CN201450254U - Hanger frame for mounting power switch - Google Patents

Hanger frame for mounting power switch Download PDF

Info

Publication number
CN201450254U
CN201450254U CN200920042528XU CN200920042528U CN201450254U CN 201450254 U CN201450254 U CN 201450254U CN 200920042528X U CN200920042528X U CN 200920042528XU CN 200920042528 U CN200920042528 U CN 200920042528U CN 201450254 U CN201450254 U CN 201450254U
Authority
CN
China
Prior art keywords
rod
anchor ear
vertical rod
fixedly connected
power switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200920042528XU
Other languages
Chinese (zh)
Inventor
高金林
杨棣康
张伟
林晓兵
陈登保
丁永贵
郑一鸣
基学林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YIZHENG POWER SUPPLY Co OF JIANGSU ELECTRIC POWER Co
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Yangzhou Power Supply Co of Jiangsu Electric Power Co
Original Assignee
YIZHENG POWER SUPPLY Co OF JIANGSU ELECTRIC POWER Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YIZHENG POWER SUPPLY Co OF JIANGSU ELECTRIC POWER Co filed Critical YIZHENG POWER SUPPLY Co OF JIANGSU ELECTRIC POWER Co
Priority to CN200920042528XU priority Critical patent/CN201450254U/en
Application granted granted Critical
Publication of CN201450254U publication Critical patent/CN201450254U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Driving Mechanisms And Operating Circuits Of Arc-Extinguishing High-Tension Switches (AREA)

Abstract

A hanger frame for mounting a power switch relates to a tool for electric construction, and includes an upper anchor ear, a lower anchor ear, an upper hanger arm, a lower hanger arm, a main hoist rod, a vertical rod and a support rod. The upper and the lower hanger arms are horizontally arranged and fixedly connected to the upper anchor ear and the lower anchor ear respectively; the vertical rod is fixedly connected between the upper hanger arm and the lower hanger arm; the main hoist rod is horizontally arranged,; one end of the main hoist rod and one end of the support rod, which faces to the vertical rod, are respectively and movably connected with the vertical rod; and the other end of the support rod is fixedly connected with the middle of the main hoist rod. The hanger frame for mounting the power switch changes the original hoisting manner, keeps an enough safe distance with an upper-layer electrified line, and achieves the purpose of increase in construction safety factors.

