CN201437576U - Fragment-free track-bed pouring device capable of climbing up steps - Google Patents

Fragment-free track-bed pouring device capable of climbing up steps Download PDF

Info

Publication number
CN201437576U
CN201437576U CN2009201034086U CN200920103408U CN201437576U CN 201437576 U CN201437576 U CN 201437576U CN 2009201034086 U CN2009201034086 U CN 2009201034086U CN 200920103408 U CN200920103408 U CN 200920103408U CN 201437576 U CN201437576 U CN 201437576U
Authority
CN
China
Prior art keywords
laterally
running gear
tracks
adjust
guide way
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009201034086U
Other languages
Chinese (zh)
Inventor
金守华
郭文武
葛学民
韩彦军
汪西应
刘军
李慧敏
陈永祥
李春晖
闫岢宏
刘卓
吴烨
张宏成
纪争建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHIJIAZHUANG RAILWAY INSTITUTE
HEBEI XINDADI ELECTROMECHANICAL MANUFACTURING Co Ltd
Original Assignee
SHIJIAZHUANG RAILWAY INSTITUTE
HEBEI XINDADI ELECTROMECHANICAL MANUFACTURING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHIJIAZHUANG RAILWAY INSTITUTE, HEBEI XINDADI ELECTROMECHANICAL MANUFACTURING Co Ltd filed Critical SHIJIAZHUANG RAILWAY INSTITUTE
Priority to CN2009201034086U priority Critical patent/CN201437576U/en
Application granted granted Critical
Publication of CN201437576U publication Critical patent/CN201437576U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a fragment-free track-bed pouring device capable of climbing up steps, which is characterized in that both two front transverse adjusting beams are provided with a guide body, a slide body, a hydraulic oil cylinder and a positioning body; the guide body and the hydraulic oil cylinder of each front transverse adjusting beam are fixed on a telescopic sleeve which corresponds to the front transverse adjusting beam, the bottom end of the slide body of each front transverse adjusting beam is fixedly connected with a wheel carrier of a front walking device which is connected with the front transverse adjusting beam, the top end of a piston rod of the hydraulic oil cylinder of each front transverse adjusting beam is hinged with the wheel carrier of the walking device which is connected with the front transverse adjusting beam, and the guide body and the slide body of each front transverse adjusting beam are locked by the positioning body which is used for fixedly joining the guide body and the slide body into a whole body on a plurality of opposite positions. Through a simple and flexible way, the fragment-free track-bed pouring device can successfully pass through the steps at the junction between the road bed and the bridge; moreover, the frame presents a horizontal state in the transverse direction, so the stability of the device is good.

