CN201460936U - Filling timbering hydraulic support - Google Patents

Filling timbering hydraulic support Download PDF

Info

Publication number
CN201460936U
CN201460936U CN2009200927835U CN200920092783U CN201460936U CN 201460936 U CN201460936 U CN 201460936U CN 2009200927835 U CN2009200927835 U CN 2009200927835U CN 200920092783 U CN200920092783 U CN 200920092783U CN 201460936 U CN201460936 U CN 201460936U
Authority
CN
China
Prior art keywords
base
hinged
jack
filling
wall supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009200927835U
Other languages
Chinese (zh)
Inventor
程凯
张学东
王长江
韩山岭
蒋继莲
张凯
燕燕
卫智慧
张煜铖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Caterpillar Zhengzhou Ltd
Original Assignee
Zhengzhou Siwei Mechanical and Electrical Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Siwei Mechanical and Electrical Manufacturing Co Ltd filed Critical Zhengzhou Siwei Mechanical and Electrical Manufacturing Co Ltd
Priority to CN2009200927835U priority Critical patent/CN201460936U/en
Application granted granted Critical
Publication of CN201460936U publication Critical patent/CN201460936U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

A filling timbering hydraulic support comprises a base, a top beam, an upright post, a four-bar linkage mechanism and a protecting wall. A shielding beam, a front linkage, a rear linkage and the base are mutually hinged to form the four-bar linkage mechanism, the rear end of the top beam is equipped with an expansion beam, the rear portion of the top beam is hinged with the front end of a jack of the expansion beam, the rear end of the jack of the expansion beam is hinged with the expansion beam, a sliding pair is arranged between the expansion beam and the top beam through a sliding groove structure, the shielding beam is equipped with a shielding beam side protecting plate, the rear linkage is equipped with a rear linkage side protecting plate, and the tail end of the base is hinged with a gangue baffle screen along the width direction of the base. The expansion beam and a rear protecting wall support a mined-out area, after the support moves forwards to achieve a step pitch, a work surface and the support are aligned, the expansion beam and the rear protecting wall are retracted, the side protecting plates of the shielding beam and the rear linkage are driven to open via the jack and form rubber pressing seal with a side protecting plate of an adjacent frame, and then a partition wall is built conveniently and fast along a work surface so as to partition a paste body for filing and prevent leakage, thereby beginning to start filling operation.

