CN201473871U - Rail track of maglev train with middle and low-speed - Google Patents

Rail track of maglev train with middle and low-speed Download PDF

Info

Publication number
CN201473871U
CN201473871U CN2009203089219U CN200920308921U CN201473871U CN 201473871 U CN201473871 U CN 201473871U CN 2009203089219 U CN2009203089219 U CN 2009203089219U CN 200920308921 U CN200920308921 U CN 200920308921U CN 201473871 U CN201473871 U CN 201473871U
Authority
CN
China
Prior art keywords
rail
rail beam
support
row
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009203089219U
Other languages
Chinese (zh)
Inventor
陈后军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
Third Railway Survey and Design Institute Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Railway Survey and Design Institute Group Corp filed Critical Third Railway Survey and Design Institute Group Corp
Priority to CN2009203089219U priority Critical patent/CN201473871U/en
Application granted granted Critical
Publication of CN201473871U publication Critical patent/CN201473871U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a rail track of a maglev train with middle and low speed. The rail track is composed of concrete components, two ends of the rail track are supported by supports arranged on bridge piers, the structure comprises: an upper flange and a web plate, the top of the rail track is fixedly provided with a table for supporting the track, the table for supporting the track connects and supports the steel rail row, the steel rail row is provided with a vertical induction rail; two ends supported by the bridge piers of the rail track are solid bodies, the rail track between supporting points of the bridge piers are hollow, and a section has an equal-width shape from top to bottom or the section has a large-top and small-bottom shape; the outer side of the web plate is provided with a diversion-rail support, the diversion-rail support is provided with a diversion rail. The utility model has beneficial effects in that: the rail track between supporting points of the bridge piers are hollow, and a section has an equal-width shape from top to bottom or the section has a large-top and small-bottom shape, which changes size of the flange in the prior art, reduces volume and weight of the rail track, reduces consumption of concrete, has low cost and simple structure, is particularly suitable for the rail track of the meglev train with middle and low-speed.

