CN201569603U - Connecting clamp for geogrid field pull-out test - Google Patents

Connecting clamp for geogrid field pull-out test Download PDF

Info

Publication number
CN201569603U
CN201569603U CN200920082805XU CN200920082805U CN201569603U CN 201569603 U CN201569603 U CN 201569603U CN 200920082805X U CN200920082805X U CN 200920082805XU CN 200920082805 U CN200920082805 U CN 200920082805U CN 201569603 U CN201569603 U CN 201569603U
Authority
CN
China
Prior art keywords
pull
gsz
geogrid
out test
top board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN200920082805XU
Other languages
Chinese (zh)
Inventor
黄成楷
卢廷荣
周军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panzhihua nineteen smelting survey design & Research Institute Co Ltd
Original Assignee
MCC Shijiu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shijiu Construction Co Ltd filed Critical MCC Shijiu Construction Co Ltd
Priority to CN200920082805XU priority Critical patent/CN201569603U/en
Application granted granted Critical
Publication of CN201569603U publication Critical patent/CN201569603U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The utility model discloses a connecting clamp for a geogrid field pull-out test, which comprises a geogrid, a clamping device and a pull-out device, wherein the clamping device and the pull-out device are in disassemble connection with the geogrid; the clamping device comprises an upper pressing plate, a lower pressing plate and a base plate; the upper pressing plate, the lower pressing plate and the base plate are all uniformly provided with open holes along the length direction; the pull-out device comprises a transverse rod, a pull rod, a jack and a counterforce device; one end of the pull rod is fixed at the middle part of the transverse rod; the transverse rod is arranged inside the bending part formed after the geogrid is overturned and is vertical to the geogrid; the pull rod passes through the counterforce device; and the jack is sleeved outside the counterforce device on the pull rod. The connecting clamp for the geogrid field pull-out test increases the friction coefficient between the clamp and the geogrid, also does not cause damage to the surface of the geogrid, selects simple materials, does not has high requirement for precision and has convenient processing production. In the test process, the geogrid also does not generate slippage. The connecting clamp of the utility model is suitable for the construction field pull-out test.