Description

The filling and support hydraulic support
Technical field:
The utility model relates to coal mine machinery, particularly hydraulic support, be specifically a kind of can be to the filling and support hydraulic support of mining and fill area carries out supporting simultaneously.
Background technology:
Rich coal resources in China, the fully-mechanized mining equipment maturation, coal winning technology is gradually improved, in short supply along with the energy, the quickening day by day of coal in China exploitation paces, increasing mine is faced with the resource exhaustion problem, presses the coal problem for solving " three times ", China presses coal by adopting multiple technologies measure liberation " three times " such as traditional band exploitation, resettlement village, filling mining, improves coal mining rate.But along with the increase of mining depth, the raising of the increase of village migration cost and filling technique technological level, the filling mining technology has become flourish gesture.Existing filling and support integrated bracket needs to construct divider wall along work plane separately mostly, inconvenient operation, and efficient is low; Simultaneously, existing divider wall sealing performance is good inadequately, and lotion can enter work plane by spillage when filling, influences exploitation work, also influences filling effect.
The utility model content:
The purpose of this utility model is to provide a kind of filling and support hydraulic support, described this filling and support hydraulic support will solve in the prior art hydraulic support and construct the divider wall inconvenience, the existing simultaneously easy spillage of divider wall and influence the technical problem of exploitation work and filling effect.
The purpose of this utility model is achieved through the following technical solutions: comprise base, back timber, be articulated in the column between back timber and the base, quadric chain and wall supporting constitute, the base rear portion is hinged with front rod and back link, the back timber rear portion is hinged with caving shield, the upper end of caving shield lower end and front rod and back link is hinged, caving shield, front rod, the mutually hinged formation quadric chain of back link and base, wall supporting is located at the back timber front end by the wall supporting jack, wherein, top beam rear end is a body structure, in top beam rear end, also be provided with extensible canopy, top beam rear end is inner hinged with extensible canopy jack front end, extensible canopy jack rear end and extensible canopy are hinged, caving shield is provided with the caving shield side guard board, be provided with jack along the base width between caving shield side guard board and the caving shield, back link is provided with the back link side guard board, is provided with another jack along the base width between back link side guard board and the back link, and the base tail end is hinged with retaining cash curtain along the base width.
The extensible canopy rear end is hinged with the back wall supporting, is provided with back wall supporting jack between back wall supporting and the extensible canopy rear end, and back wall supporting is provided with back wall supporting side guard board.
Caving shield side guard board and back link side guard board are provided with rubber outer.
Retaining cash curtain is hinged by two pin joints and base.
Described wall supporting and extensible canopy adopt plate muscle welded construction, and back wall supporting also adopts plate muscle welded construction.
Described back timber, front rod and back link adopt monolithic high strength casing welded construction.
Gap bridge easy opened high strength casing welded construction is with in described base employing, is provided with between the base crotch and passes framework and pass jack, and passing jack two ends are hinged with passing framework and base respectively.
It is hinged that the articulated form of base and front rod and back link is the single shaft hole.
Operating principle of the present utility model is: with the carrying out of work plane coal mining, what the support reach formed treats that the filling space is by the extensible canopy at back timber rear portion and face guard supporting afterwards, guarantee that inbreak does not take place the filling front top plate, the amount of crushing is in control range, after reaching step pitch, force piece straightening alignment, the side guard board of caving shield and back link opens under the jack effect, and form the rubber extruded sealing with the side guard board of adjacent frame, be built into the anti-pierced wall of isolation along work plane, back extensible canopy and back face guard are regained, and begin to carry out filling operation.
The utility model is compared with prior art, and its effect is actively with tangible.Be provided with extensible canopy beam and extensible canopy beam jack at top beam rear end in the filling and support hydraulic support of the present utility model, support the goaf, on caving shield and back link, be provided with side guard board, what the support reach formed treats that the filling space is by the balance arm supporting, guarantee that inbreak does not take place the filling front top plate, the amount of crushing is in control range, after reaching step pitch, force piece straightening alignment, extensible canopy is regained, then the side guard board of caving shield and back link by jack drive open and with the side guard board extruding formation sealing of adjacent frame, be built into divider wall along work plane quickly and easily, isolate the lotion that filling is used, prevent to reveal, begin to carry out filling operation.The back wall supporting is set behind extensible canopy, driving the back wall supporting by back wall supporting jack stretches out and can enlarge the supporting scope for the treatment of the filling space, the back wall supporting is provided with back wall supporting side guard board simultaneously, when extensible canopy and back wall supporting withdrawal, back wall supporting side guard board forms sealing with caving shield and contacts, and is convenient to filling operation and carries out.If be provided with the side guard board extruding formation rubber seal that rubber outer can make adjacent stent at caving shield side guard board and back link side guard board, be built into along work plane and isolate anti-pierced wall, strengthen the leak preventing effect of divider wall, improve filling effect.
Description of drawings:
Fig. 1 is the structural representation of filling and support hydraulic support first embodiment of the present utility model.
Fig. 2 is the vertical view of base among Fig. 1.
The specific embodiment:
Embodiment 1:
As depicted in figs. 1 and 2, this filling and support hydraulic support of the present utility model, in the present embodiment, comprise base 15, back timber 3, be articulated in the column 18 between back timber and the base, quadric chain and wall supporting 1 constitute, base 15 rear portions are hinged with front rod 11 and back link 12, back timber 3 rear portions are hinged with caving shield 9, the upper end of caving shield 9 lower ends and front rod 11 and back link 12 is hinged, caving shield 9, front rod 11, back link 12 and base 15 mutually hinged formation quadric chains, wall supporting 1 is located at back timber 3 front ends by wall supporting jack 2, wherein, back timber 3 rear ends are body structure, in back timber 3 rear ends, also be provided with extensible canopy 4, back timber 3 rear ends are inner hinged with extensible canopy jack 5 front ends, extensible canopy jack 5 rear ends and extensible canopy 4 are hinged, caving shield 9 is provided with caving shield side guard board 10, be provided with jack (not drawing among the figure) along the base width between caving shield side guard board 10 and the caving shield 9, back link 12 is provided with back link side guard board 13, be provided with another jack (not drawing among the figure) along the base width between back link side guard board 13 and the back link 12, the side guard board of caving shield and back link is a telescopic structure, stretch out by the jack effect in the time of need constructing divider wall, under the jack effect, to regain when not required. base 15 tail ends are hinged with retaining cash curtain 14 along the base width, retaining cash curtain 14 adopts plate muscle welded construction, retaining cash curtain 14 is hinged by two pin joints and base 15, in case backstop cash curtain rotates, be used to discharge the spoil that enters work plane on the one hand, can prevent again that on the other hand the lotion slip from entering work plane. extensible canopy 4 rear ends are hinged with back wall supporting 6, be provided with back wall supporting jack 7 between back wall supporting 6 and extensible canopy 4 rear ends, back wall supporting 6 is provided with back wall supporting side guard board 8, when extensible canopy 4 and 6 withdrawals of back wall supporting, back wall supporting side guard board 8 forms sealing with caving shield 9 and contacts, being convenient to filling operation carries out. and caving shield side guard board 10 and back link side guard board 13 are provided with rubber outer, when the caving shield side guard board of adjacent two supports and back link side guard board are all opened, their mutual extrusion form the sealing contact, construct divider wall along work plane. described wall supporting 1, back wall supporting 6 and extensible canopy 4 adopt plate muscle welded construction. described back timber 3, front rod 11 and back link 12 adopt monolithic high strength casing welded construction. and described base 15 adopts band gap bridge easy opened high strength casing welded construction, be provided with between the base crotch and pass framework 16 and pass jack 17, passing jack 17 two ends are hinged with passing framework 16 and base 15 respectively. and it is hinged that the articulated form of base and front rod and back link is the single shaft hole.
During concrete work, carrying out with the work plane coal mining, what the support reach formed treats that the filling space is by the extensible canopy at back timber rear portion and face guard supporting afterwards, guarantee that inbreak does not take place the filling front top plate, the amount of crushing is in control range, after reaching step pitch, force piece straightening alignment, the side guard board of caving shield and back link opens under the jack effect, and form the rubber extruded sealing with the side guard board of adjacent frame, be built into the anti-pierced wall of isolation along work plane, back extensible canopy and back face guard are regained, and begin to carry out filling operation.
Except technique scheme, the base rear portion can be provided with that a retaining protects riser or retaining cash seat is realized keeping off cash and isolated lotion.