Description

The ballastless track bed casting equipment of energy up/down steps
Technical field
The utility model relates to a kind of railway division installation apparatus, particularly a kind of ballastless track bed casting equipment of energy up/down steps.
Background technology
In the double-block type ballastless track work progress, a discrepancy in elevation has appearred in the junction of roadbed and bridge (intersection), makes the equipment (being ballastless track bed casting equipment) that is used for fluid concrete can't pass through this discrepancy in elevation smoothly.A difficult problem hereto, pertinent literature does not provide the technical scheme how to solve.
Summary of the invention
Technical problem to be solved in the utility model is, a kind of ballastless track bed casting equipment of energy up/down steps is provided, just can make this casting equipment step by producing smoothly by simple and flexible way by roadbed and bridge junction, and vehicle frame laterally is the level of state, and stabilization of equipment performance is good.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is as follows:
A kind of ballastless track bed casting equipment of energy up/down steps, have and be horizontally disposed vehicle frame, lay respectively at vehicle frame left and right sides front end be two of vertical setting before laterally adjust beam, lay respectively at rear end, the vehicle frame left and right sides be two of vertical setting after laterally adjust beam, laterally adjust two preceding running gears that beam connects as one respectively with before two, respectively with two after laterally adjust two that beam connects as one after running gear, lay respectively at auxiliary supporting leg before two of front portion, the vehicle frame left and right sides, lay respectively at auxiliary supporting leg behind two of rear portion, the vehicle frame left and right sides, laterally adjust four telescopics laterally adjusting the beam upper end behind beam and every before being individually fixed in every, laterally adjust before being used for adjusting every respectively laterally adjust beam and vehicle frame relative position behind beam and every so that adjust two preceding running gear horizontal spacings and two after four horizontal adjusting devices of running gear horizontal spacing, each supports two first tracks or two second tracks of running gear behind a preceding running gear and, laterally adjust before every laterally adjust behind beam and every beam by a telescopic above it with and a corresponding horizontal adjusting device and vehicle frame connect as one, running gear and each back running gear have respectively along the wheel of above-mentioned two first tracks or two second track travels before each, vehicle wheel frame, its technical scheme are laterally to adjust beam before above-mentioned every all to have the guide way that is vertical setting, can slide up and down and by its spacing slide mass along guide way, hydraulic jack, positioning body; Laterally adjust the guide way of beam before every, hydraulic jack is fixed on the telescopic corresponding with it, laterally the bottom of the slide mass of adjustment beam is fixedly connected with the vehicle wheel frame that should precedingly laterally adjust the preceding running gear that beam was connected before every, laterally adjust before every beam hydraulic jack the piston rod top with should before laterally to adjust the vehicle wheel frame of the preceding running gear that beam was connected hinged, before every laterally the guide way of adjustment beam and slide mass by the two is connected to one at several relative positions respectively, and slide mass is slided up and down along guide way, should precedingly laterally adjust the positioning body locking of beam.
In the technique scheme, the guide way of laterally adjusting beam before described every can be for being two square tubes of vertical setting, these two square tubes are individually fixed in the both sides, front and back of a telescopic corresponding with it, the slide mass of laterally adjusting beam before every can be for being two columns vertical setting, square, and two columns laterally adjusting the slide mass of beam before every are set with in two square tubes of its guide way; Laterally the bottom of two columns of the slide mass of adjustment beam is fixedly connected with the upper surface of the vehicle wheel frame that should precedingly laterally adjust the preceding running gear that beam was connected before every, the cylinder barrel of laterally adjusting the hydraulic jack of beam before every vertically passes with its corresponding telescopic also fixedlys connected with it, and the upper surface of the vehicle wheel frame of the preceding running gear that the piston rod top of this hydraulic jack is connected with the preceding horizontal adjustment beam at its place is hinged.The positioning body of laterally adjusting beam before above-mentioned every can comprise several the first lateral direction penetrating holes that all become to be arranged above and below on two square tubes that lay respectively at the guide way of laterally adjusting beam before this, lay respectively at several the second lateral direction penetrating holes that all become to be arranged above and below on two columns of the slide mass of laterally adjusting beam before this, several alignment pins, several in described these several alignment pins or an alignment pin pass the corresponding with it first lateral direction penetrating hole and the second lateral direction penetrating hole respectively simultaneously, and guide way and the slide mass of laterally adjusting beam before will being somebody's turn to do are fixedly connected on a certain relative position.
