CN201588301U - Steel corbel support structure on I-shaped concrete side - Google Patents

Steel corbel support structure on I-shaped concrete side Download PDF

Info

Publication number
CN201588301U
CN201588301U CN2009203184872U CN200920318487U CN201588301U CN 201588301 U CN201588301 U CN 201588301U CN 2009203184872 U CN2009203184872 U CN 2009203184872U CN 200920318487 U CN200920318487 U CN 200920318487U CN 201588301 U CN201588301 U CN 201588301U
Authority
CN
China
Prior art keywords
steel
column
steel corbel
corbel
fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009203184872U
Other languages
Chinese (zh)
Inventor
吴旻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2009203184872U priority Critical patent/CN201588301U/en
Application granted granted Critical
Publication of CN201588301U publication Critical patent/CN201588301U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a steel corbel support structure on the I-shaped concrete side, which structurally comprises an I column/beam (1), reinforcing blocks (2) arranged on both sides of the I column/beam (1), and steel pre-embedded parts arranged on the reinforcing blocks (2); and the steel pre-embedded parts are connected with the steel corbel. As the local I-shaped part of the I-shaped concrete column/beam is changed to be rectangle, the thickness of the concrete column/beam is increased, upper load bearing capacity of the steel corbel on the concrete column or steel is improved, the bearing capacity requirement is met, and the safety of the steel corbel support structure is ensured. The normal use of workshops is not affected during the strengthening construction process.

