CN201678997U CN2010201617044U CN201020161704U CN201678997U CN 201678997 U CN201678997 U CN 201678997U CN 2010201617044 U CN2010201617044 U CN 2010201617044U CN 201020161704 U CN201020161704 U CN 201020161704U CN 201678997 U CN201678997 U CN 201678997U
Authority
CN
China
Prior art keywords
pile
ring
underreamer
tool
compaction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201617044U
Other languages
English (en)
Inventor
骆军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GANSU CONSTRUCTION INVESTEMENT (HOLDING) GROUP CO Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010201617044U priority Critical patent/CN201678997U/zh
Application granted granted Critical
Publication of CN201678997U publication Critical patent/CN201678997U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型涉及建筑施工领域,具体为一种封闭式挤密桩扩孔器。其是由导向环、扩孔环、导向通气槽、工具桩、翼突组成,其特征在于:导向环与扩孔环通过焊接连接,安装在工具桩前段,受翼突的限制,可在一定范围内上下活动,与工具桩形成一个整体。在打桩时,随工具桩一同打入地基土中,挤密周边土体,提高地基承载力。拔桩时,由于受桩孔摩擦力作用,工具桩先于挤密桩扩孔器离开桩底,此时空气可于导向通气槽的间隙进入桩底,避免了桩孔出现真空状态而造成拔桩困难;当翼突上缘与其导向通气槽上缘接触后,受到拔桩力,挤密桩扩孔器与工具桩一同拔出桩孔,完成成孔施工。本实用新型可有效减少挤密桩成孔过程中的塌落土。

Description

一种封闭式挤密桩扩孔器
技术领域
本实用新型涉及工程机具,具体为一种封闭式挤密桩扩孔器。
技术背景
基础处理工程,挤密桩施工是地基处理的常用方法,在施工过程中,挤密桩孔成孔深度是挤密桩质量控制的重要指标,为了达到该指标,在施工中一般采取超打的方法,即在沉管施工时超过设计的桩长,如设计桩长为10米,沉管时则打至11米,工具桩拔出,孔壁土塌落后,成孔深度达到设计桩长要求。这种施工方法由于塌落土过多,造成成孔深度不够,留下了很大的隐患。塌落土厚度过大,夯实机便夯不实,虽然在设计桩长范围内质量达到要求,但在该桩下部留下了一段虚土。
目前常用的挤密桩桩架最高为23米,杆式柴油打桩锤长5米,还要留最少1米的活动距离,工具桩最长可达17米(不算桩尖)。17米的工具桩,打入深度一般为16.7米左右,在正常地质条件下,拔桩后一般为15.5米左右,虚土深度约1.2米。如果,再往上接桩架,则机械的稳定性将无法保证,有可能面临倾覆的危险。
发明内容
本实用新型涉及一种封闭式挤密桩扩孔器,其目的是为了充分发挥设备的能力,减少挤密桩成孔过程中的塌落土问题,与原有工具桩联合使用,随工具桩一同打入地基土中,挤密周边土体,提高地基承载力。
一种封闭式挤密桩扩孔器是由导向环1、扩孔环2、导向通气槽3、工具桩4、翼突5组成,其特征在于:导向环1与扩孔环2通过焊接连接,安装在工具桩4 前段,受翼突5的限制,可在一定范围内上下活动,与工具桩4形成一个整体。所述导向环1内径大于工具桩4,下口部为30°的直立刃口,外径与扩孔环2外径相同,形成一个上小下大的圆台环,并开有8个导向通气槽3,与工具桩4上的翼突5相吻合,起到导向和通气的作用。打桩时,随工具桩4一同打入地基土中,挤密周边土体,提高地基承载力。拔桩时,由于受桩孔摩擦力作用,工具桩4先于挤密桩扩孔器离开桩底,此时空气可于导向通气槽3的间隙进入桩底,避免了桩孔出现真空状态而造成拔桩困难;当翼突5上缘与其导向通气槽3上缘接触后,受到拔桩力,挤密桩扩孔器与工具桩4一同拔出桩孔,完成挤密桩的成孔施工。
本实用新型的有益效果是可有效的避免将桩壁土刮入桩底,达到挤密桩打入多长,拔出后有效孔就多长,在施工中减少了“挂环”这一施工环节,减轻了工人的劳动强度。并且充分发挥了现有设备的处理能力,可突破目前挤密桩处理深度15米这一极限数值。
附图说明
如图所示:一种封闭式挤密桩扩孔器由导向环1、扩孔环2、导向通气槽3、工具桩4、翼突5组成;
图1是一种封闭式挤密桩扩孔器立面图。
图2是一种封闭式挤密桩扩孔器工具桩的立面图。
图3是一种封闭式挤密桩扩孔器安装后打桩时及停桩时的状态参考图。
图4是一种封闭式挤密桩扩孔器安装后拔桩时的状态参考图。
图5是一种封闭式挤密桩扩孔器施工时工具桩及扩孔器的三种状态示意图:
(1)是打桩时及停桩时的状态;
(2)是工具桩拔起时的状态,空气可从导向通气槽中进入孔底;
(3)是工具桩拔起后,扩孔器与工具桩一同拔起的状态。
具体实施方式
一种挤密桩扩孔器是由导向环1、扩孔环2、导向通气槽3、工具桩4、翼突5组成,其特征在于:导向环1与扩孔环2通过焊接连接,安装在工具桩4前段,受翼突5的限制,可在一定范围内上下活动,与工具桩4形成一个整体。所述导向环1内径大于工具桩4,下口部为30°的直立刃口,外径与扩孔环2外径相同,形成一个上小下大的圆台环,并开有8个导向通气槽3,与工具桩4上的翼突5相吻合,起到导向和通气的作用。打桩时,随工具桩4一同打入地基土中,挤密周边土体,提高地基承载力。拔桩时,由于受桩孔摩擦力作用,工具桩4先于挤密桩扩孔器离开桩底,此时空气可于导向通气槽3的间隙进入桩底,避免了桩孔出现真空状态而造成拔桩困难;当翼突5上缘与其导向通气槽3上缘接触后,受到拔桩力,挤密桩扩孔器与工具桩4一同拔出桩孔,完成挤密桩的成孔施工。
工作时的三种状态,如图5所示:(1)是打桩时及停桩时的状态;(2)是工具桩拔起时的状态,空气可从导向通气槽中进入孔底,避免出现真空现象,使桩管易于拔起;(3)是工具桩拔起后,扩孔器与工具桩一同拔起,扩孔器与桩壁整体接触,避免了刮擦,再次将桩壁土挤密。