Description

Middle low-speed maglev train rail beam
Technical field
The utility model relates to light rail and subway magnetic levitation track girder, particularly be middle low-speed maglev train rail beam.
Background technology
The operation of magnetic suspension train is to utilize the electromagnetic force that special-purpose member produced that is provided with in orbit to realize that described special-purpose member comprises buoyant element, guiding parts, driver part and rotatable parts.Magnetic suspension train need move on the magnetic levitation track girder that adapts to its functional requirement.
Fig. 1 is the magnetic levitation track girder cross sectional representation of prior art.As shown in Figure 1, the magnetic levitation track girder 21 of prior art is to be made of concrete component, and described magnetic levitation track girder 21 comprises: top flange 22, web 24, bottom flange 25 and base plate 26; The functor 23 that promising train operation provides electromagnetic force is installed on the outrigger base of top flange 22; Bottom flange 25 is supported on the bridge pier 8 by bearing 7.Bottom flange 25 is much larger than the top flange 22, and roomy bottom flange 25, cross section helps bearing the power that the high-speed cruising train applies, and also helps to change noise sound transmission route, the influence of noise when reducing the train high-speed cruising.
Above-mentioned prior art magnetic levitation track girder dead load is big, and the concrete consumption is many, sets up the cost height, is applicable to the high-speed cruising train, does not need so high magnetic levitation track girder of cost with respect to middle low cruise train.Low speed train operation during people urgently wish to be applicable to, the middle low-speed maglev train rail beam that cost is low occurs.
Summary of the invention
The purpose of this utility model is to overcome the deficiency of above-mentioned technology, provides a kind of cost low, simple in structure, the middle low-speed maglev train rail beam of low speed train operation in being fit to.
The technical scheme that solves the problems of the technologies described above is: low-speed maglev train rail beam in a kind of, described rail beam is made of concrete component, these rail beam two ends are by the seat supports that is arranged on the bridge pier, its structure comprises: top flange, web, top surface of the beam, top surface of the beam is set with the support rail platform, the support rail platform connects and supporting rail row, and rail row is provided with perpendicular reaction rail; Described rail beam supported two ends on bridge pier are solid, are wide or big up and small down shape about hollow and cross section are in the rail beam between the bridge pier strong point; In the outside of described web water conservancy diversion rail support is installed, water conservancy diversion rail support is provided with the water conservancy diversion rail.
Technique effect of the present utility model is: be wide or big up and small down shape about hollow and cross section are in the rail beam between the bridge pier strong point of the present utility model, changed the size of prior art bottom flange, has the volume and weight that alleviates rail beam, reduce the concrete consumption, cost is low, simple in structure, practical, the rail beam of low-speed maglev train in being specially adapted to.
Description of drawings
Fig. 1 is a prior art magnetic levitation track girder cross sectional representation;
Fig. 2 is the beam basal cross section schematic diagram of the utility model U-rail beam bridge Dun Zhichengdianchu;
Fig. 3 is a girder span schematic cross-section between the utility model U-rail beam bridge pier strong point;
Fig. 4 is that the utility model is apart from girder span schematic cross-section between the shape rail beam bridge pier strong point;
Fig. 5 is a girder span schematic cross-section between the utility model v-shaped track beam bridge pier strong point;
Fig. 6 is the schematic cross-section of rail beam of the present utility model at curve paragraph place;
Fig. 7 is that the interior embedded bar of the utility model rail beam and support rail platform, rail are arranged connection diagram;
Fig. 8 is the utility model foot bolt and support rail platform, rail row connection diagram regularly in the preformed hole of rail beam top.
" sequence number explanation in the accompanying drawing "
1: rail beam; 2: the top flange; 4: web; 7: bearing; 8: bridge pier; 9: at the bottom of the beam;
10: hollow in the beam; 11: water conservancy diversion rail support; 12: the water conservancy diversion rail; 13: the support rail platform;
14: reaction rail; 15: top surface of the beam; 16: rail row; 17: stone bolt; 21: rail beam; 22: the top flange; 23: functor; 24: web; 25: the bottom flange; 26: base plate.
The specific embodiment
Below in conjunction with accompanying drawing enforcement of the present utility model is described in further detail.
Fig. 1 is a prior art magnetic levitation track girder cross sectional representation; Fig. 2 is the beam basal cross section schematic diagram of the utility model U-rail beam bridge Dun Zhichengdianchu; Fig. 3 is a girder span schematic cross-section between the utility model U-rail beam bridge pier strong point; Fig. 4 is that the utility model is apart from girder span schematic cross-section between the shape rail beam bridge pier strong point; Fig. 5 is a girder span schematic cross-section between the utility model v-shaped track beam bridge pier strong point; Fig. 6 is the schematic cross-section of rail beam of the present utility model at curve paragraph place; Fig. 7 is that the interior embedded bar of the utility model rail beam and support rail platform, rail are arranged connection diagram; Fig. 8 is the utility model foot bolt and support rail platform, rail row connection diagram regularly in the preformed hole of rail beam top.
The utility model provide a kind of in the low-speed maglev train rail beam, as Fig. 1 to shown in Figure 5, described in low-speed maglev train rail beam 1 constitute by concrete component, these rail beam 1 two ends are supported by the bearing 7 that is arranged on the bridge pier 8.
The structure of described the utility model rail beam 1 comprises: top flange 2, web 4, top surface of the beam 15, on top surface of the beam 15, be set with support rail platform 13, and support rail platform 13 connects and supporting rail row 16, and rail row 16 is provided with perpendicular reaction rail 14; Described rail beam 1 supported two ends on bridge pier 8 are solid, are wide or big up and small down shape about hollow and cross section are in the rail beam 1 between the bridge pier strong point; In the outside of described web 4 water conservancy diversion rail support 11 is installed, water conservancy diversion rail support 11 is provided with water conservancy diversion rail 12.Described water conservancy diversion rail support 11 is installed water conservancy diversion rail 12 and is convenient to power to maglev vehicle.
The cross sectional shape of rail beam 1 is rectangle, U-shaped, V-arrangement between the bridge pier strong point.
Cross sectional shape as Fig. 2, rail beam shown in Figure 31 is a U-shaped; The cross sectional shape of rail beam 1 is a rectangle as shown in Figure 4; The cross sectional shape of rail beam 1 is a V-arrangement as shown in Figure 5.9 parts are widened to the square-section at the bottom of the beam at bridge pier 8 tops, with erection support 7.
Described rail row has following dual mode with support rail platform and rail beam syndeton:
A kind ofly be: an end of reinforcing bar is embedded in rail beam 1 top, and support rail platform 13 backs that the other end of reinforcing bar passes cast are inserted and are fixed on rail and arrange 16 bottoms.
Another kind is: an end of stone bolt 17 is fixed on rail and arranges 16 bottoms, and the other end of stone bolt 17 passes support rail platform 13 backs that are fixed as one with it and inserts in the preformed hole at rail beam 1 top, and concrete spouting rail beam top preformed hole is fixedly connected.
Described rail beam in the structure at curve paragraph place is: the cross section of rail beam is plain bending and cross section rotation with curved section track plan and superelevation, keeps rail row 16 parallel with the top surface of the beam 15 of rail beam 1, is convenient to the installation of reaction rail 14 and water conservancy diversion rail 12.

