- CN201540532U CN201540532U CN2009202702906U CN200920270290U CN201540532U CN 201540532 U CN201540532 U CN 201540532U CN 2009202702906 U CN2009202702906 U CN 2009202702906U CN 200920270290 U CN200920270290 U CN 200920270290U CN 201540532 U CN201540532 U CN 201540532U
- Authority
- CN
- China
- Prior art keywords
- signal
- power supply
- management controller
- baseboard management
- motherboard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Power Sources (AREA)
Abstract
The utility model relates to a server system, at least comprising a power supply module, a main board with a substrate management controller, and an input/output board. The input/output board is inserted on the main board in electrically connection; the power supply module provides power for the substrate management controller so that the substrate management controller works so as to guarantee that the substrate management controller can operate starting self-check programming after the input/output board is detected, thereby solving the disadvantage of abnormal work caused by the substrate management controller incapable of detecting the insertion of the input/output board in real time; thus, the adaptation of diverse configuration requirements and each component cooperation support of system are realized.
Description
Technical field
The utility model relates to a kind of server system, relates in particular to the complete server system that is inserted in behind the motherboard the baseboard management controller power supply of a kind of input/output board.
Background technology
The design of server is at present tended to compile on its motherboard all multi-functional usually, yet, the needed server capability of different customer groups is also inequality, that is, all multi-functional some client on the motherboard differs surely and to use fully, causes that some function is unnecessary functions to some clients on the motherboard, and these redundancy functions can significantly increase the price of product, and then cause the discontented of client, also can cause adverse effects such as time-consuming simultaneously to our design of motherboard.
In addition, the motherboard that is used for server system at present generally all can have baseboard management controller assemblies such as (BMC), described these assemblies are usually when this server system is energized and starts shooting operation, just start working, if the system unit on this motherboard plugs do not finish this moment, then can cause system exception, thereby exist the technical matters that server system can't adapt to each parts cooperation in diversified configuration needs and the back-up system.
Therefore, how to propose a kind of server system that adapts to diversified configuration needs,, become the problem that present industry needs to be resolved hurrily in fact with the cooperation of each parts in the back-up system.
The utility model content
In view of the shortcoming of above-mentioned prior art, a purpose of the present utility model is to provide a kind of server system, adapts to diversified configuration needs, and the cooperation of interior each parts of back-up system.
For reaching above-mentioned and other purpose, the utility model provides a kind of server system, comprising: power supply module provides a power supply; At least one motherboard connects this power supply module; And at least one input/output board, this motherboard of pluggable connection, thus make this motherboard to this input/output board power supply, and make this input/output board output one connect signal to this motherboard; Wherein, this motherboard comprises: one first modular converter, and receive this power supply and be converted to a standby voltage, when this standby voltage transitions is finished, output one power supply perfect signal; One control module receives this connection signal, and connects this first modular converter to receive this power supply perfect signal, exports an operating voltage; And a baseboard management controller, connect this control module; When this control module received this power supply perfect signal and this connection signal simultaneously, this control module was exported an operating voltage to this baseboard management controller, thereby made this baseboard management controller start working.
In an embodiment of the present utility model, this control module further comprises a processing unit, this processing unit connects this first modular converter, and receive this connection signal and this power supply perfect signal respectively, when receiving this connection signal and this power supply perfect signal simultaneously, sends this processing unit a ready signal.
In another embodiment of the present utility model, this control module further comprises a delay unit and a processing unit; This delay unit receives this connection signal, and output one connects confirmation signal after receiving this to connect signal; This processing unit connects this delay unit and this first modular converter respectively, to receive this connection confirmation signal and this power supply perfect signal respectively, sends a ready signal when receiving this connection confirmation signal and this power supply perfect signal simultaneously.
In addition, this control module further comprises one second modular converter, connect this processing unit and this first modular converter respectively, to receive this ready signal and this standby voltage respectively, when this second modular converter receives this ready signal, with this standby voltage transitions for the operating voltage of this baseboard management controller and export this baseboard management controller to, thereby make this baseboard management controller start working.Whether when this baseboard management controller is started working, it is normal with each assembly in the detecting system in regular turn to carry out startup self-detection (POST).
Than prior art, server system of the present utility model comprises power supply module at least, has the motherboard and the input/output board of baseboard management controller.Be inserted on this motherboard and after finishing electric connection at this input/output board, this power supply module side can be to this baseboard management controller power supply, to make this baseboard management controller carry out work, thereby guarantee that this baseboard management controller can just can carry out the startup self-detection supervisor after detecting this input/output board, can't in time detect plugging of this input/output board and the disappearance of operation irregularity to solve this baseboard management controller, and then reach the effect that adapts to each parts cooperation in diversified configuration needs and the back-up system.
Description of drawings
Fig. 1 is the basic framework block schematic diagram of the server system of an embodiment of the present utility model.