Description

Power switch is installed suspension bracket
Technical field
The utility model relates to a kind of power construction frock, and the travelling cradle of power switch specifically is installed.
Background technology
Along with deepening continuously of power grid construction, what line switching was a large amount of applies in the 10KV circuit, our power engineering company only, and the annual 10KV switch of installing just has nearly 50, wherein mostly is to install under live state.The installation switch that do not have a power failure on the bar, traditional way are to utilize the automobile lifting; Or the bolt sling is hung pulley on electric pole, finishes with the method for strand mill lifting.The former is subjected to landform restriction, expense height, potential safety hazard is arranged (with the difficult control of the safe distance on upper strata); Latter's expense is low, but the difficult control in sling position, the switch lifting is uneven, need have a power failure to install, and do not have the danger of electric shock, but switch may contact, collide with electric pole.
The utility model content
The utility model provides a kind of lifting balance at above problem, guarantee not contacted, collide with electric pole by hanging piece, and environmental suitability height, the reliable power switch of operation is installed suspension bracket.
The technical solution of the utility model is: it comprises anchor ear, following anchor ear, upper cantilever, lower cantalever, main suspension rod, vertical rod and strut, upper cantilever, lower cantalever all are horizontally disposed with and are fixedly connected on respectively on anchor ear, the following anchor ear, vertical rod is fixedly connected between upper cantilever, the lower cantalever, main suspension rod is horizontally disposed with, main suspension rod, strut flexibly connect with vertical rod respectively towards an end of vertical rod, and the other end of strut is fixedly connected on main suspension rod middle part.
Between main suspension rod and vertical rod, be provided with locking device.
It is fixing point that the utility model has adopted the fixedly anchor ear that connects electric pole, and main suspension rod is regulated left and right directions by be rotatably connected with the vertical rod activity (pivot joint).For guaranteeing control to left and right directions, on the suspension rod drive-connecting shaft, establish locking device, can guarantee that the suspension rod stationary positioned is on any circumferential position.About suspension centre, for security consideration, do not advocate that it can be free to slide, three fixing points are set, can be according to the switch of Different Weight, type, it is just passable to select suitable suspension centre to hang pulley.The utility model will because vertical rod links to each other with anchor ear by cantilever, be made between vertical rod and the electric pole to have kept certain distance by after hanging piece (switch) lifting, can avoid being bumped by hanging piece and electric pole.Play Hanging roller and be installed on main suspension rod bar bottom, leave shaft, steadily lifting has changed original lifting pattern, has kept enough safe distances with the epipelagic zone electric line, reaches the purpose that improves the construction safety coefficient.
Description of drawings
Fig. 1 is a structural representation of the present utility model
1 is following anchor ear among the figure, the 2nd, and electric pole, the 3rd, last anchor ear, the 4th, upper cantilever, the 5th, locking device, the 6th, last hinge device, the 7th, main suspension rod, the 8th, hanger, the 9th, strut, the 10th, vertical rod, the 11st, following hinge device, the 12nd, lower cantalever.
Fig. 2 is the vertical view of Fig. 1
Embodiment
The utility model such as Fig. 1, shown in 2, it comprises and is used for fixing last anchor ear 3 and the following anchor ear 1 that connects electric pole 2, fixedly connected horizontally disposed upper cantilever 4 on last anchor ear 3 and the following anchor ear 1 respectively, lower cantalever 12, at upper cantilever 4, fixedly connected vertical rod 10 between the lower cantalever 12, main suspension rod 7 is horizontally disposed with, main suspension rod 7, strut 9 passes through last hinge device 6 respectively towards an end of vertical rod 10, following hinge device 11 flexibly connects with vertical rod 10, the other end of strut 9 is fixedly connected on main suspension rod 7 middle parts. and main suspension rod 7 other ends are provided with a plurality of hangers 8. to be stopped in a certain position for making main suspension rod 7, is provided with locking device 5. between main suspension rod 7 and vertical rod 10

Claims (2)

1. power switch is installed suspension bracket, it is characterized in that, it comprises anchor ear, following anchor ear, upper cantilever, lower cantalever, main suspension rod, vertical rod and strut, upper cantilever, lower cantalever all are horizontally disposed with and are fixedly connected on respectively on anchor ear, the following anchor ear, vertical rod is fixedly connected between upper cantilever, the lower cantalever, main suspension rod is horizontally disposed with, and main suspension rod, strut flexibly connect with vertical rod respectively towards an end of vertical rod, and the other end of strut is fixedly connected on main suspension rod middle part.
2. power switch according to claim 1 is installed suspension bracket, it is characterized in that, is provided with locking device between main suspension rod and vertical rod.
CN200920042528XU 2009-06-23 2009-06-23 Hanger frame for mounting power switch Expired - Fee Related CN201450254U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920042528XU CN201450254U (en) 2009-06-23 2009-06-23 Hanger frame for mounting power switch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920042528XU CN201450254U (en) 2009-06-23 2009-06-23 Hanger frame for mounting power switch

Publications (1)

Publication Number Publication Date
CN201450254U true CN201450254U (en) 2010-05-05

Family

ID=42554977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920042528XU Expired - Fee Related CN201450254U (en) 2009-06-23 2009-06-23 Hanger frame for mounting power switch

Country Status (1)

Country Link
CN (1) CN201450254U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104638553A (en) * 2015-03-13 2015-05-20 国网上海市电力公司 180-degree rotary reinforced concrete pole lazy arm
CN104682210A (en) * 2015-03-23 2015-06-03 国家电网公司 Single-pole switch frame for 10 KV line
CN105552757A (en) * 2016-01-15 2016-05-04 国网浙江省电力公司湖州供电公司 Portable distribution transformer lifting frame
CN107171231A (en) * 2017-06-06 2017-09-15 国网江苏省电力公司高邮市供电公司 A kind of distribution box job platform
CN107769078A (en) * 2017-11-20 2018-03-06 国网湖北省电力公司宜昌供电公司 The multifunction insulating bar hanging rack of 10kV insulating bar working systems
CN109510092A (en) * 2018-12-28 2019-03-22 宁波甬新东方电气有限公司 A kind of installing mechanism and installation method of pole-mounted circuit breaker
CN110654991A (en) * 2019-11-06 2020-01-07 国网新疆电力有限公司阿克苏供电公司 Portable hoisting support
CN111790077A (en) * 2020-08-06 2020-10-20 国网黑龙江省电力有限公司哈尔滨供电公司 Insulating bearing rescue device