A kind of method of topping bar of ballastless track bed casting equipment of energy up/down steps, the walking of described casting equipment is on two first tracks or two second tracks, two first tracks, two second tracks are supported on respectively on bridge and the roadbed, step produces in the junction of bridge and roadbed, to be described casting equipment be may further comprise the steps by the method for two second tracks to the roadbed on two first tracks on the bridge at its place its technical scheme: the above-mentioned step place that 1. two preceding running gears of described casting equipment is walked to two first tracks on the bridge, before above-mentioned two, assist supporting leg on bridge, to prop respectively, will be laterally adjusting that guide way in the beam and slide mass are fixedly connected on a certain relative position before every and the positioning body release that locks, the piston rod of laterally adjusting the hydraulic jack in the beam before making every shrinks, running gear and slide mass and along the guide way disorbit that moves up before it is driven, and two preceding running gears are packed up; 2. the above-mentioned step place of two first tracks on bridge, add a cushion block respectively, each cushion block is by the bridge positioning support, the thickness of each cushion block equates with the height of its corresponding step, the upper surface of each cushion block all has track, two cushion blocks just in time be placed on respectively two preceding running gears below, the track on two cushion blocks is connected with two second tracks on the roadbed respectively; 3. before above-mentioned two, assist supporting leg to pack up, make two preceding running gears respectively along two second tracks on track on two cushion blocks and the roadbed, make that running gear moves forward along two first tracks on the bridge respectively after two, after two preceding running gears leave two tracks on the cushion block and enter two second tracks on the roadbed, take two cushion blocks away; 4. when running gear after two walks to the above-mentioned step place of two first tracks on the bridge, after two, assist supporting leg on roadbed, to prop respectively, running gear leaves two first tracks respectively after making two, laterally adjust the piston rod elongation of the hydraulic jack in the beam before making every simultaneously, making it drive guide way moves up, to guarantee that vehicle frame is the level of state, the above-mentioned step place of two first tracks on bridge, add a cushion block respectively, each cushion block is by the bridge positioning support, two cushion blocks just in time be placed on respectively running gear after two below, the track on two cushion blocks is connected with two second tracks on the roadbed respectively; 5. after above-mentioned two, assist supporting leg (5) to pack up, make two preceding running gears respectively along two second tracks on the roadbed, make that running gear moves forward along the track on two cushion blocks respectively after two, after running gear after two leaves two tracks on the cushion block and enters two second tracks on the roadbed, take two cushion blocks away, laterally adjust positioning body in the beam before making every and guide way and slide mass are fixedly connected on a certain relative position and lock.
In the technique scheme, carry out above-mentioned steps 3. with step 5. the time, can be earlier adjust the horizontal spacing of running gear behind the horizontal spacing of two preceding running gears and two by horizontal adjusting device, the wheel of being convenient to them can pass through two first tracks and two second tracks smoothly.
A kind of method of getting out of a predicament or an embarrassing situation of ballastless track bed casting equipment of energy up/down steps, the walking of described casting equipment is on two second tracks or two first tracks, two second tracks, two first tracks are supported on respectively on roadbed and the bridge, step produces in the junction of bridge and roadbed, to be described casting equipment be may further comprise the steps by the method for two first tracks to the bridge under two second tracks on the roadbed at its place its technical scheme: A, the above-mentioned step place of two first tracks on bridge, add a cushion block respectively, each cushion block is by the bridge positioning support, the thickness of each cushion block equates with the height of its corresponding step, the upper surface of each cushion block all has track, track on two cushion blocks is connected with two second tracks on the roadbed respectively, makes two preceding running gears go on the track of two cushion blocks respectively; B, auxiliary supporting leg before above-mentioned two is propped on roadbed respectively, will be laterally adjusting that guide way in the beam and slide mass are fixedly connected on a certain relative position before every and the positioning body release that locks, take two cushion blocks away, laterally adjust the piston rod elongation of the hydraulic jack in the beam before making every, running gear and slide mass and move down along guide way before it is driven can be fallen on two first tracks on the bridge two preceding running gears respectively; C, auxiliary supporting leg before above-mentioned two is packed up, make two preceding running gears respectively along two first tracks on the bridge, make that running gear moves forward along two second tracks on the roadbed respectively after two; The above-mentioned step place of D, two first tracks on bridge, add a cushion block respectively, each cushion block is by the bridge positioning support, track on two cushion blocks is connected with two second tracks on the roadbed respectively, when running gear after two is gone on two tracks on the cushion block respectively, after two, assist supporting leg on bridge, to prop respectively, take two cushion blocks away; E, auxiliary supporting leg after two is packed up, running gear after two can be fallen respectively on two first tracks on the bridge, the piston rod of laterally adjusting the hydraulic jack in the beam before making every simultaneously shrinks, making it drive guide way moves down, to guarantee that vehicle frame is the level of state, laterally adjust positioning body in the beam before making every and guide way and slide mass are fixedly connected on a certain relative position and lock.
In the technique scheme, when carrying out above-mentioned steps C and step e, can be earlier adjust the horizontal spacing of running gear behind the horizontal spacing of two preceding running gears and two by horizontal adjusting device, the wheel of being convenient to them can pass through two first tracks and two second tracks smoothly.
