- CN201649616U CN201649616U CN2010201168187U CN201020116818U CN201649616U CN 201649616 U CN201649616 U CN 201649616U CN 2010201168187 U CN2010201168187 U CN 2010201168187U CN 201020116818 U CN201020116818 U CN 201020116818U CN 201649616 U CN201649616 U CN 201649616U
- Authority
- CN
- China
- Prior art keywords
- scaffold
- building
- connecting tube
- connecting piece
- rigid connecting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model relates to the building construction technology field, in particular to a rigid connecting tube of a scaffold and a building suitable for low-storied and high-storied industry and civil building construction. The rigid connecting tube comprises an embedded part vertically fixed on a building edge beam; and the embedded part is fixedly connected with the scaffold through a horizontal connecting piece. The rigid connecting tube is pulled by the scaffold outwards when in use, and at the moment, the embedded part is solidified by the building edge beam, so that the scaffold can be prevented from transverse deformation as well as larger inward or outward deformation caused by wind load and also can improve the bearing force as a middle constraint part of a frame body, thereby ensuring the monolithic stability of the scaffold.
Description
Technical field
The utility model relates to technical field of building construction, is specially to be applicable to low layer, high-rise industry and the scaffold of civilian construction construction use and the rigidity wall-connecting piece of building.
Background technology
Wall-connecting piece is meant the member that connects scaffold and building, is the important component part of scaffold.Both at home and abroad the scaffold collapse accident that takes place occurs repeatedly, and substantially all is because wall-connecting piece is fixing insecure with outer body of wall, after deficiency or wall-connecting piece are set are removed in time benefit establish and cause, so must attract great attention and guarantee that it is provided with effectively.
External scaffolding is most important to the safety of external scaffolding with the quality of outer body of wall anchoring, the way of custom is with the direct crosswise fixed of steel pipe outside the building on the body of wall, the steel pipe other end fixes with fastener and scaffold upright rod, the bearing of steel pipe and exterior wall is after being subjected to lateral pull for a long time, fixedly being easy to generate of itself and body of wall is loosening, horizontal destabilization problems occurs, can cause scaffold integral body to be toppled when serious.
The utility model content
The utility model has solved the problem that is rigidly connected of scaffold and building, the rigidity wall-connecting piece of a kind of scaffold and building is provided, it can bear pulling force and pressure effect, certain bending resistance and anti-twisting property are arranged again, it can resist scaffold on the one hand with respect to falling in the body of wall and outer distortion, simultaneously also certain effect of contraction can be arranged, thereby improve the anti-unstability ability of scaffold, reach the reliable purpose of connecting of scaffold and building the buckling deformation of vertical rod.
In order to solve the problems of the technologies described above, the utility model is achieved through the following technical solutions:
The rigidity wall-connecting piece of a kind of scaffold and building comprises the built-in fitting of vertical fixing on the building side bar, and above-mentioned built-in fitting is fixedlyed connected with scaffold by a horizontal connector.
Further, described connector is fixedlyed connected with the vertical rod of above-mentioned scaffold.
Further, fixedly connected between described built-in fitting, connector and the scaffold upright rod by fastener.
Further, described built-in fitting and connector are steel pipe.
Compared with prior art, the beneficial effects of the utility model are:
1, rigidity wall-connecting piece described in the utility model is subjected to the outside pulling force of scaffold in use, this moment, built-in fitting was subjected to the consolidation force that the building side bar gives, can effectively prevent the scaffold lateral deformation, prevent to take place inwardly big or outwards distortion because of wind load, can be used as the middle constraint of support body simultaneously, improve bearing capacity, ensure the monolithic stability of scaffold.
2, above-mentioned rigidity wall-connecting piece is simple in structure, and power transmission is reasonable, and is safe and reliable, and convenient and quick construction can obtain remarkable economic efficiency and social benefit.
Description of drawings
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
Fig. 1 is the utility model structural representation.
The specific embodiment
As shown in Figure 1, the rigidity wall-connecting piece of scaffold described in the utility model and building, comprise the built-in fitting 2 of vertical fixing on building side bar 1, built-in fitting 2 is fixedlyed connected with scaffold upright rod 4 by a horizontal connector 3, in the present embodiment, built-in fitting 2 and connector 3 are steel pipe, and be fixedly connected by fastener 5 between built-in fitting 2, connector 3 and the scaffold upright rod 4.