Description

The on-the-spot pull-out test jockey of GSZ
Technical field
The utility model relates to the on-the-spot pull-out test jockey of GSZ.
Background technology
The muscle body material that is used for reinforced earth technology is broadly divided into two classes, and a class is the bigger rigid rib material of rigidity, and a class is the less flexible muscle material of rigidity, as various geotextiles and GSZ.Wherein GSZ is a kind of main geosynthetics, compares with other geosynthetics, has particular performances and effect.
After engineering site laying GSZ is finished, whether design parameters such as the friction factor between GSZ and the filler, cohesive strength, angle of internal friction reach requirement, need simulate pull-out test by engineering site, the value of thrust that obtains according to pull-out test, calculate above-mentioned design parameter value, verify the laying quality of GSZ with this.The principle of pull-out test is rubbing action, by applying normal stress, make between the GSZ and the soil body and combine closely, thereby utilize the stiction opposing external force on the cross section each other, one end of GSZ is exposed at soil body outside, apply horizontal pulling capacity and simulate the relative motion of the soil body and grid face, surrender, be pulled out or break up to grid.The purpose of pull-out test is the interfacial property of research soil and geosynthetics.
And current national codes does not still have clear and definite regulation just at the inspection parameter and the method for the quality of GSZ own to the method for inspection of engineering construction effect.For this reason, need design the GSZ anchor clamps that a cover satisfies the engineering site testing requirements.Because the GSZ such as the polypropylene GSZ smooth surface that have if the excessive grid surface that easily causes of clamping force is impaired, in the damaged part fracture, reduce the intensity of grid in the drawing process; If clamp power is too small, easily produce slippage in the drawing, influence normally carrying out of pull-out test.
The utility model content
The purpose of this utility model provides the on-the-spot pull-out test jockey of a kind of GSZ, can not cause damage to GSZ in drawing process, and GSZ can not produce slippage yet.
The technical scheme that the utility model adopted is:
The on-the-spot pull-out test jockey of GSZ comprises GSZ, also comprises clamp device and draw-off gear, and described clamp device and draw-off gear and GSZ removably connect.
Described clamp device comprises top board, lower platen and backing plate, and top board, lower platen and backing plate evenly are provided with perforate along its length.
Described top board, lower platen and backing plate along its length every meter to be provided with the perforate number be 4-6.
Described perforate is provided with the bolt that matches, and bolt is provided with the nut that matches.
Be provided with pad between described nut and top board or the lower platen.
Described top board, lower platen and backing plate are the hard plank.
Described draw-off gear comprises cross bar, pull bar, lifting jack and counterforce device, pull bar one end is fixed on the cross bar middle part, the sweep that cross bar places GSZ turnover back to form is inboard and vertical with GSZ, counterforce device is provided with the hole that is complementary with pull bar, pull bar passes counterforce device, and lifting jack is socketed on the outside of counterforce device on the pull bar.
Described pull bar is a screw-thread steel, and cross bar is a round steel, and counterforce device is a reaction beam.
Being connected between GSZ and the lifting jack is the key of pull-out test, and whether jockey rationally directly influences the reliability of pull-out test data again, and used lifting jack is the punching lifting jack.Use lignum vitae board clamp helps increasing the friction factor between anchor clamps and the GSZ in clamping process, do not cause the GSZ surface impaired again simultaneously.
The beneficial effects of the utility model are:
Use the utility model increases the friction factor between anchor clamps and the GSZ in clamping process, do not cause the GSZ surface impaired again simultaneously, and the material of selecting for use is simple, and accuracy requirement is not high, and processing and fabricating is convenient; Use the utility model both GSZ not to be caused damage in process of the test, GSZ does not produce slippage yet, and is respond well through verification experimental verification; Be applicable to the engineering site pull-out test; Be not only applicable to the on-the-spot pull-out test of GSZ, be applicable to the on-the-spot pull-out test of other flexible muscle materials yet.
Description of drawings
Fig. 1 is the utility model embodiment site test vertical view;
Fig. 2 is the utility model clamp device sectional view.
The corresponding component names of mark among the figure: 1-GSZ; The 2-top board; The 3-lower platen; The 4-backing plate; The 5-perforate; The 6-bolt; The 7-nut; The 8-pad; The 9-cross bar; 10-pole; The 11-lifting jack; The 12-counterforce device.
Embodiment
As depicted in figs. 1 and 2, the utility model comprises GSZ 1, also comprises clamp device and draw-off gear, and described clamp device and draw-off gear and GSZ 1 removably connect.
Wherein clamp device comprises top board 2, lower platen 3 and backing plate 4, and top board 2, lower platen 3 and backing plate 4 evenly are provided with perforate 5 along its length, along its length every meter to be provided with perforate 5 numbers be 6, six perforates are corresponding.Perforate 5 is provided with the bolt 6 that matches, and bolt 6 is provided with the nut 7 that matches.Be provided with pad 8 between nut 7 and top board 2 or the lower platen 3.During test GSZ 1 is turned down, GSZ and following GSZ in the formation, sweep is positioned at soil body outside, and remainder is covered by the soil body.Backing plate 4 is placed between GSZ and the following GSZ, then top board 2 is placed on above the GSZ, lower platen 3 is placed on down below the GSZ, top board 2, lower platen 3 and backing plate 4 stack alignment, the outside of top board 2 and lower platen 3 is distributed with pad 8, and this pad 8 can be a steel plate washer.Top board 2, lower platen 3 and backing plate 4 are the hard plank.Bolt 6 passes top board 2, lower platen 3 and backing plate 4 corresponding perforates 5, and nut 7 is enclosed within bolt 6 outsides, pad 8 tops, and fastening nut 7 is fixing with GSZ 1.
Draw-off gear comprises cross bar 9, pull bar 10, lifting jack 11 and counterforce device 12, pull bar 10 1 ends are weldingly fixed on cross bar 9 middle parts, cross bar 9 is socketed in the sweep inboard that GSZ 1 turnover back forms, pull bar 10 passes counterforce device 12, and lifting jack 11 is socketed on the outside of counterforce device 12 on the pull bar 10.Pull bar 10 can be screw-thread steel, and cross bar 9 can be round steel, and counterforce device 12 can be reaction beam, and lifting jack 11 is the punching lifting jack.