[simple declaration of assembly label]
10 power supply modules
101 power supply backplanes
11 input/output boards
12 motherboards
121 first modular converters
122 control modules
1221 delay units
1222 processing units
1,223 second modular converters
123 baseboard management controllers
The V1 supply voltage
V2 standby voltage
The V3 operating voltage
S1 connects signal
The S2 perfect signal of powering
The S3 ready signal
S4 connects confirmation signal
Embodiment
Below by specific instantiation embodiment of the present utility model is described, those skilled in the art can understand other advantage of the present utility model and effect easily by the content that following instructions disclosed.The utility model also can be implemented or be used by other different instantiation, but it should be noted that the every details in this instructions also can be based on different viewpoints and application, carries out various modifications and change under the spirit of the present utility model not deviating from.
As shown in Figure 1, be the basic framework synoptic diagram of the server system of an embodiment of the present utility model, this server system 1 comprises power supply module 10, input/output board 11 (IOboard) and motherboard 12.Below promptly the server system 1 of present embodiment is elaborated.
This input/output board 11 is used on the comparatively easy motherboard 12 of function, when the client has specific (special) requirements, to be inserted on this motherboard 12 by the input/output board 11 that will have specific function, meet requirement of client with the function of strengthening this server system 1, use the design time-histories and the manufacturing cost of this motherboard 12 of effective minimizing.
This power supply module 10 electrically connects by a power supply backplane 101 and this motherboard 12, to provide a supply voltage V1 to this motherboard 12, uses thereby provide this server system 1 to operate.These input/output board 11 pluggable being located on this motherboard 12 electrically connecting with this motherboard 12, thereby make 11 power supplies of 12 pairs of these input/output boards of this motherboard, and make these input/output board 11 outputs one connect signal S1 to this motherboard 12.
In the present embodiment, this motherboard 12 is combined by one first modular converter 121, a control module 122 and a baseboard management controller 123 at least.This first modular converter 121 for example is a transformer, to receive this supply voltage V1 and this supply voltage V1 is converted to a standby voltage V2, output one power supply perfect signal S2 when this standby voltage V2 converts.This control module 122 receives this and connects signal S1, and connects this first modular converter 121 to receive this power supply perfect signal S2.
This baseboard management controller 123 and this control module 122 have the relation of electric connection.When this control module 122 receives this connection signal S1 and this power supply perfect signal S2 simultaneously, this control module 122 must be exported an operating voltage V3 to this baseboard management controller 123, thereby make this baseboard management controller 123 start working, for example, the startup self-detection of executive system (POST) operation.
In the present embodiment, has a processing unit 1222 on this control module 122, this processing unit 1222 connects this first modular converter 121, and receive this connection signal S1 and this power supply perfect signal S2 respectively, when receiving this connection signal S1 and this power supply perfect signal S2 simultaneously, exports this processing unit 1222 a ready signal S3.Above-mentioned processing unit 1222 is by for example being constituted with arithmetic logic unit such as door or door and perimeter circuit thereof, but not as limit.
In addition, in the present embodiment, this control module 122 further comprises a delay unit 1221 and a processing unit 1222.This delay unit 1221 receives this and connects signal S1, and connects the laggard line delay processing of signal S1 in receiving this, connects confirmation signal S4 to export one.This processing unit 1222 has electrical connection with this delay unit 1221 and this first modular converter 121 respectively, to receive this connection confirmation signal S4 and this power supply perfect signal S2 respectively, when receiving this connection confirmation signal S4 and this power supply perfect signal S2 simultaneously, this processing unit 1222 can send a ready signal S3.Above-mentioned delay unit 1221 is to be made of complex logic assembly (CPLD) and perimeter circuit thereof, but not as limit, in other embodiments, also can for example select for use a plurality of phase inverters and perimeter circuit thereof to constitute this delay unit 1221.
This delay unit 1221 solved since when power supply this baseboard management controller 123 working time and this input/output board 11 be inserted between this motherboard 12 poor if having time, and cause this baseboard management controller 123 can't detect plugging on this input/output board 11 in real time, cause the shortcoming that this baseboard management controller 123 can't operate as normal.
In the present embodiment, this control module 122 further comprises one second modular converter 1223, it for example is transformer, has electrical connection with this processing unit 1222 and this first modular converter 121 respectively, to receive this ready signal S3 and this standby voltage V2 respectively, when this second modular converter 1223 receives this ready signal S3, this standby voltage V2 is converted to the operating voltage V3 of this baseboard management controller 123 and exports this baseboard management controller 123 to, thereby make this baseboard management controller 123 start working.It should be noted that when this baseboard management controller 123 is started working whether carry out startup self-detection (POST) normal with each assembly in the detecting system in regular turn, thereby the system that is beneficial to carries out follow-up operation.
Than prior art, server system of the present utility model comprises power supply module at least, has the motherboard and the input/output board of baseboard management controller.Be inserted on this motherboard and after finishing electric connection at this input/output board, this power supply module side can be to this baseboard management controller power supply, to make this baseboard management controller carry out work, thereby guarantee that this baseboard management controller can just can carry out the startup self-detection supervisor after detecting this input/output board, can't in time detect plugging of this input/output board and the shortcoming of operation irregularity to solve this baseboard management controller, and then reach the effect that adapts to each parts cooperation in diversified configuration needs and the back-up system.