The utility model (in other words conj.or perhaps can ballastless track bed casting equipment main body of the up/down steps) is realized the lifting of two preceding running gears by laterally adjusting slide mass in the beam before two with respect to the lifting of vehicle frame, cushion block adopts simply and flexible way just can make this ballastless track bed casting equipment step by being produced by roadbed and bridge junction smoothly by adding, up/down steps can guarantee that this ballastless track bed casting equipment uses at straightway by this way, also can satisfy the requirement of using at curved section, simultaneously from transversely, vehicle frame remains level, it can adapt to different discrepancy in elevation requirements, can be smoothly by the step of differing heights, stabilization of equipment performance is good.
Description of drawings
Fig. 1 is structural representation of the present utility model (described ballastless track bed casting equipment is by the track to the roadbed on the track on the bridge at its place).
Fig. 2 is structural representation of the present utility model (described ballastless track bed casting equipment is by the track to the bridge under the track on the roadbed at its place).
Fig. 3 be among Fig. 2 A to view.
Fig. 4 is that a cushion block of the present utility model covers the partial view on one first track corresponding with it.
Fig. 5 is the structural representation of the preceding running gear that horizontal adjustment beam is connected with it before in the utility model.
Fig. 6 be among Fig. 2 B to partial view.
The specific embodiment
As Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, shown in Figure 6, the utlity model has and be horizontally disposed (square shape) vehicle frame 4, lay respectively at vehicle frame left and right sides front end be two of vertical setting before laterally adjust beam 2, lay respectively at rear end, the vehicle frame left and right sides be two of vertical setting after laterally adjust beam 6, laterally adjust two preceding running gears 1 that beam 2 connects as one respectively with before two, respectively with two after laterally adjust two that beam 6 connects as one after running gear 8, lay respectively at auxiliary supporting leg 3 before two of front portion, the vehicle frame left and right sides, lay respectively at auxiliary supporting leg 5 behind two of rear portion, the vehicle frame left and right sides, laterally adjust four telescopic 2a that laterally adjust the beam upper end behind beam and every before being individually fixed in every, laterally adjust before being used for adjusting every respectively laterally adjust beam and vehicle frame relative position behind beam and every so that adjust two preceding running gear horizontal spacings and two after four horizontal adjusting devices 7 of running gear horizontal spacing, each support two first tracks 9 of running gear behind a preceding running gear and or two second tracks 9 ', hydraulic system, actuating unit (these are prior art, and are not shown) before being installed on respectively on running gear and the back running gear and a pair of template 9a that lays respectively at two first tracks, 9 inboards and be connected to one with it, lay respectively at two second tracks 9 ' inboard and be connected to one with it another to template 9a '.Laterally adjust before every laterally adjust behind beam and every beam by a telescopic 2a above it with and a corresponding horizontal adjusting device 7 connect as one with vehicle frame 4, running gear 1 and each back running gear 8 have respectively along wheel 1a, 8a and vehicle wheel frame 1b, the 8b of above-mentioned two first tracks 9 or two second track 9 ' walkings before each.Running gear and each back running gear can adopt the single-wheel carrying before each, also can adopt the two-wheel carrying, can also be other form of structure.Laterally adjusting beam 2 before above-mentioned every all has the guide way 2c that is vertical setting, can slide up and down and by its spacing slide mass 2d, hydraulic jack 2b, positioning body 2e along guide way 2c.Laterally adjust the guide way 2c of beam 2 before every, hydraulic jack 2b is fixed on the telescopic 2a corresponding with it, laterally the bottom of the slide mass 2d of adjustment beam is fixedly connected with the vehicle wheel frame 1b that should precedingly laterally adjust the preceding running gear that beam was connected before every, laterally adjust before every beam hydraulic jack 2b the piston rod top with should before laterally to adjust the vehicle wheel frame 1b of the preceding running gear that beam was connected hinged, before every laterally the guide way 2c of adjustment beam 2 and slide mass 2d by the two is connected to one at several relative positions respectively, and slide mass 2d is slided up and down along guide way 2c, should precedingly laterally adjust the positioning body 2e locking of beam.The guide way 2c that laterally adjusts beam 2 before above-mentioned every is two square tubes being vertical setting (can adopt square steel pipe or be welded by steel plate), these two square tubes are individually fixed in the both sides, front and back of a telescopic 2a corresponding with it, the slide mass 2d that laterally adjusts beam before every is two columns vertical setting, square (can adopt square steel), and two columns laterally adjusting the slide mass 2d of beam before every are set with in two square tubes of its guide way 2c; Laterally adjust before every beam slide mass 2d two columns the bottom with should before the horizontal upper surface fixedly connected (can adopt welding) of the vehicle wheel frame 1b of the adjustment preceding running gear that beam was connected, the cylinder barrel of laterally adjusting the hydraulic jack 2b of beam before every vertically passes and its corresponding telescopic 2a and fixedly connected with it (can adopt flange to be connected), and the upper surface of the vehicle wheel frame 1b of the preceding running gear that the piston rod top of this hydraulic jack 2b is connected with the preceding horizontal adjustment beam at its place is hinged.The