CN201560798U - Horizontal directional drilling machine framework - Google Patents

Horizontal directional drilling machine framework Download PDF

Info

Publication number
CN201560798U
CN201560798U CN2009203174279U CN200920317427U CN201560798U CN 201560798 U CN201560798 U CN 201560798U CN 2009203174279 U CN2009203174279 U CN 2009203174279U CN 200920317427 U CN200920317427 U CN 200920317427U CN 201560798 U CN201560798 U CN 201560798U
Authority
CN
China
Prior art keywords
tripod
crane
big
drilling machine
big tripod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009203174279U
Other languages
Chinese (zh)
Inventor
杨积凯
聂政熊
龙陆军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING SHOUER ENGINEERING TECHNOLOGY Co Ltd
Priority to CN2009203174279U priority Critical patent/CN201560798U/en
Application granted granted Critical
Publication of CN201560798U publication Critical patent/CN201560798U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

A horizontal directional drilling machine framework comprises a front set of framework body and a rear set of framework body, wherein the front set of framework body and the rear set of framework body are axially connected on a surface of a chapelet via profile steels. Each set of framework body consists of a left large triangular bracket, a right large triangular bracket, two small triangular brackets and a lifter, wherein the left large triangular bracket and the right large triangular bracket are disposed shoulder to shoulder, the two small triangular brackets are slidably connected onto the large triangular brackets, the lifter is connected between the two large triangular brackets, and the front set of framework body and the rear set of framework body are integrally connected via profile steels. The framework is convenient in assembling and moving, joints of the framework can be connected by utilizing clamp plates and high strength bolts, and then the framework has the advantages of high integrity, stability, safety and reliability. During construction, the horizontal direction drilling machine framework does not need to be detached, cut or welded, thereby greatly shortening shifting time of drilling machines. Three drilling machines can be put into construction simultaneously, can also respectively move independently and are convenient and flexible. In addition, the horizontal direction drilling machine framework can guarantee full-face drilling construction, reduces operation labor intensity, increases construction production efficiency and is adaptable to various tunnels and field working faces with different sizes.