The foregoing description is illustrative principle of the present utility model and effect thereof only, but not is used to limit the utility model.Any those skilled in the art all can be under spirit of the present utility model and category, and the foregoing description is modified and changed.Therefore, rights protection scope of the present utility model should be listed as claims.
Claims (5)
1. server system comprises:
Power supply module provides a power supply;
At least one motherboard, it connects this power supply module; And
At least one input/output board, its this motherboard of pluggable connection, thus make this motherboard to this input/output board power supply, and make this input/output board output one connect signal to this motherboard; It is characterized in that,
This motherboard comprises:
One first modular converter receives this power supply and is converted to a standby voltage, when this standby voltage transitions is finished, and output one power supply perfect signal;
One control module receives this connection signal, and connects this first modular converter to receive this power supply perfect signal, exports an operating voltage; And
One baseboard management controller connects this control module; When this control module received this power supply perfect signal and this connection signal simultaneously, this control module was exported an operating voltage to this baseboard management controller, thereby made this baseboard management controller start working.
2. server system according to claim 1, it is characterized in that, this control module further comprises a processing unit, this processing unit connects this first modular converter, and receive this connection signal and this power supply perfect signal respectively, when receiving this connection signal and this power supply perfect signal simultaneously, sends this processing unit a ready signal.
3. server system according to claim 1 is characterized in that, this control module further comprises a delay unit and a processing unit; This delay unit receives this connection signal, and output one connects confirmation signal after receiving this to connect signal; This processing unit connects this delay unit and this first modular converter respectively, to receive this connection confirmation signal and this power supply perfect signal respectively, exports a ready signal when this processing unit receives this connection confirmation signal and this power supply perfect signal simultaneously.
4. according to claim 2 or 3 described server systems, it is characterized in that, this control module further comprises one second modular converter, connect this processing unit and this first modular converter respectively, to receive this ready signal and this standby voltage respectively, when this second modular converter receives this ready signal, with this standby voltage transitions for the operating voltage of this baseboard management controller and export this baseboard management controller to, thereby make this baseboard management controller start working.
5. server system according to claim 1 is characterized in that, whether when this baseboard management controller is started working, it is normal with each assembly in the detecting system in regular turn to carry out startup self-detection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202702906U CN201540532U (en) | 2009-11-27 | 2009-11-27 | Server system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202702906U CN201540532U (en) | 2009-11-27 | 2009-11-27 | Server system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201540532U true CN201540532U (en) | 2010-08-04 |
Family
ID=42591993
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009202702906U Expired - Fee Related CN201540532U (en) | 2009-11-27 | 2009-11-27 | Server system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201540532U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102945196A (en) * | 2012-10-29 | 2013-02-27 | 杭州华为数字技术有限公司 | Method and device for server IO (Input Output) diagnosis |
CN108021402A (en) * | 2017-12-21 | 2018-05-11 | 威创集团股份有限公司 | Start-up control method and processing equipment |
-
2009
- 2009-11-27 CN CN2009202702906U patent/CN201540532U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102945196A (en) * | 2012-10-29 | 2013-02-27 | 杭州华为数字技术有限公司 | Method and device for server IO (Input Output) diagnosis |
CN108021402A (en) * | 2017-12-21 | 2018-05-11 | 威创集团股份有限公司 | Start-up control method and processing equipment |
CN108021402B (en) * | 2017-12-21 | 2020-06-23 | 威创集团股份有限公司 | Starting-up control method and processing equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103809724A (en) | Equipment cabinet and power source control method thereof | |
US10064304B2 (en) | Separated server back plane | |
US7388508B2 (en) | Uninterruptible power supply controller and method | |
CN102724093B (en) | A kind of ATCA machine frame and IPMB method of attachment thereof | |
CN103809723A (en) | Equipment cabinet and power source control method thereof | |
US9748799B2 (en) | Adaptable external battery modules and related systems | |
US20090144569A1 (en) | Communication device, amc and method for supplying power to the amc | |
CN102880087A (en) | Method for controlling power supply and power supply controller | |
CN103853686A (en) | Server | |
US20140292070A1 (en) | Adapter to provide power from a power supply | |
CN201540532U (en) | Server system | |
CN102253703B (en) | Switch-on and switch-off system of motherboards | |
CN113177019B (en) | Switch board and server | |
CN205091605U (en) | Intelligent link ware module and bus control system | |
CN100438258C (en) | Circuit and method for control of multi-module power supply synchronization | |
CN103605303A (en) | Injection-molding-machine digital IO switch-over terminal junction box with redundancy detection function | |
CN103901858A (en) | Electric actuator control system and method based on internal bus | |
CN209895300U (en) | Power supply adapter plate applied to power supply of server | |
CN108279763A (en) | A kind of high-reliability server board power-supply system | |
US11108266B2 (en) | Control method for power supply system and power supply system | |
CN203838545U (en) | Electric performer control system based on internal bus | |
EP2985673B1 (en) | Method and terminal device for continuous power supply to external carrier | |
CN103683976A (en) | Universal power supply system | |
CN201562232U (en) | Server power supply control system | |
CN206162165U (en) | Man -machine supporting system control cabinet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100804 Termination date: 20141127 |
|
EXPY | Termination of patent right or utility model |