabricated section and forms.
Be filled with macromolecule glue in the slit between the adjacent described prefabricated section.
The beneficial effects of the utility model are:
1, the utility model is made by the method that prefabricated guardrail panel and cast-in-site combine, have the intensity height, moulding is attractive in appearance, highly polished, adopt vibroplatform prefabricated in addition, avoid honeycomb, pitted skin, reduced the concrete pore rate of cast-in-site, improved the grade strength and the compactness of guardrail, thereby effectively improve the application life of guardrail, reduce later stage maintenance cost.
2, the utility model prefabricated section and cage of reinforcement are all made according to designing requirement in the processing space unification, and be transported to the job site then and carry out assembly unit, the construction of batch production production line, its high efficiency, cost of manufacture is low.
3, the utility model integrates numerous advantages such as short construction period, cost be low, is applicable to the making of multiple highway and Bridge guardrail, has good economic benefit after the popularization.
Four. description of drawings:
Fig. 1 is the structural representation of novel wall fence for highway.
Five. the specific embodiment:
Embodiment: referring to Fig. 1, among the figure, the inboard preformed layer 1 of novel wall fence for highway is set in outside cast in situs layer 2, and outside LIFT 2 is formed by cage of reinforcement 3 and concrete cast in situs.
Inboard preformed layer 1 is arranged side by side by a plurality of prefabricated sections and forms.And, be filled with macromolecule glue (not drawing among the figure) in the slit between contiguous prefabricated.
Its making step is:
A, site operation setting-out: according to construction design drawing, go out the inside and outside sideline of guardrail with total powerstation accurate setting-out on bridge hollow board, and along absolute altitude control point of the every 4-5 rice layout of inner edge, measure the elevation at each absolute altitude control point with level gauge, guarantee that the height of guardrail meets design requirement;
The installation of b, cage of reinforcement: according to the inner edge of the guardrail of site operation setting-out and the thickness of prefabricated section, on hollowcore slab, indicate the inner edge of cage of reinforcement with the line of ink marker, at a guardrail reinforcing bar of distance guardrail outer edge design protection layer thickness place with the outside control line of a line of ink marker as cage of reinforcement, the guardrail reinforcing bar is processed into semiproduct in the unification of reinforcing bar processing space according to code requirement, is transported to connect weldering with the prestressed cored slab reserved steel bar behind the job site and make type;
C, leveling layer is set: with the M12.5 mortar the wide leveling layer of 5cm is set along the guardrail inner edge on the hollowcore slab top;
D, prefabricated section and outboard template are installed: prefabricated section is in the unified processing of prefabricated processing space, be transported to the job site with transport vehicle, guardrail inner edge according to the site operation setting-out is provided with control line with cotton rope with the absolute altitude control point on the cage of reinforcement of guardrail upper end, with the elevation and the line style of this control line control prefabricated section; After the leveling layer mortar reaches certain intensity, by outside vertical columns and the outside horizontal support bar supporting outboard template is installed, with crane prefabricated section is lifted on the leveling layer then, after prefabricated section is just flat, install and fix the inboard vertical columns and the inboard horizontal support bar of prefabricated section, and prefabricated section and outboard template are closely connected into an integral body by the twice drag link of inboard vertical columns top and bottom, prefabricated section and outboard template are carried out essence put down by adjusting the drag link that is connected with inboard vertical columns and diagonal member;
E, concreting: at first water is moistening with hollowcore slab top and prefabricated section, use the bucket special of making according to guardrail width suitable for reading that the guardrail concrete is discharged in the guardrail template then, the guardrail concrete is built moulding at twice, for shortening the time interval of two-step pouring, each cover equipment that vibrates of front and back is constructed continuously;
F, health: after finishing, concreting in time covers with geotextiles, and the health of after concrete final set, sprinkling water;
G, piece are handled: after treating that the guardrail concrete reaches the intensity of design and code requirement, carry out the prefabricated section piece and handle.At first the cement mortar in the piece is rejected, with pencil and ruler the not straight suitable part of piece is marked then, subsequently according to the pencil line that indicates, with the small-size concrete cutting machine the not straight suitable part of piece is repaired, guarantee that piece is directly suitable up and down, seam is wide evenly, size is consistent, clog piece with macromolecule glue at last.
The above, it only is preferred embodiment of the present utility model, be not that the utility model is done any pro forma restriction, every foundation technical spirit of the present utility model all still belongs in the scope of technical solutions of the utility model any simple modification, equivalent variations and modification that above embodiment did.