Claims (5)

1. low-speed maglev train rail beam in a kind, described rail beam is made of concrete component, these rail beam two ends are by the seat supports that is arranged on the bridge pier, its structure comprises: top flange, web, top surface of the beam, it is characterized in that, top surface of the beam is set with the support rail platform, and the support rail platform connects and supporting rail row, and rail row is provided with perpendicular reaction rail; Described rail beam supported two ends on bridge pier are solid, are wide or big up and small down shape about hollow and cross section are in the rail beam between the bridge pier strong point; In the outside of described web water conservancy diversion rail support is installed, water conservancy diversion rail support is provided with the water conservancy diversion rail.
2. according to the middle low-speed maglev train rail beam described in the claim 1, it is characterized in that the cross sectional shape of rail beam is rectangle, U-shaped, V-arrangement between the described bridge pier strong point.
3. according to the middle low-speed maglev train rail beam described in the claim 1, it is characterized in that, described rail row with support rail platform and rail beam syndeton is: an end of reinforcing bar is embedded in the rail beam top, and the other end of reinforcing bar passes to insert behind the support rail platform of cast and is fixed on rail row bottom.
4. according to the middle low-speed maglev train rail beam described in the claim 1, it is characterized in that, described rail row with support rail platform and rail beam syndeton is: an end of stone bolt is fixed on rail row bottom, the other end of stone bolt inserts in the preformed hole at rail beam top after passing the support rail platform that is fixed as one with it, and concrete spouting rail beam top preformed hole is fixedly connected.
5. according to the middle low-speed maglev train rail beam described in the claim 1, it is characterized in that, described rail beam in the structure at curve paragraph place is: the cross section of rail beam is plain bending and cross section rotation with curved section track plan and superelevation, keeps rail row parallel with the top surface of the beam of rail beam.
CN2009203089219U 2009-08-26 2009-08-26 Rail track of maglev train with middle and low-speed Expired - Lifetime CN201473871U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203089219U CN201473871U (en) 2009-08-26 2009-08-26 Rail track of maglev train with middle and low-speed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203089219U CN201473871U (en) 2009-08-26 2009-08-26 Rail track of maglev train with middle and low-speed

Publications (1)

Publication Number Publication Date
CN201473871U true CN201473871U (en) 2010-05-19