Claims (8)

1. filling and support hydraulic support, comprise base, back timber, be articulated in the column between back timber and the base, quadric chain and wall supporting constitute, the base rear portion is hinged with front rod and back link, the back timber rear portion is hinged with caving shield, the upper end of caving shield lower end and front rod and back link is hinged, caving shield, front rod, the mutually hinged formation quadric chain of back link and base, wall supporting is located at the back timber front end by the wall supporting jack, it is characterized in that: top beam rear end is a body structure, in top beam rear end, also be provided with extensible canopy, top beam rear end is inner hinged with extensible canopy jack front end, extensible canopy jack rear end and extensible canopy are hinged, caving shield is provided with the caving shield side guard board, be provided with jack along the base width between caving shield side guard board and the caving shield, back link is provided with the back link side guard board, is provided with another jack along the base width between back link side guard board and the back link, and the base tail end is hinged with retaining cash curtain along the base width.
2. filling and support hydraulic support as claimed in claim 1 is characterized in that: the extensible canopy rear end is hinged with the back wall supporting, is provided with back wall supporting jack between back wall supporting and the extensible canopy rear end, and back wall supporting is provided with back wall supporting side guard board.
3. filling and support hydraulic support as claimed in claim 1 is characterized in that: caving shield side guard board and back link side guard board are provided with rubber outer.
4. filling and support hydraulic support as claimed in claim 1 is characterized in that: retaining cash curtain is hinged by two pin joints and base.
5. filling and support hydraulic support as claimed in claim 1 is characterized in that: described wall supporting and extensible canopy adopt plate muscle welded construction.
6. filling and support hydraulic support as claimed in claim 1 is characterized in that: described back timber, front rod and back link adopt monolithic high strength casing welded construction.
7. filling and support hydraulic support as claimed in claim 1, it is characterized in that: described base adopts band gap bridge easy opened high strength casing welded construction, be provided with between the base crotch and pass framework and pass jack, passing jack two ends are hinged with passing framework and base respectively.
8. filling and support hydraulic support as claimed in claim 1 is characterized in that: it is hinged that the articulated form of base and front rod and back link is the single shaft hole.
CN2009200927835U 2009-09-02 2009-09-02 Filling timbering hydraulic support Expired - Fee Related CN201460936U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200927835U CN201460936U (en) 2009-09-02 2009-09-02 Filling timbering hydraulic support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200927835U CN201460936U (en) 2009-09-02 2009-09-02 Filling timbering hydraulic support