Claims (6)

1. the on-the-spot pull-out test jockey of GSZ comprises GSZ (1), it is characterized in that also comprise clamp device and draw-off gear, described clamp device and draw-off gear and GSZ (1) removably connect; Described clamp device comprises top board (2), lower platen (3) and backing plate (4), and top board (2), lower platen (3) and backing plate (4) evenly are provided with perforate (5) along its length; Described draw-off gear comprises cross bar (9), pull bar (10), lifting jack (11) and counterforce device (12), pull bar (10) one ends are fixed on cross bar (9) middle part, the sweep that cross bar (9) places GSZ (1) turnover back to form is inboard and vertical with GSZ (1), counterforce device (12) is provided with the hole that is complementary with pull bar (10), pull bar (10) passes counterforce device (12), and lifting jack (11) is socketed on the outside that pull bar (10) is gone up counterforce device (12).
2. the on-the-spot pull-out test jockey of GSZ according to claim 1 is characterized in that, described top board (2), lower platen (3) and backing plate (4) along its length every meter to be provided with perforate (5) number be that 4-6 is individual.
3. the on-the-spot pull-out test jockey of GSZ according to claim 2 is characterized in that described perforate (5) is provided with the bolt (6) that matches, and bolt (6) is provided with the nut (7) that matches.
4. the on-the-spot pull-out test jockey of GSZ according to claim 3 is characterized in that, is provided with pad (8) between described nut (7) and top board (2) or the lower platen (3).
5. the on-the-spot pull-out test jockey of GSZ according to claim 1 and 2 is characterized in that described top board (2), lower platen (3) and backing plate (4) are the hard plank.
6. the on-the-spot pull-out test jockey of GSZ according to claim 1 is characterized in that described pull bar (10) is a screw-thread steel, and cross bar (9) is a round steel, and counterforce device (12) is a reaction beam.
CN200920082805XU 2009-07-22 2009-07-22 Connecting clamp for geogrid field pull-out test Expired - Lifetime CN201569603U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920082805XU CN201569603U (en) 2009-07-22 2009-07-22 Connecting clamp for geogrid field pull-out test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920082805XU CN201569603U (en) 2009-07-22 2009-07-22 Connecting clamp for geogrid field pull-out test

Publications (1)

Publication Number Publication Date
CN201569603U true CN201569603U (en) 2010-09-01

Family

ID=42661897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920082805XU Expired - Lifetime CN201569603U (en) 2009-07-22 2009-07-22 Connecting clamp for geogrid field pull-out test

Country Status (1)

Country Link
CN (1) CN201569603U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101986129A (en) * 2010-06-22 2011-03-16 交通运输部公路科学研究所 Hydraulic wide geogrid clamp
CN104062230A (en) * 2014-07-03 2014-09-24 安徽省(水利部淮河水利委员会)水利科学研究院 Concrete carbonized protective layer bonding strength detector
CN104099919A (en) * 2013-04-07 2014-10-15 唐善祥 Reinforced earth connection device
CN105784465A (en) * 2016-03-30 2016-07-20 广西众诚工程质量检测有限公司 Square supporting device for pull-out test
CN107091774A (en) * 2017-05-22 2017-08-25 中国农业大学 A kind of GSZ drawing fixture and its implementation
CN108225944A (en) * 2018-01-22 2018-06-29 西南交通大学 A kind of rubble railway ballast direct shear test instrument
CN108844827A (en) * 2018-05-25 2018-11-20 武汉理工大学 Multifunctional earth grid pull-out test device based on actual condition
CN109352971A (en) * 2018-10-11 2019-02-19 安徽徽风新型合成材料有限公司 A kind of TGXG production stretching device and its working method
CN109975204A (en) * 2019-05-08 2019-07-05 中交隧道工程局有限公司 A kind of high mountain artificial snow-making pipeline testing device for friction coefficient and its method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101986129A (en) * 2010-06-22 2011-03-16 交通运输部公路科学研究所 Hydraulic wide geogrid clamp
CN101986129B (en) * 2010-06-22 2013-09-11 交通运输部公路科学研究所 Hydraulic wide geogrid clamp
CN104099919A (en) * 2013-04-07 2014-10-15 唐善祥 Reinforced earth connection device
CN104062230A (en) * 2014-07-03 2014-09-24 安徽省(水利部淮河水利委员会)水利科学研究院 Concrete carbonized protective layer bonding strength detector
CN105784465A (en) * 2016-03-30 2016-07-20 广西众诚工程质量检测有限公司 Square supporting device for pull-out test
CN107091774A (en) * 2017-05-22 2017-08-25 中国农业大学 A kind of GSZ drawing fixture and its implementation
CN107091774B (en) * 2017-05-22 2023-09-15 中国农业大学 Geogrid drawing clamp and implementation method thereof
CN108225944A (en) * 2018-01-22 2018-06-29 西南交通大学 A kind of rubble railway ballast direct shear test instrument
CN108844827A (en) * 2018-05-25 2018-11-20 武汉理工大学 Multifunctional earth grid pull-out test device based on actual condition
CN109352971A (en) * 2018-10-11 2019-02-19 安徽徽风新型合成材料有限公司 A kind of TGXG production stretching device and its working method
CN109352971B (en) * 2018-10-11 2020-07-28 安徽徽风新型合成材料有限公司 Stretching device for geogrid production and working method thereof
CN109975204A (en) * 2019-05-08 2019-07-05 中交隧道工程局有限公司 A kind of high mountain artificial snow-making pipeline testing device for friction coefficient and its method