Description

A kind of steel corbel braced structures of I shape concrete side
Technical field
The utility model relates to a kind of steel corbel braced structures, particularly a kind of steel corbel structure of I shape concrete side.
Background technology
In the old factory rehabilitation engineering,, need install steel corbel additional in the concrete column one or both sides and bear upper load in order to bear the active force that newly adds steel platform or new oil (gas) filling device in the one or both sides of I shape concrete column/beam.Present way is a direct pre-buried steel built-in fitting in I-column/beam when teemer's font concrete column or beam, weldable steel bracket on the steel built-in fitting.Steel corbel is welded by two vertical gripper shoes dull and stereotyped and below it.Because the thinner thickness of I-column/beam mid portion, the steel corbel that newly adds can not satisfy the requirement of bearing capacity, and the dowel of steel built-in fitting is pulled out from I shape concrete column/beam, causes I shape concrete column/beam to damage.
The utility model content
The purpose of this utility model is, a kind of steel corbel braced structures of I shape concrete side is provided, and can prevent to cause when bearing capacity is excessive the damage of I shape concrete column/beam.
The technical solution of the utility model: a kind of steel corbel braced structures of I shape concrete side, formation comprises I-column/beam, and I-column/beam both sides are provided with boss, and boss is provided with the steel built-in fitting, and the steel built-in fitting is connected with steel corbel.
In the steel corbel braced structures of above-mentioned I shape concrete side, described I-column/beam is provided with one group of reinforced hole.
In the steel corbel braced structures of aforementioned I shape concrete side, described I-column/beam is provided with the steel bar framework that runs through reinforced hole.
In the steel corbel braced structures of aforementioned I shape concrete side, the boss of described I-column/beam both sides is the reinforced concrete structure that is wrapped in steel bar framework.
In the steel corbel braced structures of aforementioned I shape concrete side, described steel built-in fitting comprises and connects steel plate and be located at the dowel that is connected on the steel plate.
In the steel corbel braced structures of aforementioned I shape concrete side, described steel corbel comprises flat board and is located at the gripper shoe of dull and stereotyped below.
Compared with prior art, the utility model is transformed into rectangle with the part of I shape concrete column/beam by I shape, has increased the thickness of concrete column/beam, can improve the ability that steel corbel bears upper load on concrete column or the beam, satisfy the requirement of bearing capacity, guaranteed the safety of structure.And do not influence the normal use of factory building in the process of construction reinforcement.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is a schematic appearance;
Fig. 3 is the structural representation of I-column/beam;
Fig. 4 is the structural representation of steel bar framework;
Fig. 5 is the prior art constructions schematic diagram.
Being labeled as in the accompanying drawing: 1-I-column/beam, the 2-boss, the 3-reinforced hole, the 4-steel bar framework, 5-connects steel plate, 6-dowel, 7-flat board, 8-gripper shoe.
The specific embodiment
The utility model is described in further detail below in conjunction with drawings and Examples.
Embodiment.A kind of steel corbel braced structures of I shape concrete side, as shown in Figure 1.Fig. 2 is the schematic appearance after the assembling.Formation of the present utility model comprises I-column/beam 1, and I-column/beam 1 is provided with one group of reinforced hole 3 as shown in Figure 3.I-column/beam 1 is provided with the steel bar framework 4 (as shown in Figure 4) that runs through reinforced hole 3.I-column/beam 1 both sides are provided with boss 2, and boss 2 is the reinforced concrete structure that is wrapped in steel bar framework 4.Boss 2 is provided with the steel built-in fitting, and the steel built-in fitting comprises and connects steel plate 5 and be located at the dowel 6 that is connected on the steel plate 5.The steel built-in fitting is connected with steel corbel, and steel corbel comprises flat board 7 and is located at the gripper shoe 8 of dull and stereotyped 7 belows.
During concrete the construction, can on I-column/beam 1, beat some reinforced holes 3 as shown in Figure 3 with Churn drill earlier, be woven into as shown in Figure 4 steel bar framework 4 with reinforcing bar then, by root reinforcing bar is passed reinforced hole 3 on I-column/beam 1, the steel bar framework 4 of I-column/beam 1 both sides is connected as a single entity, and the steel bar framework 4 of both sides is preferably impartial.Make the mould of boss 2 in steel bar framework 4 outsides, the outside and the I-column/Liangping of mould are neat, the partial cross section that makes I-column/beam is a rectangle, use concrete casting boss 2 then, earlier the steel built-in fitting is placed in the diaphragm capsule before casting, during placement, the dowel 6 on the steel built-in fitting inserts in the diaphragm capsule of boss 2, connection steel plate 5 on the steel built-in fitting flushes with or slightly higher than the diaphragm capsule inwall with the diaphragm capsule inwall, its objective is for the ease of the weldable steel bracket.After the concrete setting to be cast, again steel corbel is welded on the connection steel plate 5 of steel built-in fitting.Steel corbel comprises that dull and stereotyped 7 and be located at the gripper shoe 8 of dull and stereotyped 7 belows, dull and stereotyped 7 weld together with the steel plate 5 that is connected of steel built-in fitting with the side of gripper shoe 8.For easy for installation, can on dull and stereotyped 7, bore some installing holes.Bracket after finishing as shown in Figure 2.
Fig. 5 is the prior art constructions schematic diagram, and as can be seen from Fig. 5, present way is a direct pre-buried steel built-in fitting in I-column/beam when teemer's font concrete column/beam 1, weldable steel bracket on the steel built-in fitting.Because the thinner thickness of I-column/beam mid portion, the steel corbel that newly adds can not satisfy the requirement of bearing capacity, and the dowel 6 of steel built-in fitting is pulled out from I shape concrete column/beam 1, causes I shape concrete column/beam to damage.

Claims (6)

1. the steel corbel braced structures of an I shape concrete side constitutes and comprises I-column/beam (1), and it is characterized in that: I-column/beam (1) both sides are provided with boss (2), and boss (2) is provided with the steel built-in fitting, and the steel built-in fitting is connected with steel corbel.
2. according to the steel corbel braced structures of the described I shape concrete of claim 1 side, it is characterized in that: described I-column/beam (1) is provided with one group of reinforced hole (3).
3. according to the steel corbel braced structures of the described I shape concrete of claim 2 side, it is characterized in that: described I-column/beam (1) is provided with the steel bar framework (4) that runs through reinforced hole (3).
4. according to the steel corbel braced structures of the described I shape concrete of claim 3 side, it is characterized in that: the boss (2) of described I-column/beam (1) both sides is the reinforced concrete structure that is wrapped in steel bar framework (4).
5. according to the steel corbel braced structures of the described I shape concrete of claim 4 side, it is characterized in that: described steel built-in fitting comprises and connects steel plate (5) and be located at the dowel (6) that is connected on the steel plate (5).
6. according to the steel corbel braced structures of the described I shape concrete of claim 5 side, it is characterized in that: described steel corbel comprises flat board (7) and is located at the gripper shoe (8) of flat board (7) below.
CN2009203184872U 2009-12-24 2009-12-24 Steel corbel support structure on I-shaped concrete side Expired - Fee Related CN201588301U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203184872U CN201588301U (en) 2009-12-24 2009-12-24 Steel corbel support structure on I-shaped concrete side