Publications (1)

Publication Number Publication Date
CN201460936U true CN201460936U (en) 2010-05-12

Family

ID=42388290

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200927835U Expired - Fee Related CN201460936U (en) 2009-09-02 2009-09-02 Filling timbering hydraulic support

Country Status (1)

Country Link
CN (1) CN201460936U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102269000A (en) * 2010-06-01 2011-12-07 郑州四维机电设备制造有限公司 Front frame of integral paste filling and supporting hydraulic bracket
CN102465707A (en) * 2010-11-14 2012-05-23 林州重机集团股份有限公司 High-inclination-angle hydraulic support
CN102562110A (en) * 2010-12-17 2012-07-11 郑州四维机电设备制造有限公司 Integrated hydraulic support of four-post paste filling supporting in thin coal seam
CN108506035A (en) * 2018-05-07 2018-09-07 郑州煤矿机械集团股份有限公司 Big working resistance advanced hydraulic support for air return lane

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102269000A (en) * 2010-06-01 2011-12-07 郑州四维机电设备制造有限公司 Front frame of integral paste filling and supporting hydraulic bracket
CN102269000B (en) * 2010-06-01 2012-07-25 郑州四维机电设备制造有限公司 Front frame of integral paste filling and supporting hydraulic bracket
CN102465707A (en) * 2010-11-14 2012-05-23 林州重机集团股份有限公司 High-inclination-angle hydraulic support
CN102562110A (en) * 2010-12-17 2012-07-11 郑州四维机电设备制造有限公司 Integrated hydraulic support of four-post paste filling supporting in thin coal seam
CN102562110B (en) * 2010-12-17 2014-04-02 郑州四维机电设备制造有限公司 Integrated hydraulic support of four-post paste filling supporting in thin coal seam
CN108506035A (en) * 2018-05-07 2018-09-07 郑州煤矿机械集团股份有限公司 Big working resistance advanced hydraulic support for air return lane

Similar Documents

Publication Publication Date Title
CN201460935U (en) Filling timbering integrated hydraulic support
CN201874597U (en) Tetrastyle paste filling timbering hydraulic support used in thin coal seam
CN201606089U (en) Supporting and filling integrated hydraulic bracket
CN201460936U (en) Filling timbering hydraulic support
CN202047852U (en) Twin-station two-column low-position top coal caving hydraulic bracket
CN102168572A (en) Waste filling supporting bracket
CN201554481U (en) Filling supporting hydraulic support
CN201714412U (en) Hydraulic support for non-solid-filled working face
CN102168567A (en) Filling supporting partition board bracket
CN201460934U (en) Filling timbering hydraulic support
CN201606097U (en) Waste rock filling supporting bracket
CN201661307U (en) Filling supporting barrier bracket
CN201606098U (en) Basic bracket of filling support
CN201661308U (en) Basic stand of filling support
CN103104277B (en) A kind of multi-pace band tail boom brace type filling hydraulic support
CN202300450U (en) Transition hydraulic support for gob-side entry retaining
CN102168571A (en) Basic bracket for filing support
CN102536284A (en) Tetrastyle paste filling timbering hydraulic support for thin coal seam
CN201460942U (en) Mining and filling hydraulic bracket
CN102003196B (en) Integrated hydraulic support for mining and filling
CN102828762B (en) Backstop gangue beam suspension swinging beam type gangue filing hydraulic support frame with side protection plate
CN201513189U (en) Rear support of stowing hydraulic support
CN204283455U (en) Novel thin coal seam filling hydraulic support
CN201568067U (en) Integrated fully mechanized top-coal caving face end support frame
CN201661306U (en) Hydraulic support frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CATERPILLAR (ZHENGZHOU) CO., LTD.

Free format text: FORMER NAME: ZHENGZHOU SIWEI ELECTROMECHANICAL EQUIPMENT MANUFACTURING CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 450001 No. 7 shuttle Road, hi tech Industrial Development Zone, Henan, Zhengzhou

Patentee after: Caterpillar (Zhengzhou) Co., Ltd.

Address before: 450001 No. 7 shuttle Road, hi tech Industrial Development Zone, Henan, Zhengzhou

Patentee before: Zhengzhou Siwei Electromechanical Equipment Manufacturing Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100512

Termination date: 20170902

CF01 Termination of patent right due to non-payment of annual fee