Description

The horizontal directional drilling machine frame
Technical field
The utility model relates to the frame of a kind of constructing tunnel with horizontal directional drilling machine.
Background technology
Horizontal directional drilling machine is mainly used in pipe canopy, horizontal jet grouting stake and country rock anchoring, the mortar depositing construction in tunnel portal and the tunnel.Existing level directional drilling machine frame mainly contains two kinds: reassembling type intersecting parallels frame and crawler type board.In the work progress, along with column need be cut off or weld to the variation of position, hole, not only unrestrained waste materials influences work efficiency to reassembling type well type frame, and has reduced the stiffness of column, influences the stability of whole frame, has serious potential safety hazard in the tunnel.Though crawler type board good integrity is higher to the job site site requirements, along with the variation of position, hole, need repeatedly excavate smooth to the work-yard platform, not only operation is cumbersome, the prolongation construction period, and because the import and export vertical shaft restriction of city tunnel can't enter construction in the tunnel.
The utility model content
The purpose of this utility model provides a kind of horizontal directional drilling machine frame, solve existing rack construction and be difficult to adapt to the variation of position, hole, influences the technical problem of efficiency of construction.
For achieving the above object, the utility model adopts following technical scheme:
This horizontal directional drilling machine frame, be included in the chapelet over glaze to the two groups of frame support bodys in front and back that connect by shaped steel, every group of frame support body by about two big tripods that are provided with shoulder to shoulder, two little tripods that on big tripod, are slidingly connected, and be connected two cranes between the big tripod and constitute; Connect into integral body by shaped steel between the big tripod of the two groups of frame support bodys in front and back;
Described big tripod is the triangular structure of right angle that is connected into by column, bottom girder and cant beam; Two adjacent middle parts, tunnel that are arranged at of big tripod column, big tripod cant beam is towards the tunnel-side setting, axially be equipped with a chassis rail perpendicular to the tunnel on the platform of every group of frame support body bottom, two big tripod bottom girder two ends are equipped with the frame pulley, and two big tripod bottoms are slidingly connected by frame pulley and chassis rail;
One side of described little tripod is connected with big tripod cant beam by slips, and little tripod top and big tripod top all are connected with little tripod lifting and draw ear;
Described crane is connected between two big tripod columns, it is the rectangular frame structure that connects into by two crane columns, crane bottom girder and crane back timber, crane bottom girder and big tripod column top all are connected with crane and draw ear, and crane bottom girder two ends are connected with big tripod column.
Have the rule that is used to control the crane adjustable height on the described big tripod column.
Two sides, described crane column front and back has wears the effective locating ring of shelf.
Be connected with middle beam between the column at described big tripod middle part and the cant beam.
Described crane bottom girder two ends are connected with big tripod column by the crane slips.
Described big tripod, crane, little tripod all adopt shaped steel to be formed by connecting by slips and high-strength bolt.
Described crane and little tripod can be driven by Chain block or hydraulic jack.
Described big tripod cant beam can be direct rod shape or circular-arc.
Described shaped steel can be H shaped steel, i iron, round steel, steel pipe or square steel.
Compared with prior art the utlity model has following characteristics and beneficial effect:
The utility model can be installed both sides, tunnel and middle part rig respectively on two little tripods and crane; Two big tripods can be adjusted the position by the track of bottom during use, and then adjust the rig horizontal level; Move by Chain block or hydraulic jack pulling crane and little tripod, and then adjust the rig upper-lower position, make that rig is convenient from the bottom, safe mobile is to the top.
This frame assembling, conveniently moving, each node of frame all can adopt clamping plate to be connected with high-strength bolt, has the high advantage of globality, stability and security reliability.In work progress, need not shorten the time that rig is shifted greatly with dismounting, cutting or welding borer frame.Three bench drill machines can be constructed together simultaneously, also can distinguish alone and move, and are convenient, flexible, can guarantee the construction of full section boring, reduced operation labor intensity, improved construction production efficiency, are applicable to the site work face of various tunnels and different size.
Description of drawings
The utility model is described in more detail below in conjunction with accompanying drawing.
Fig. 1 is a structural representation of the present utility model.
Fig. 2 is the structural representation of shaped steel.
Fig. 3 is the structural representation of big tripod.
Fig. 4 is the structural representation of crane.
Fig. 5 is the structural representation of locating ring.
The big tripod of Reference numeral: 1-, the big tripod column of 1.1-, the big tripod bottom girder of 1.2-, the big tripod cant beam of 1.3-, 1.4-middle beam;
2-crane, 2.1-crane column, 2.2-crane bottom girder, 2.3-crane back timber, 2.4-locating ring, 2.5-crane slips;
The little tripod of 3-, 4-chassis rail, 5-frame pulley, 6-slips, 7-chapelet face, 8-crane draw ear, the little tripod lifting of 9-to draw ear, 10-rule, 11-shaped steel, 12-platform.
The specific embodiment
Embodiment is referring to shown in Figure 1, this horizontal directional drilling machine frame, be included in two groups of frame support bodys in front and back that tunnel 7 is axially connected by shaped steel, every group of frame support body by about two big tripods that are provided with shoulder to shoulder 1, two little tripods 3 that on big tripod, are slidingly connected, and be connected two cranes 2 between the big tripod and constitute.Big tripod 1, crane 2, little tripod 3 all adopt shaped steel to be formed by connecting by slips and high-strength bolt.
Referring to shown in Figure 2, connect into integral body by shaped steel 11 between the big tripod of the two groups of frame support bodys in front and back.As: connect by H shaped steel between the bottom girder of the big tripod 1 of the two groups of frame support bodys in front and back, connect by round steel between the column and between the top.
Referring to shown in Figure 3, big tripod 1 is the triangular structure of right angle that is connected into by column, bottom girder and cant beam.Two big tripod column 1.1 adjacent middle parts, tunnel that are arranged at have the rule 10 that is used to control the crane adjustable height on the column.Big tripod cant beam 1.3 is towards the tunnel-side setting.Axially being equipped with 4, two big tripod bottom girders of a chassis rail, 1.2 two ends perpendicular to the tunnel on the platform of every group of frame support body bottom is equipped with 5, two big tripods of frame pulley bottom and is slidingly connected by frame pulley and chassis rail.Be connected with middle beam 1.4 between the column at big tripod middle part and the cant beam, on middle beam, can set up the manually-operated platform.
One side of little tripod 3 is slidingly connected by slips 6 and big tripod cant beam, and little tripod top and big tripod top all are connected with little tripod lifting and draw ear 9, and little tripod is driven by Chain block or hydraulic jack.
Referring to Fig. 4, shown in Figure 5, described crane is connected between two big tripod columns 1.1, is the rectangular frame structure that is connected into by two crane columns 2.1, crane bottom girder 2.2 and crane back timber 2.3.Crane bottom girder 2.2 and big tripod column 1.1 tops all are connected with crane and draw ear 8, crane is driven by Chain block or hydraulic jack, crane bottom girder 2.2 two ends are connected with big tripod column 1.1 by crane slips 2.5, but lay-up operation platform on the crane bottom girder 2.2.Two sides, crane column front and back has wears the effective locating ring of shelf 2.4.
The course of work of the present utility model: with the work plane leveling, track and with tunnel axis vertical lay parallel with the tunnel mileage line installed big tripod earlier on the track of front and back.Big tripod installs the back and adjusts its position, between two big tripods, crane is installed, and crane is connected by clamping plate and high-strength bolt with big tripod, connect shaped steel by the front and back frame at last the big triangle frame in front and back is connected respectively with middle crane, make whole shelf become as a whole.
When three bench drill machines are constructed simultaneously, rationally arrange the job task of two bench drill machines, avoid phase mutual interference in the work progress, should treat that then shelf installs after, three bench drill machines are installed on the little tripod of a side respectively and on the middle crane.Adjust the position of this rig by Chain block and little tripod upper sliding plate, make rig and design hole bit alignment.Rig on the middle crane can be adjusted its height by Chain block, when adjusting the rig horizontal level as need, then can whole shelf be moved in orbit by the movable pulley of big tripod bottom, also can on middle crane, feed frame by direct mobile rig, again with high-strength bolt fixedly rig feed frame.If have only a bench drill machine, then can begin to set from an end of tripod, operation on the little shelf in the middle of rig moves on to then, last rig moves on to operation on the big tripod of opposite side.