positioning body 2e that laterally adjusts beam 2 before above-mentioned every comprises several the first lateral direction penetrating holes that all become to be arranged above and below on two square tubes that lay respectively at the guide way 2c that laterally adjusts beam before this, lay respectively at several the second lateral direction penetrating holes that all become to be arranged above and below on two columns of the slide mass 2d that laterally adjusts beam before this, several alignment pins, in described these several alignment pins several or an alignment pin pass the corresponding with it first lateral direction penetrating hole and the second lateral direction penetrating hole respectively simultaneously, and the guide way 2c and the slide mass 2d that will laterally adjust beam before will being somebody's turn to do are fixedly connected on a certain relative position (in the present embodiment, can be provided with three relative positions, certainly if increase by first, the quantity in two lateral direction penetrating holes also can be provided with a plurality of relative positions).It is connected described hydraulic jack 2b with above-mentioned hydraulic system with control valve by oil pipe into and out of hydraulic fluid port.
As Fig. 1, Fig. 3, Fig. 4, Fig. 5, shown in Figure 6, the method of topping bar of the ballastless track bed casting equipment of energy up/down steps, the walking of described casting equipment two first tracks 9 or two second tracks 9 ' on, two first tracks 9, two second tracks 9 ' be supported on respectively on bridge 10 and the roadbed 11, step produces in the junction of bridge 10 and roadbed 11.Described casting equipment by two second tracks 9 to the roadbed on two first tracks 9 on the bridge at its place ' method may further comprise the steps: the above-mentioned step place that 1. two preceding running gears 1 of described casting equipment is walked to two first tracks 9 on the bridge, before above-mentioned two, assist supporting leg 3 on bridge, to prop respectively, will be laterally adjusting that guide way 2c in the beam 2 and slide mass 2d are fixedly connected on a certain relative position before every and the positioning body 2e release (being about to above-mentioned several alignment pins extracts from the first lateral direction penetrating hole and the second lateral direction penetrating hole) that locks, the piston rod of laterally adjusting the hydraulic jack 2b in the beam 2 before making every shrinks, running gear 1 and slide mass 2d and along the guide way 2c disorbit 9 that moves up before it is driven, and make two preceding running gears 1 pack up (the roughly corresponding shoulder height of the height that running gear is packed up before each quite or equate) with it.2. the above-mentioned step place of two first tracks 9 on bridge, add a cushion block 12 respectively, each cushion block 12 is by bridge 10 positioning supports (spacing in other words supporting), the thickness of each cushion block equates that with the height of its corresponding step (two second tracks on the curved section roadbed might the discrepancy in elevation not wait, therefore the height of these two second pairing steps of track might not equate, promptly the thickness of two cushion blocks might not equate), the upper surface of each cushion block all has track, two cushion blocks 12 just in time be placed on respectively two preceding running gears 1 below, the track on two cushion blocks respectively with roadbed on two second tracks 9 ' be connected.3. before above-mentioned two, assist supporting leg 3 to pack up, make two preceding running gears 1 respectively along two second tracks 9 on track on two cushion blocks and the roadbed ', make that running gear 8 moves forward along two first tracks 9 on the bridge respectively after two, when two preceding running gears 1 leave two tracks on the cushion block enter two second tracks 9 on the roadbed ' after, take two cushion blocks 12 away.4. when running gear 8 after two walks to the above-mentioned step place of two first tracks 9 on the bridge, after two, assist supporting leg 5 propping (propping of running gear highly is shoulder height after two) on the roadbed 11 respectively, running gear 8 leaves two first tracks 9 respectively after making two, laterally adjust the piston rod elongation of the hydraulic jack 2b in the beam 2 before making every simultaneously, make it drive guide way 2c move up (returned to step before position), to guarantee that vehicle frame 4 is the level of state, the above-mentioned step place of two first tracks 9 on bridge, add a cushion block 12 respectively, each cushion block 12 is by bridge 10 positioning supports, two cushion blocks 12 just in time be placed on respectively running gear 8 after two below, the track on two cushion blocks respectively with roadbed on two second tracks 9 ' be connected.5. after above-mentioned two, assist supporting leg (5) to pack up, make two preceding running gears 1 respectively along two second tracks 9 on the roadbed ', make that running gear 8 moves forward along the track on two cushion blocks respectively after two, when running gear 8 after two leave two tracks on the cushion block enter two second tracks 9 on the roadbed ' after, take two cushion blocks 12 away, laterally adjust positioning body 2e in the beam 2 before making every and guide way 2c and slide mass 2d are fixedly connected on a certain relative position and lock.Carry out above-mentioned steps 3. the time, can be earlier adjust the horizontal spacing of running gear 8 behind the horizontal spacing of two preceding running gears 1 and two by horizontal adjusting device 7, be convenient to their wheel 1a, 8a can be smoothly by two first tracks 9 and two second tracks 9 '.Carry out above-mentioned steps 5. the time, can be earlier adjust the horizontal spacing of running gear 8 behind the horizontal spacing of two preceding running gears 1 and two by horizontal adjusting device 7, be convenient to their wheel 1a, 8a can be smoothly by two first tracks 9 and two second tracks 9 '.Above-mentioned steps 2. with step 4. in, each cushion block 12 can be that the length of each cushion block 12 quite (equates with the length of one of them back running gear by the concrete