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203184872U CN201588301U (en) 2009-12-24 2009-12-24 Steel corbel support structure on I-shaped concrete side

Publications (1)

Publication Number Publication Date
CN201588301U true CN201588301U (en) 2010-09-22

Family

ID=42748074

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203184872U Expired - Fee Related CN201588301U (en) 2009-12-24 2009-12-24 Steel corbel support structure on I-shaped concrete side

Country Status (1)

Country Link
CN (1) CN201588301U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510618A (en) * 2013-10-24 2014-01-15 华煜建设集团有限公司 Cantilever beam support structure
CN106153443A (en) * 2016-08-19 2016-11-23 上海市政工程设计研究总院(集团)有限公司 A kind of loading counter weight device and loading method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510618A (en) * 2013-10-24 2014-01-15 华煜建设集团有限公司 Cantilever beam support structure
CN106153443A (en) * 2016-08-19 2016-11-23 上海市政工程设计研究总院(集团)有限公司 A kind of loading counter weight device and loading method thereof

Similar Documents

Publication Publication Date Title
CN101906754B (en) Rigid connection method for steel beam and concrete pier
CN201339250Y (en) Stiffness structure framework beam preformed steel reinforcement framework structure
CN201902010U (en) Instrumental overhanging scaffold hoop
CN204023411U (en) Novel assembled bracket bracket construction equipment
CN101487332A (en) Prefabricated hollow superposed beam, and cast-in-situ construction method for beam and precast slab
CN201588301U (en) Steel corbel support structure on I-shaped concrete side
CN105672568A (en) Stratified casting construction method of super-large-section stiffened concrete transfer beam
CN202007535U (en) Supporting reinforcing structure
CN102605799A (en) Connection structure and method of column feet and foundation of thermal power plant boiler
CN101831869A (en) Connecting structure of combined beam and concrete bearing cross beam
CN107165056B (en) Anti-overturning steel bar bracket for cantilever bent cap concrete pouring and mounting method thereof
CN212715350U (en) Section steel concrete beam column structure
CN203440828U (en) Assembled tower footing
CN202936807U (en) Assembled tower footing
CN210797296U (en) Steel-concrete combination beam bridge floor flange plate bracket mounting structure
CN205501843U (en) Consolidate rigid framed arch bridge
CN104047233A (en) Method for construction of continuous beam linear segment without floor stand
CN102995804A (en) Method for effectively reducing self-weight of prefabricated composite floor slab
CN105442457A (en) Construction structure and method for extending bridge floor plate bridge filled with fine sand
CN205712733U (en) Super-section strengthening concrete conversion beam formwork system
CN201144524Y (en) Reinforcement for detached wall stud
CN207419702U (en) The high-order single frame attaching structure of tower crane non-floor
CN102900096A (en) Fabricated tower footing
CN112814154A (en) Connection and manufacturing method of steel frame column and concrete column base
CN201381803Y (en) T-shaped base of beam pumper

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER OWNER: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

Effective date: 20110608

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 550004 NO. 208, BEIJING ROAD, GUIYANG CITY, GUIZHOU PROVINCE TO: 550081 NO.2, JINZHU ROAD, JINYANG NEW DISTRICT, GUIYANG CITY, GUIZHOU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110608

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100922

Termination date: 20141224