Family

ID=42410118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203089219U Expired - Lifetime CN201473871U (en) 2009-08-26 2009-08-26 Rail track of maglev train with middle and low-speed

Country Status (1)

Country Link
CN (1) CN201473871U (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103966951A (en) * 2014-05-14 2014-08-06 中铁二院工程集团有限责任公司 Elastic strip pressing type low and medium speed magnetic levitation traffic system track stretching adjusting structure
CN104480810A (en) * 2014-12-11 2015-04-01 中铁第四勘察设计院集团有限公司 Medium-and-low speed magnetic levitation railway low route continuous framework type bearing rail beam structure and construction method
CN105297561A (en) * 2015-08-10 2016-02-03 中铁二十三局集团轨道交通工程有限公司 Medium and low speed prefabricated reinforced concrete magnetic levitation beam and manufacturing method thereof
CN105401493A (en) * 2015-12-08 2016-03-16 成都科创佳思科技有限公司 Frame type rail bearing beam structure
CN106283971A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line excavation location pile foundation joist type support rail girder construction
CN106283970A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev two-wire embankment location detached pier pillar support rail beam transition section structure
CN106283955A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN106436496A (en) * 2016-09-15 2017-02-22 中铁第四勘察设计院集团有限公司 Composite bearing trail beam transition section structure of pile foundation at fill section of medium-low speed magnetic levitation singlet line
CN106436497A (en) * 2016-09-15 2017-02-22 中铁第四勘察设计院集团有限公司 Independent pier stud type bearing rail beam structure at fill sections of double lines in medium-low speed magnetic levitation traffic engineering
CN106758556A (en) * 2016-09-15 2017-05-31 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering two-wire excavation location pile foundation joist type support rail girder construction
CN108621857A (en) * 2018-04-20 2018-10-09 西南交通大学 Suspension type maglev vehicle and rail system
CN109457558A (en) * 2018-10-15 2019-03-12 中铁磁浮交通投资建设有限公司 A kind of beam-rail integration medium-and low-speed maglev track girder
CN114808564A (en) * 2022-05-20 2022-07-29 西南交通大学 Track structure suitable for medium-low speed maglev train and installation method thereof

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103966951A (en) * 2014-05-14 2014-08-06 中铁二院工程集团有限责任公司 Elastic strip pressing type low and medium speed magnetic levitation traffic system track stretching adjusting structure
CN103966951B (en) * 2014-05-14 2015-12-30 中铁二院工程集团有限责任公司 Spring pressing type medium-and low-speed maglev traffic system rail telescopic adjustment structure
CN104480810A (en) * 2014-12-11 2015-04-01 中铁第四勘察设计院集团有限公司 Medium-and-low speed magnetic levitation railway low route continuous framework type bearing rail beam structure and construction method
CN104480810B (en) * 2014-12-11 2016-05-04 中铁第四勘察设计院集团有限公司 Low circuit continuous frame formula support rail girder construction and the construction method thereof of putting of middle low speed magnetic suspension
CN105297561A (en) * 2015-08-10 2016-02-03 中铁二十三局集团轨道交通工程有限公司 Medium and low speed prefabricated reinforced concrete magnetic levitation beam and manufacturing method thereof
CN105401493A (en) * 2015-12-08 2016-03-16 成都科创佳思科技有限公司 Frame type rail bearing beam structure
CN106436497A (en) * 2016-09-15 2017-02-22 中铁第四勘察设计院集团有限公司 Independent pier stud type bearing rail beam structure at fill sections of double lines in medium-low speed magnetic levitation traffic engineering
CN106283971B (en) * 2016-09-15 2017-11-17 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line excavation location pile foundation joist type support rail girder construction
CN106283955A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN106436496A (en) * 2016-09-15 2017-02-22 中铁第四勘察设计院集团有限公司 Composite bearing trail beam transition section structure of pile foundation at fill section of medium-low speed magnetic levitation singlet line
CN106283971A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line excavation location pile foundation joist type support rail girder construction
CN106758556A (en) * 2016-09-15 2017-05-31 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering two-wire excavation location pile foundation joist type support rail girder construction
CN106283970B (en) * 2016-09-15 2017-11-14 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev two-wire embankment location independence pier stud type support rail beam transition section structure
CN106283970A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev two-wire embankment location detached pier pillar support rail beam transition section structure
CN106283955B (en) * 2016-09-15 2017-12-12 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN106758556B (en) * 2016-09-15 2018-04-10 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering two-wire excavation location pile foundation joist type support rail girder construction
CN108621857A (en) * 2018-04-20 2018-10-09 西南交通大学 Suspension type maglev vehicle and rail system
CN108621857B (en) * 2018-04-20 2023-06-23 西南交通大学 Suspension type magnetic levitation vehicle and track system
CN109457558A (en) * 2018-10-15 2019-03-12 中铁磁浮交通投资建设有限公司 A kind of beam-rail integration medium-and low-speed maglev track girder
CN114808564A (en) * 2022-05-20 2022-07-29 西南交通大学 Track structure suitable for medium-low speed maglev train and installation method thereof
CN114808564B (en) * 2022-05-20 2023-02-17 西南交通大学 Track structure suitable for medium-low speed maglev train and installation method thereof