grammar of bridge positioning support, the length of preceding running gear is less than the length of back running gear), the bottom surface of each cushion block 12 has depression, each cushion block 12 covers on one first track 9 corresponding with it by the depression of its bottom surface, the medial surface of each cushion block 12 is by a template 9a corresponding with it spacing (location), each is spacing by a timber wedge 13 for its lateral surface, described timber wedge can be fixed on the bridge 10 by steel nail, and its cross section is a right-angled triangle.The depression of the bottom surface of each above-mentioned cushion block 12 can be inserted the holding area of the diapire of two space segments of this cushion block bottom surface (bottom) and this first track for two sidewalls of one first track 9 corresponding with it respectively, described these of two space segments are channel form, another is positioned at the medial surface of cushion block and makes the medial surface of cushion block be step-like (stepped), certainly, the bottom surface of each cushion block 12 is mutually neat with the bottom surface of its corresponding one first track 9, thereby realizes that each cushion block 12 is supported by bridge.Each cushion block 12 can also be an alternate manner by the concrete grammar of bridge positioning support.Each cushion block 12 can be welded by steel plate, its integral body can be cuboid, its length and width size preferably with the length and width size of back running gear quite or equate that (length of preceding running gear is less than the length of back running gear, the two width quite or equate), it also can be other shape.Track on each cushion block can and be fixedlyed connected with the upper surface of this cushion block by welding or bolt connection.
As Fig. 2, Fig. 3, Fig. 4, Fig. 5, shown in Figure 6, the method of getting out of a predicament or an embarrassing situation of the ballastless track bed casting equipment of energy up/down steps, the walking of described casting equipment two second tracks 9 ' or two first tracks 9 on, two second tracks 9 ', two first tracks 9 are supported on respectively on roadbed 11 and the bridge 10, step produces in the junction of bridge 10 and roadbed 11.Described casting equipment be may further comprise the steps by the method for two second tracks 9 on the roadbed at its place ' following two first tracks 9 to bridge: A, the above-mentioned step place of two first tracks 9 on bridge, add a cushion block 12 respectively, each cushion block 12 is by bridge 10 positioning supports, the thickness of each cushion block equates that with the height of its corresponding step (two second tracks on the curved section roadbed might the discrepancy in elevation not wait, therefore the height of these two second pairing steps of track might not equate, promptly the thickness of two cushion blocks might not equate), the upper surface of each cushion block all has track, track on two cushion blocks respectively with roadbed on two second tracks 9 ' be connected, make two preceding running gears 1 go on the track of two cushion blocks 12 respectively.B, auxiliary supporting leg 3 before above-mentioned two is propped on roadbed respectively, will be laterally adjusting that guide way 2c in the beam 2 and slide mass 2d are fixedly connected on a certain relative position before every and the positioning body 2e release that locks, take two cushion blocks 12 away, laterally adjust the piston rod elongation of the hydraulic jack 2b in the beam 2 before making every, running gear 1 and slide mass 2d and move down along guide way 2c before it is driven can fall on two first tracks 9 on the bridge two preceding running gears 1 respectively.C, auxiliary supporting leg 3 before above-mentioned two is packed up, make two preceding running gears 1 respectively along two first tracks 9 on the bridge, make after two running gear 8 respectively along two second tracks 9 on the roadbed ' move forward.The above-mentioned step place of D, two first tracks 9 on bridge, add a cushion block 12 respectively, each cushion block 12 is by bridge 10 positioning supports, track on two cushion blocks respectively with roadbed on two second tracks 9 ' be connected, when running gear 8 after two is gone on two tracks on the cushion block 12 respectively, after two, assist supporting leg 5 on bridge 10, to prop respectively, take two cushion blocks 12 away.E, auxiliary supporting leg 5 after two is packed up, running gear 8 after two can be fallen respectively on two first tracks on the bridge, the piston rod of laterally adjusting the hydraulic jack 2b in the beam 2 before making every simultaneously shrinks, make it drive guide way 2c and move down (returning to the preceding position of step), to guarantee that vehicle frame 4 is the level of state, laterally adjust positioning body 2e in the beam 2 before making every and guide way 2c and slide mass 2d are fixedly connected on a certain relative position and lock.When carrying out above-mentioned steps C, can be earlier adjust the horizontal spacing of running gear 8 behind the horizontal spacing of two preceding running gears 1 and two by horizontal adjusting device 7, be convenient to their wheel 1a, 8a can be smoothly by two first tracks 9 and two second tracks 9 '; When carrying out above-mentioned steps E, can be earlier adjust the horizontal spacing of running gear 8 behind the horizontal spacing of two preceding running gears 1 and two by horizontal adjusting device 7, be convenient to their wheel 1a, 8a can be smoothly by two first tracks 9 and two second tracks 9 '.Among above-mentioned steps A and the step D, each cushion block 12 can be that the length of the length of each cushion block 12 and one of them back running gear is suitable by the concrete grammar of bridge positioning support, the bottom surface of each cushion block 12 has depression, each cushion block 12 covers on one first track 9 corresponding with it by the depression of its bottom surface, the medial surface of each cushion block 12 is spacing by a template 9a corresponding with it, each is spacing by a timber wedge 13 for its lateral surface, described timber wedge is fixed on the bridge 10, and its cross section is a right-angled triangle.