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104638553A (en) * 2015-03-13 2015-05-20 国网上海市电力公司 180-degree rotary reinforced concrete pole lazy arm
CN104682210A (en) * 2015-03-23 2015-06-03 国家电网公司 Single-pole switch frame for 10 KV line
CN104682210B (en) * 2015-03-23 2017-01-18 国家电网公司 Single-pole switch frame for 10 KV line
CN105552757A (en) * 2016-01-15 2016-05-04 国网浙江省电力公司湖州供电公司 Portable distribution transformer lifting frame
CN107171231A (en) * 2017-06-06 2017-09-15 国网江苏省电力公司高邮市供电公司 A kind of distribution box job platform
CN107171231B (en) * 2017-06-06 2023-05-05 国网江苏省电力有限公司高邮市供电分公司 Block terminal operation platform
CN107769078A (en) * 2017-11-20 2018-03-06 国网湖北省电力公司宜昌供电公司 The multifunction insulating bar hanging rack of 10kV insulating bar working systems
CN109510092A (en) * 2018-12-28 2019-03-22 宁波甬新东方电气有限公司 A kind of installing mechanism and installation method of pole-mounted circuit breaker
CN109510092B (en) * 2018-12-28 2023-06-06 宁波甬新东方电气有限公司 Mounting mechanism and mounting method of pole-mounted circuit breaker
CN110654991A (en) * 2019-11-06 2020-01-07 国网新疆电力有限公司阿克苏供电公司 Portable hoisting support
CN111790077A (en) * 2020-08-06 2020-10-20 国网黑龙江省电力有限公司哈尔滨供电公司 Insulating bearing rescue device

Similar Documents

Publication Publication Date Title
CN201450254U (en) Hanger frame for mounting power switch
CN202755635U (en) Movable-type basket support
CN202321987U (en) Automatic lifting appliance for crucible
CN201999640U (en) Crane-cable trailing-traveling device
CN103332608B (en) GW6 disconnecting link porcelain knob is changed special pole and is hung
CN102412532A (en) Overhead line pulley device
CN204980821U (en) Pressure -bearing formula lifting device and pressure -bearing formula compensating beam
CN103738852B (en) Hoisting crane test mass device
CN2639275Y (en) Balance device of lifting article
CN205087828U (en) Simple and easy lifting device of 35kV circuit breaker
CN105366559A (en) Small hoisting machine fixed on channel steel framework
CN211444689U (en) General hoist based on bridge segment promotes
CN201530687U (en) Maintenance cantilever crane of tower crane
CN204823697U (en) Crouch and roll up hoist
CN208883427U (en) A kind of killer switch inspection trolley
CN202988576U (en) Simple and easy chain hoist lifting support
CN202721386U (en) utility model
CN202657877U (en) Circuit equipment construction lifting frame
CN110790121A (en) General hoist based on bridge segment promotes
CN202395384U (en) Operation tool for multiloop of 110-220kV electric transmission line
CN201296608Y (en) A double beam bridge crane
CN220223223U (en) Box-type substation top cap hoisting structure
CN218201818U (en) Two girder construction bale handle hoist
CN205151577U (en) Fix small -size hoisting machine on steel support of groove
CN202296821U (en) Installation structure for lifting appliance

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: YANGZHOU POWER SUPPLY CO., JIANGSU PROV ELECTRIC P

Effective date: 20121109

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20121109

Address after: 211400 No. 154 workers North Road, Yizheng, Jiangsu

Patentee after: Yizheng Power Supply Company of Jiangsu Electric Power Company

Patentee after: Yangzhou Power Supply Company of Jiangsu Electric Power Company

Patentee after: Jiangsu Electric Power Company

Patentee after: State Grid Corporation of China

Address before: 211400 No. 154 workers North Road, Yizheng, Jiangsu

Patentee before: Yizheng Power Supply Company of Jiangsu Electric Power Company

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100505

Termination date: 20170623

CF01 Termination of patent right due to non-payment of annual fee