Similar Documents

Publication Publication Date Title
CN201473871U (en) Rail track of maglev train with middle and low-speed
CN101054793A (en) Middle and low speed magnetic levitation track girder
CN202482710U (en) Floating ballast bed of prefabricated short plate
CN103590315B (en) Public iron is with layer great cantilever steel box-girder
CN204875390U (en) Low -speed magnetic suspension roof beam among precast reinforced concrete
CN201102544Y (en) Hanging train traffic system of hanging rail
CN105568786B (en) Overhanging combination box track roof beam suspension system of suspension type monorail transit bottom plate
CN201347538Y (en) Integral movable-type bracket of steel-concrete combination beam
CN100465376C (en) High speed magnetic suspension superimposition rail beam connection mechanism, rail beam and its producing method
CN214831554U (en) High-speed magnetic suspension roadbed structure
CN201321598Y (en) Multi-directionally displaced bridge expansion joint
CN105544322B (en) A kind of discrete type pillar track bridge system of maintenance in magnetic suspension train storehouse
CN108824104B (en) Suspension type track traffic double-line concrete pier beam system
CN213804840U (en) Damper device suitable for seamless bridge
CN205474626U (en) Concrete track roof beam that bottom plate opening, roof hung
CN105586813B (en) Suspended monorail traffic bottom plate opening combined box type track beam suspension system
CN205276073U (en) Two line track roof beams of rail formula track traffic are embraced in magnetic suspension
CN201016200Y (en) Magnetic levitation orbit beam
CN201390928Y (en) Support rail continuous beam in double track railway
CN206956534U (en) A kind of railway and track traffic suspended beam type Frame Pier
CN202577061U (en) Prefabricated floating slab
CN211006170U (en) High-speed magnetic levitation traffic steel-concrete combined structure track slab
CN205474783U (en) Combination box track roof beam that bottom plate is overhanging, roof hung
CN210561505U (en) Beam-rail integrated medium-low speed magnetic levitation track beam containing pi-shaped track
CN210561503U (en) High-speed magnetic levitation track containing longitudinal and transverse beam type track panel and bridge beam structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 300142 Hebei District, Zhongshan Road, No. 10,

Patentee after: China Railway Design Group Limited

Address before: 300142 Hebei District, Zhongshan Road, No. 10,

Patentee before: China Railway Third Survey and Design Institute Group Ltd.

CP01 Change in the name or title of a patent holder
CX01 Expiry of patent term

Granted publication date: 20100519

CX01 Expiry of patent term