Claims (9)

1. horizontal directional drilling machine frame, be included in two groups of frame support bodys in front and back that chapelet face (7) is axially connected by shaped steel, it is characterized in that: every group of frame support body by about two big tripods (1) that are provided with shoulder to shoulder, two little tripods (3) that on big tripod, are slidingly connected, and be connected two cranes (2) between the big tripod and constitute; Connect into integral body by shaped steel (11) between the big tripod of the two groups of frame support bodys in front and back;
Described big tripod (1) is the triangular structure of right angle that is connected into by column, bottom girder and cant beam; The adjacent middle part, tunnel that is arranged at of two big tripod columns (1.1), big tripod cant beam (1.3) is towards the tunnel-side setting, the platform (12) of every group of frame support body bottom is gone up and axially is equipped with a chassis rail (4) perpendicular to the tunnel, two big tripod bottom girders (1.2) two ends are equipped with frame pulley (5), and two big tripod bottoms are slidingly connected by frame pulley and chassis rail;
One side of described little tripod (3) is connected with big tripod cant beam by slips (6), and little tripod top and big tripod top all are connected with little tripod lifting and draw ear (9);
Described crane is connected between two big tripod columns (1.1), it is the rectangular frame structure that connects into by two crane columns (2.1), crane bottom girder (2.2) and crane back timber (2.3), crane bottom girder (2.2) and big tripod column (1.1) top all are connected with crane and draw ear (8), and crane bottom girder two ends are connected with big tripod column.
2. horizontal directional drilling machine frame according to claim 1 is characterized in that: have the rule (10) that is used to control the crane adjustable height on the described big tripod column.
3. horizontal directional drilling machine frame according to claim 1 is characterized in that: two sides, described crane column front and back has wears the effective locating ring of shelf (2.4).
4. horizontal directional drilling machine frame according to claim 1 is characterized in that: be connected with middle beam (1.4) between the column at described big tripod middle part and the cant beam.
5. horizontal directional drilling machine frame according to claim 1 is characterized in that: described crane bottom girder (2.2) two ends are connected with big tripod column (1.1) by crane slips (2.5).
6. horizontal directional drilling machine frame according to claim 1 is characterized in that: described big tripod (1), crane (2), little tripod (3) all adopt shaped steel to be formed by connecting by slips and high-strength bolt.
7. horizontal directional drilling machine frame according to claim 1 is characterized in that: described crane and little tripod are driven by Chain block or hydraulic jack.
8. horizontal directional drilling machine frame according to claim 1 is characterized in that: described big tripod cant beam (1.3) is a direct rod shape or circular-arc.
9. horizontal directional drilling machine frame according to claim 1 is characterized in that: described shaped steel (11) is H shaped steel, i iron, round steel, steel pipe or square steel.
CN2009203174279U 2009-12-15 2009-12-15 Horizontal directional drilling machine framework Expired - Lifetime CN201560798U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203174279U CN201560798U (en) 2009-12-15 2009-12-15 Horizontal directional drilling machine framework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203174279U CN201560798U (en) 2009-12-15 2009-12-15 Horizontal directional drilling machine framework

Publications (1)

Publication Number Publication Date
CN201560798U true CN201560798U (en) 2010-08-25