Claims (3)

1. the ballastless track bed casting equipment of an energy up/down steps, have and be horizontally disposed vehicle frame (4), lay respectively at vehicle frame left and right sides front end be two of vertical setting before laterally adjust beam (2), lay respectively at rear end, the vehicle frame left and right sides be two of vertical setting after laterally adjust beam (6), laterally adjust two preceding running gears (1) that beam (2) connects as one respectively with before two, respectively with two after laterally adjust two that beam (6) connects as one after running gear (8), lay respectively at auxiliary supporting leg (3) before two of front portion, the vehicle frame left and right sides, lay respectively at auxiliary supporting leg (5) behind two of rear portion, the vehicle frame left and right sides, laterally adjust four telescopics (2a) of laterally adjusting the beam upper end behind beam and every before being individually fixed in every, laterally adjust before being used for adjusting every respectively laterally adjust beam and vehicle frame relative position behind beam and every so that adjust two preceding running gear horizontal spacings and two after four horizontal adjusting devices (7) of running gear horizontal spacing, each supports two first tracks (9) or two second tracks (9 ') of running gear behind a preceding running gear and, laterally adjust before every laterally adjust behind beam and every beam by the telescopic (2a) above it with and a corresponding horizontal adjusting device (7) and vehicle frame (4) connect as one, running gear (1) and each back running gear (8) have respectively along the wheel (1a of above-mentioned two first tracks (9) or two second tracks (9 ') walking before each, 8a), vehicle wheel frame (1b, 8b), it is characterized in that:
Laterally adjusting beam (2) before above-mentioned every all has the guide way (2c) that is vertical setting, can slide up and down and by its spacing slide mass (2d), hydraulic jack (2b), positioning body (2e) along guide way (2c);
Laterally adjust the guide way (2c) of beam (2) before every, hydraulic jack (2b) is fixed on the telescopic corresponding with it (2a), laterally the bottom of the slide mass (2d) of adjustment beam is fixedly connected with the vehicle wheel frame (1b) that should precedingly laterally adjust the preceding running gear that beam was connected before every, laterally adjust before every beam hydraulic jack (2b) the piston rod top with should before laterally to adjust the vehicle wheel frame (1b) of the preceding running gear that beam was connected hinged, before every laterally the guide way (2c) of adjustment beam (2) and slide mass (2d) by the two is connected to one at several relative positions respectively, and slide mass (2d) is slided up and down along guide way (2c), should precedingly laterally adjust positioning body (2e) locking of beam.
2. casting equipment according to claim 1, it is characterized in that laterally adjusting before above-mentioned every the guide way (2c) of beam (2) for being two square tubes of vertical setting, these two square tubes are individually fixed in the both sides, front and back of a telescopic corresponding with it (2a), the slide mass (2d) of laterally adjusting beam before every is for being two columns vertical setting, square, and two columns laterally adjusting the slide mass (2d) of beam before every are set with in two square tubes of its guide way (2c); Laterally the bottom of two columns of the slide mass (2d) of adjustment beam is fixedly connected with the upper surface of the vehicle wheel frame (1b) that should precedingly laterally adjust the preceding running gear that beam was connected before every, the cylinder barrel of laterally adjusting the hydraulic jack (2b) of beam before every vertically passes with its corresponding telescopic (2a) also fixedlys connected with it, and the upper surface of the vehicle wheel frame (1b) of the preceding running gear that the piston rod top of this hydraulic jack (2b) is connected with the preceding horizontal adjustment beam at its place is hinged.
3. casting equipment according to claim 2, the positioning body (2e) that it is characterized in that before above-mentioned every laterally adjusting beam (2) comprises several the first lateral direction penetrating holes that all become to be arranged above and below on two square tubes that lay respectively at the guide way (2c) of laterally adjusting beam before this, lay respectively at several the second lateral direction penetrating holes that all become to be arranged above and below on two columns of the slide mass (2d) of laterally adjusting beam before this, several alignment pins, several in described these several alignment pins or an alignment pin pass the corresponding with it first lateral direction penetrating hole and the second lateral direction penetrating hole respectively simultaneously, and guide way (2c) and the slide mass (2d) of laterally adjusting beam before will being somebody's turn to do are fixedly connected on a certain relative position.
CN2009201034086U 2009-06-24 2009-06-24 Fragment-free track-bed pouring device capable of climbing up steps Expired - Lifetime CN201437576U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201034086U CN201437576U (en) 2009-06-24 2009-06-24 Fragment-free track-bed pouring device capable of climbing up steps