Claims (2)

1.一种封闭式挤密桩扩孔器由导向环(1)、扩孔环(2)、导向通气槽(3)、工具桩(4)、翼突(5)组成,其特征在于:导向环(1)与扩孔环(2)通过焊接连接,安装在工具桩(4)前段,受翼突(5)的限制,可在一定范围内上下活动,与工具桩(4)形成一个整体。
2.根据权利要求1所述的一种封闭式挤密桩扩孔器,其特征在于:导向环(1)内径大于工具桩(4),下口部为30°的直立刃口,外径与扩孔环(2)外径相同,形成一个上小下大的圆台环,并开有8个导向通气槽(3),与工具桩(4)上的翼突(5)相吻合。 
CN2010201617044U 2010-04-15 2010-04-15 一种封闭式挤密桩扩孔器 Expired - Fee Related CN201678997U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201617044U CN201678997U (zh) 2010-04-15 2010-04-15 一种封闭式挤密桩扩孔器

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201617044U CN201678997U (zh) 2010-04-15 2010-04-15 一种封闭式挤密桩扩孔器

Publications (1)

Publication Number Publication Date
CN201678997U true CN201678997U (zh) 2010-12-22

Family

ID=43344048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201617044U Expired - Fee Related CN201678997U (zh) 2010-04-15 2010-04-15 一种封闭式挤密桩扩孔器

Country Status (1)

Country Link
CN (1) CN201678997U (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727308A (zh) * 2015-02-12 2015-06-24 刘清洁 一种施工沉管挤密桩或混凝土灌注桩的设备及施工方法
CN113668497A (zh) * 2021-09-01 2021-11-19 陕西龙海新创基础工程有限公司 一种超长沉管挤密桩的施工装置及方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727308A (zh) * 2015-02-12 2015-06-24 刘清洁 一种施工沉管挤密桩或混凝土灌注桩的设备及施工方法
CN113668497A (zh) * 2021-09-01 2021-11-19 陕西龙海新创基础工程有限公司 一种超长沉管挤密桩的施工装置及方法

Similar Documents

Publication Publication Date Title
CN106013151A (zh) 一种连续桩墙施工方法及其所用的施工装置
CN106149684A (zh) 一种全套管长螺旋钻孔灌注桩施工方法
CN204199335U (zh) 一种减小phc管桩施工挤土效应的泄压井
CN101886390A (zh) 狭小空间全套管静压拔桩技术
CN201770981U (zh) 一种随钻跟管桩的桩侧注浆装置
CN102108706A (zh) 预应力管桩桩芯补强简易手动螺旋取土装置
CN105421445A (zh) 非预应力离心高强混凝土桩植桩施工方法
CN201678997U (zh) 一种封闭式挤密桩扩孔器
CN108978635A (zh) 一种同步注浆钢板桩及使用方法
US11773555B2 (en) Methods and apparatuses for compacting soil and granular materials
CN103741690B (zh) 一种土塞补偿管桩拔出施工方法及其所用的土塞补偿管桩拔桩装置
CN110258504B (zh) 一种利用内置夯锤进行底部夯击的沉管挤密桩施工工艺
CN207047834U (zh) 一种空心预制桩的施工系统
CN109027419A (zh) 一种手掘式顶管施工方法
CN108867643A (zh) 超长桩基混凝土护筒拔出方法
CN210439338U (zh) 钻孔灌注桩混凝土浇灌高度检测装置
CN210598826U (zh) 扩底灌注基桩机械成桩装置
CN212052771U (zh) 一种快速清理预制管桩桩芯填土装置
CN110206012B (zh) 一种可连接式螺旋板深层强夯装置及施工方法
CN208563419U (zh) 一种套挖装置
CN111778969A (zh) 双套管式全回转超长桩施工工具及施工工法
CN209243711U (zh) 一种挤密螺纹大直径筒桩及其成桩装置
CN2354994Y (zh) 沉管灌注混凝土桩的施工用取土器
CN202117569U (zh) 钻头
CN114164824B (zh) 一种对周边地层微扰动的长钢护筒灌注桩及应用

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GANSU PROVINCIAL CONSTRUCTION INVESTMENT (HOLDINGS

Free format text: FORMER OWNER: LUO JUN

Effective date: 20110517

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 730000 ROOM 304, EAST, NO. 39, JING ER STREET, CHENGGUAN DISTRICT, LANZHOU CITY, GANSU PROVINCE TO: 730050 NO. 575, XIJIN EAST ROAD, QILIHE DISTRICT, LANZHOU CITY, GANSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110517

Address after: Qilihe District of Gansu city in Lanzhou Province, 730050 West East Road No. 575

Patentee after: Gansu Construction Investement (Holding) Group Co.,Ltd.

Address before: 730000, room 304, East 39, Jing Tong Street, Chengguan District, Gansu, Lanzhou

Patentee before: Luo Jun

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101222

Termination date: 20140415