Construction process of the present utility model is: after each floor face beam reinforced steel bar colligation is installed and checked and accepted, (be embedded in 300mm in the beam at building side bar 1 pre-buried built-in fitting 2, expose beam face 300mm) and fixing, beam slab concrete pouring construction then, after treating that concrete reaches certain intensity, fixedly connected with scaffold upright rod 4 by connector 3, fastener 5, form rigidity anchoring wall-connecting piece, along with rising, structure up installs, untie fastener 5 during dismounting, with cutting machine built-in fitting 2 is exposed at the outer part of building side bar 1 and cuts away and get final product.
The utility model is not limited to above-mentioned embodiment, if various changes of the present utility model or distortion are not broken away from spirit and scope of the present utility model, if these changes and distortion belong within claim of the present utility model and the equivalent technologies scope, then the utility model also is intended to comprise these changes and distortion.
Claims (4)
1. the rigidity wall-connecting piece of scaffold and building, it is characterized in that: comprise the built-in fitting of vertical fixing on the building side bar, above-mentioned built-in fitting is fixedlyed connected with scaffold by a horizontal connector.
2. the rigidity wall-connecting piece of scaffold according to claim 1 and building is characterized in that: described connector is fixedlyed connected with the vertical rod of above-mentioned scaffold.
3. the rigidity wall-connecting piece of scaffold according to claim 2 and building is characterized in that: fixedly connected by fastener between described built-in fitting, connector and the scaffold upright rod.
4. according to the rigidity wall-connecting piece of each described scaffold of claim 1 to 3 and building, it is characterized in that: described built-in fitting and connector are steel pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010201168187U CN201649616U (en) | 2010-02-09 | 2010-02-09 | Rigid connecting tube of scaffold and building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010201168187U CN201649616U (en) | 2010-02-09 | 2010-02-09 | Rigid connecting tube of scaffold and building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201649616U true CN201649616U (en) | 2010-11-24 |
Family
ID=43114845
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010201168187U Expired - Lifetime CN201649616U (en) | 2010-02-09 | 2010-02-09 | Rigid connecting tube of scaffold and building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201649616U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312563A (en) * | 2011-06-16 | 2012-01-11 | 永升建设集团有限公司 | Method for connecting external scaffold with wall for large-span and ultra-story-height structures |
CN106368427A (en) * | 2015-07-23 | 2017-02-01 | 华北冶建工程建设有限公司 | Binding and unloading construction method for scaffold |
-
2010
- 2010-02-09 CN CN2010201168187U patent/CN201649616U/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102312563A (en) * | 2011-06-16 | 2012-01-11 | 永升建设集团有限公司 | Method for connecting external scaffold with wall for large-span and ultra-story-height structures |
CN106368427A (en) * | 2015-07-23 | 2017-02-01 | 华北冶建工程建设有限公司 | Binding and unloading construction method for scaffold |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202577934U (en) | Screw thread wall-connection member of scaffold and building | |
CN201902010U (en) | Instrumental overhanging scaffold hoop | |
CN103291066B (en) | A kind of construction elevator wall-attached frame servicing unit reinforcement means | |
CN202324616U (en) | Triangular steel truss supporting formwork system with high-altitude big-overhanging structure | |
CN204299145U (en) | For the operating platform that external climbing tower crane support frame is installed | |
CN101806107A (en) | Side column connecting node of thin steel plate shear wall | |
CN201649616U (en) | Rigid connecting tube of scaffold and building | |
CN204675672U (en) | A kind of spliced tower crane service platform | |
CN204199667U (en) | Detachable builder's jack corner tripod | |
CN203654710U (en) | Instrumental connecting tube for external wall scaffold shearing wall portion | |
CN103046743B (en) | A kind of Super High conversion layer steel reinforced concrete crossbeam suspension type form bracing system and construction method | |
CN202090577U (en) | Template supporting construction platform for lift wells in high-rise buildings | |
CN204343642U (en) | Builder's jack corner support frame | |
CN202969897U (en) | Ringlock type scaffold joist system | |
CN202990407U (en) | Quick-release scaffold | |
CN205314539U (en) | Large -scale cantilever type combination steel form | |
CN201635214U (en) | Side column connecting node of sheet steel shear wall | |
CN204343647U (en) | A kind of the shaped steel suspension scaffolding bracing frame | |
CN201460200U (en) | Combined steel formwork | |
CN203271105U (en) | Auxiliary device of building hoist wall attaching frame | |
CN203022327U (en) | Elevator shaft high-altitude construction platform device | |
CN203257075U (en) | Core tube inner lifting type multifunctional operating platform for high-rise building construction | |
CN203547114U (en) | Wall connecting assembly | |
CN207092546U (en) | A kind of subsiding crack both sides shear wall formwork for placing frame being easily installed | |
CN203452270U (en) | Steel reinforcement protective layer controlled horse-shaped stool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20101124 |
|
CX01 | Expiry of patent term |