Family

ID=42625945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203174279U Expired - Lifetime CN201560798U (en) 2009-12-15 2009-12-15 Horizontal directional drilling machine framework

Country Status (1)

Country Link
CN (1) CN201560798U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806277A (en) * 2015-04-14 2015-07-29 王发秀 Automatic rod feeding device for mine anchor rod drilling machine
CN104308815B (en) * 2014-09-28 2016-04-06 上海锅炉厂有限公司 Bipyramid platform assembling assembly fixture
CN105604590A (en) * 2016-03-16 2016-05-25 浙江八达隧道工程股份有限公司 Arch roof bolter supporting device for tunnel construction and method thereof
CN108002288A (en) * 2017-12-10 2018-05-08 建研地基基础工程有限责任公司 A kind of horizontal directional drilling machine assembled hoistable platform for the construction of tunnel vertical duct curtain
CN109736823A (en) * 2018-11-30 2019-05-10 中铁十六局集团第一工程有限公司 A kind of more work surface construction methods of large cross-section tunnel super-front large pipe shed

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104308815B (en) * 2014-09-28 2016-04-06 上海锅炉厂有限公司 Bipyramid platform assembling assembly fixture
CN104806277A (en) * 2015-04-14 2015-07-29 王发秀 Automatic rod feeding device for mine anchor rod drilling machine
CN105604590A (en) * 2016-03-16 2016-05-25 浙江八达隧道工程股份有限公司 Arch roof bolter supporting device for tunnel construction and method thereof
CN108002288A (en) * 2017-12-10 2018-05-08 建研地基基础工程有限责任公司 A kind of horizontal directional drilling machine assembled hoistable platform for the construction of tunnel vertical duct curtain
CN109736823A (en) * 2018-11-30 2019-05-10 中铁十六局集团第一工程有限公司 A kind of more work surface construction methods of large cross-section tunnel super-front large pipe shed

Similar Documents

Publication Publication Date Title
CN106089258B (en) Tunnel device and construction method
CN102900362B (en) Narrow-machine-body full-hydraulic bolt and anchor cable drill carriage for coal mine tunnel
CN201560798U (en) Horizontal directional drilling machine framework
CN104695984A (en) Multifunctional tunnel construction trolley
CN102251747B (en) Arc-shaped drill rack
CN101832102A (en) Movable two-platform partitioned four-arm hanging wall anchor rod and anchor cable construction drill carriage
CN104747078A (en) Tunnel construction trolley
CN103711447A (en) Truck-mounted drilling rig rod changing device
CN108457666A (en) A kind of liftable adjustable type tunnel multi-step excavates rack
CN102720432A (en) Self-propelled underground boring jumbo
CN204627622U (en) The multi-functional construction trolley in a kind of tunnel
CN109611112A (en) A kind of tunnel excavation driving bull rock drilling machine
CN204703761U (en) A kind of tunnel construction trolley
CN202055821U (en) Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform
CN103541735A (en) Tunneling machine stepping pushing supporting device and construction method
CN203499559U (en) Conveniently moved hydraulic anchoring drill for roadway
CN102116155A (en) Method for supporting and coalmining in transition section of large-mining-height working face
CN107989042A (en) A kind of construction method of pile-grafting machine
CN205558915U (en) Portable operation device
CN208010356U (en) A kind of liftable adjustable type tunnel multi-step excavates rack
CN201635656U (en) Side-propping anchor rod-anchor cable construction drill carriage with three movable arms
CN201671650U (en) Extremely-thin seam mining hydraulic support
CN104405425B (en) Development machine automatic moving type leading support equipment
CN103147437A (en) Section steel soil cement mixing pile with longitudinal displacement mechanism
CN110778279A (en) Lifting type synchronous drilling equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Horizontal directional drilling machine framework

Effective date of registration: 20110127

Granted publication date: 20100825

Pledgee: Bank of Communications Ltd Beijing Zhongguancun Park sub branch

Pledgor: Beijing Shouer Engineering Technology Co., Ltd.

Registration number: 2011990000031

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20120217

Granted publication date: 20100825

Pledgee: Bank of Communications Ltd Beijing Zhongguancun Park sub branch

Pledgor: Beijing Shouer Engineering Technology Co., Ltd.

Registration number: 2011990000031

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Horizontal directional drilling machine framework

Effective date of registration: 20120903

Granted publication date: 20100825

Pledgee: Bank of Communications Ltd Beijing Zhongguancun Park sub branch

Pledgor: Beijing Shouer Engineering Technology Co., Ltd.

Registration number: 2012990000487

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20100825