Claims (3)

1. a novel wall fence for highway contains inboard preformed layer and outside cast in situs layer, and it is characterized in that: described inboard preformed layer is set in outside cast in situs layer, and described outside LIFT is formed by cage of reinforcement and concrete cast in situs.
2. novel wall fence for highway according to claim 1 is characterized in that: described inboard preformed layer is arranged side by side by prefabricated section and forms.
3. novel wall fence for highway according to claim 2 is characterized in that: be filled with macromolecule glue in the slit between the adjacent described prefabricated section.
CN2010202130261U 2010-06-03 2010-06-03 Novel wall fence used for road Expired - Lifetime CN201686953U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202130261U CN201686953U (en) 2010-06-03 2010-06-03 Novel wall fence used for road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202130261U CN201686953U (en) 2010-06-03 2010-06-03 Novel wall fence used for road

Publications (1)

Publication Number Publication Date
CN201686953U true CN201686953U (en) 2010-12-29

Family

ID=43375238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202130261U Expired - Lifetime CN201686953U (en) 2010-06-03 2010-06-03 Novel wall fence used for road

Country Status (1)

Country Link
CN (1) CN201686953U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493340A (en) * 2011-12-19 2012-06-13 中国一冶集团有限公司 External mounting type anti-collision guardrails for landscape bridge
CN102493350A (en) * 2011-12-19 2012-06-13 中国一冶集团有限公司 Construction method of landscape bridge outside-hanging crash barrier
CN103061267A (en) * 2013-01-15 2013-04-24 广州市市政工程设计研究院 Construction method of combined prefabricated bridge anti-collision wall
CN107587422A (en) * 2016-07-07 2018-01-16 上海公路桥梁(集团)有限公司 Precast splice type anti-collision wall and its manufacture method
CN111472303A (en) * 2018-12-07 2020-07-31 杭州江润科技有限公司 Middle pier anti-collision system and construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102493340A (en) * 2011-12-19 2012-06-13 中国一冶集团有限公司 External mounting type anti-collision guardrails for landscape bridge
CN102493350A (en) * 2011-12-19 2012-06-13 中国一冶集团有限公司 Construction method of landscape bridge outside-hanging crash barrier
CN103061267A (en) * 2013-01-15 2013-04-24 广州市市政工程设计研究院 Construction method of combined prefabricated bridge anti-collision wall
CN107587422A (en) * 2016-07-07 2018-01-16 上海公路桥梁(集团)有限公司 Precast splice type anti-collision wall and its manufacture method
CN111472303A (en) * 2018-12-07 2020-07-31 杭州江润科技有限公司 Middle pier anti-collision system and construction method
CN111472303B (en) * 2018-12-07 2021-08-20 杭州江润科技有限公司 Middle pier anti-collision system and construction method

Similar Documents

Publication Publication Date Title
CN101864744B (en) Construction method of novel wall fence for highway
CN206070562U (en) Subassembly formula underground structure
CN201686953U (en) Novel wall fence used for road
CN101487332A (en) Prefabricated hollow superposed beam, and cast-in-situ construction method for beam and precast slab
CN104963289A (en) Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud
CN201395769Y (en) Tie bar arch type bracket used for building bridge pylon concrete upper cross beam
CN103981803B (en) The combined gate pier of precast assembly and construction method thereof
CN202000251U (en) Cylindrical hollow prefabricated prestressed concrete pier structure
CN106976157A (en) A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape
CN203174510U (en) Movable assembly type hanging basket for bridge anti-collision guardrail construction and formwork for construction
CN204510650U (en) A kind of precast splice type stringer type stairway
CN101148862A (en) Pier body cap cracking body outside stress reinforcing method
CN204266136U (en) Stone arch bridge cover arch rib shotcrete ruggedized construction
CN102071740A (en) Long-span prestressed concrete slab small pre-frame structure and construction method thereof
CN103556564B (en) A kind of assembled slab bridge based on the connection of steel diaphragm plate and construction method thereof
CN201908380U (en) Small simulation framework structure of large-span prestressed concrete beam plate
CN202989755U (en) Integral-casting and fabricated prestressing force bridge structure
CN104032741B (en) The rapid constructing method of a kind of hydraulic engineering large volume temperature control
CN203593973U (en) Continuous beam long cast-in-site section bracket balancing method construction device
CN203393880U (en) Enhanced type reinforced concrete laminated floor slab
CN205591349U (en) Strong prestressing tendons's precast concrete beam post node in adoption
CN205382505U (en) Board -like concrete air cooling platform basis of rib is erected in area
CN209854576U (en) Trolley for construction of cover plate culvert or channel
CN203878460U (en) Prefabricated assembly combined type portal pier
CN104294762B (en) The synchronous crossings on different level construction method of camber

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20101229

CX01 Expiry of patent term