Similar Documents

Publication Publication Date Title
CN201569603U (en) Connecting clamp for geogrid field pull-out test
CN105829624B (en) Device with concrete pedestal and tower and the method for building tower
CN104179886B (en) Anchoring device for fiber reinforced plastic composite cable
CN103234902B (en) Device and method for testing adhesive property between fiber reinforce plastic (FRP) rib and concrete under complicated stress state
CN105002939B (en) Model device and method for grouped pile field test
CN109403396B (en) Horizontal and upward pulling combined loading device and method for pile foundation model test
CN101655432A (en) uniaxial tension and soil beam bending tester
CN205743030U (en) Carbon fiber board mechanical grip anchorage and bracing means
CN201310102Y (en) Static load test conversion beam
CN106289987A (en) A kind of can realize each pilot system to drawing and implementation thereof
CN108362578B (en) Shear bearing capacity testing device for thin steel plate stud
CN206902781U (en) The detection means of anchor pole internal force exterior measuring
CN205607767U (en) Test FRP cloth stress relaxation's device
CN105716949B (en) A kind of test method for testing FRP cloth stress relaxation
CN209945875U (en) T-shaped section bar strength testing device
CN105862941A (en) Model device and method for measuring time effect of bearing capacity of pile foundations on site
CN109778926B (en) Single pile compression-resistant static load test device, construction method and special tool
CN207114334U (en) Stretching-resisting bending-resisting testing machine
EP1705313A3 (en) Reinforced console column and the method of its production
CN207004052U (en) A kind of pre-stress stretching device for assembled sheet material
CN101285333A (en) Special anchorage for combined variable-corrugated fiber sheets and prestressing force stretching thereof
CN203414351U (en) Prestrain reinforced experimental device
CN205530763U (en) Tensile overlapped rubber vibration -isolated base
CN210597412U (en) Connecting assembly for anchor pile drawing test
CN205530764U (en) Tensile overlapped rubber vibration -isolated base

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Panzhihua nineteen smelting survey design & Research Institute Co Ltd

Assignor: MCC Shijiu Construction Co., Ltd.

Contract record no.: 2010510000120

Denomination of utility model: Connecting clamp for geogrid field pull-out test

Granted publication date: 20100901

License type: Exclusive License

Record date: 20101117

ASS Succession or assignment of patent right

Owner name: PANZHIHUA 19TH METALLURGICAL SURVEYING DESIGN INST

Free format text: FORMER OWNER: MCC SHIJIU CONSTRUCTION CO., LTD.

Effective date: 20110329

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 617000 NO. 350, RENMIN STREET, PANZHIHUA CITY, SICHUAN PROVINCE TO: 617000 NO. 16, GAOFENG ROAD, EAST DISTRICT, PANZHIHUA CITY, SICHUAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110329

Address after: 617000 Panzhihua Province, East Road, Sichuan, No. 16

Patentee after: Panzhihua nineteen smelting survey design & Research Institute Co Ltd

Address before: 617000 No. 350 Renmin Street, Sichuan, Panzhihua

Patentee before: MCC Shijiu Construction Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20100901

CX01 Expiry of patent term