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201034086U CN201437576U (en) 2009-06-24 2009-06-24 Fragment-free track-bed pouring device capable of climbing up steps

Publications (1)

Publication Number Publication Date
CN201437576U true CN201437576U (en) 2010-04-14

Family

ID=42399552

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201034086U Expired - Lifetime CN201437576U (en) 2009-06-24 2009-06-24 Fragment-free track-bed pouring device capable of climbing up steps

Country Status (1)

Country Link
CN (1) CN201437576U (en)

Similar Documents

Publication Publication Date Title
CN101985826A (en) Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
CN110607751B (en) Straddle type monorail track beam line type adjusting system and adjusting method thereof
CN101586322B (en) Ballastless track road-bed pouring device with capability of step ascending-and-descending and step ascending-and-descending method
CN103541735B (en) Tunneling machine stepping pushing supporting device and construction method
CN209907228U (en) Steel beam pushing and guiding device
CN102002913A (en) Prefabricated T beam transferring trolley
CN106320736A (en) Method for shifting, climbing, lifting and steering of building
CN208380591U (en) Send rail tunnel hydraulic two linings trolley automatically
CN211256687U (en) Straddle type monorail track beam linear adjusting system
CN209761465U (en) Non-repeated support advance support and carrying complete equipment
CN205576749U (en) Pontic roof beam structure promotes and rackwork
CN106285040A (en) The track discrepancy in elevation is utilized to realize the method that building moving turns to
CN101967798A (en) Highway double-guide-beam bridge erecting machine and turning method
CN206800215U (en) Bridge incremental launching Bridge Erector
CN201437576U (en) Fragment-free track-bed pouring device capable of climbing up steps
CN109081259A (en) A method of realization combustion engine large size PCC equipment is installed in place in narrow space
CN107829374A (en) Highway prestress concrete box girder mobile formwork and construction method of encorbelmenting
CN205558947U (en) Coal face's gob entry floodwater drainage moves support certainly about being fit for
CN102305035B (en) Device for adjusting centration of complete vehicle-mounted service machine to wellhead
CN217922859U (en) Gauge correction device for track laying
CN111119912A (en) Down-through railway frame box culvert jacking construction device and construction method thereof
CN203531916U (en) Tunnel boring machine step pushing support device
CN104141264B (en) Plate-type slag-free orbit lays precision keeping method
CN201330365Y (en) Bench formwork trolley for construction of two-course pavement structure in tunnel
CN202809475U (en) Full hydraulic full-automatic control tunnel invert trestle

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20100414

CX01 Expiry of patent term