CN201420263Y - Breast wall of prefabricated concrete pipe of manual hole digging pile - Google Patents

Breast wall of prefabricated concrete pipe of manual hole digging pile Download PDF

Info

Publication number
CN201420263Y
CN201420263Y CN2009200519272U CN200920051927U CN201420263Y CN 201420263 Y CN201420263 Y CN 201420263Y CN 2009200519272 U CN2009200519272 U CN 2009200519272U CN 200920051927 U CN200920051927 U CN 200920051927U CN 201420263 Y CN201420263 Y CN 201420263Y
Authority
CN
China
Prior art keywords
concrete pipe
concrete
pipe
pile
cascaded surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009200519272U
Other languages
Chinese (zh)
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Zhongcheng Building Group Co., Ltd.
Original Assignee
叶长青
朱奎
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 叶长青, 朱奎 filed Critical 叶长青
Priority to CN2009200519272U priority Critical patent/CN201420263Y/en
Application granted granted Critical
Publication of CN201420263Y publication Critical patent/CN201420263Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a breast wall of a prefabricated concrete pipe of a manual hole digging pile; the breast wall comprises an upper concrete pipe, a plurality of intermediate concrete pipes and a lower concrete pipe which are connected end to end, wherein, the lower end of the upper concrete pipe is provided with an inner step surface, the upper end of the intermediate concrete pipe is provided with an outer step surface which is distributed in a ring shape, a low plane at the outside of the outer step surface is mounted with an embedded iron piece, the lower end of the intermediate concrete pipe is provided with the inner step surface which is distributed in a ring shape, the upper end of the lower concrete pipe is provided with the inner step surface which is distributed in a ring shape, the lower end of the lower concrete pipe is provided with a foot blade, the inner side of the foot blade is provided with an oblique plane which is expanded outwards, the outer side of the foot blade is provided with a projection; the side walls of the upper concrete pipe, the intermediate concrete pipes and the lower concrete pipe are all embedded with drainage tubes which are obliquelydistributed from low internal side to high external side. The breast wall of the prefabricated concrete pipe of the manual hole digging pile which is formed by connection of the upper concrete pipe,the plurality of intermediate concrete pipes and the lower concrete pipe can effectively reinforce the side wall of the pile hole; therefore, the breast wall can separate the inside of the pile hole and the quicksand even in the serious quicksand region, and ensures the integrity of the pile hole, and makes the pile body formed through casting have better quality.

Description

A kind of prefabricated concrete of hand excavated pile is managed and protected wall
Technical field
The utility model relates to a kind of prefabricated concrete of hand excavated pile and manages and protects wall.
Background technology
Tradition hand excavated pile panelling construction technology is Cast-in-place concrete retaining wall in the stake hole generally, treats that Cast-in-place concrete reaches after certain length of time form removal pouring pile concrete again, if but just the Cast-in-place concrete retaining wall can't be constructed when quicksand is serious, thus can not guarantee pore-forming.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of collapse prefabricated concrete of hand excavated pile in hole of a hole that can effectively prevent and manages and protects wall.
For this reason, the prefabricated concrete of the hand excavated pile that the utility model provides is managed and protected wall and is gone up the concrete pipe by a joint, the linking of concrete pipe formed under concrete pipe and saved in the middle of the more piece, the lower end of wherein going up the concrete pipe has interior cascaded surface, the upper end of middle concrete pipe has the outer cascaded surface of annular spread, the lower end of middle concrete pipe has the interior cascaded surface of annular spread, the upper end of following concrete pipe has the interior cascaded surface of annular spread, the lower end of following concrete pipe has the sword pin, the inboard of sword pin has the inclined-plane that expands outwardly, the outside of sword pin has projection, last concrete pipe, all be embedded with the drainage tube that low outer height diagonally distributes in being on the sidewall of middle concrete pipe and following concrete pipe.
Since the utility model provide by concrete pipe in the middle of the last concrete pipe, more piece and a joint down the concrete pipe be connected the prefabricated concrete that forms and manage and protect wall energy and enough effectively reinforces a hole sidewall, even the zone serious at drift sand also can intercept an inside, hole and a drift sand, guarantee the integrality in stake hole, thereby the pile quality that cast is obtained is better.
Description of drawings
The prefabricated concrete of the hand excavated pile that Fig. 1 provides for the utility model is managed and protected the structure cross-sectional schematic of wall.
Fig. 2 is the structure cross-sectional schematic of the last concrete pipe among Fig. 1.
Fig. 3 is the structure cross-sectional schematic of the middle concrete pipe among Fig. 1.
Fig. 4 is the structure cross-sectional schematic of the following concrete pipe among Fig. 1.
In each accompanying drawing: 1A, go up the concrete pipe, 1B, middle concrete pipe, 1C, concrete pipe down, cascaded surface in 2A, the outer cascaded surface, 2B, 3, ironware, 4, drainage tube, 5, the sword pin, 6, the inclined-plane, 7, projection.
The specific embodiment
As Fig. 1, Fig. 2, Fig. 3, shown in Figure 4, the prefabricated concrete of the hand excavated pile that the utility model provides is managed and protected wall and is gone up concrete pipe 1A by a joint, concrete pipe 1C linking formed under concrete pipe 1B and saved in the middle of the more piece, the lower end of wherein going up concrete pipe 1A has interior cascaded surface 2B, the upper end of middle concrete pipe 1B has the outer cascaded surface 2A of annular spread, the lower end of middle concrete pipe 1B has the interior cascaded surface 2B of annular spread, last concrete pipe 1A, the outer cascaded surface 2A of middle concrete pipe 1B and following concrete pipe 1C and the low bit plane of interior cascaded surface 2B are provided with embedded iron parts 3, make outer cascaded surface 2A and interior cascaded surface 2B can adopt the mode of welding to be connected reinforcing, the upper end of following concrete pipe 1C has the interior cascaded surface 2B of annular spread, the lower end of following concrete pipe 1C has sword pin 5, the inboard of sword pin 5 has the inclined-plane 6 that expands outwardly, the outside of sword pin 5 has projection 7, last concrete pipe 1A, all be embedded with the drainage tube 4 that low outer height diagonally distributes in being on the sidewall of middle concrete pipe 1B and following concrete pipe 1C.

Claims (2)

1, a kind of prefabricated concrete of hand excavated pile is managed and protected wall, it is characterized in that: prefabricated concrete dado is gone up concrete pipe (1A) by a joint, concrete pipe (1C) linking formed under concrete pipe (1B) and saved in the middle of the more piece, the lower end of wherein going up concrete pipe (1A) has interior cascaded surface (2B), the upper end of middle concrete pipe (1B) has the outer cascaded surface (2A) of annular spread, the lower end of concrete pipe (1B) has the interior cascaded surface (2B) of annular spread in the middle of described, the described upper end of concrete pipe (1C) down has the interior cascaded surface (2B) of annular spread, the lower end of following concrete pipe (1C) has sword pin (5), the inboard of sword pin (5) has the inclined-plane (6) that expands outwardly, the outside of sword pin (5) has projection (7), the described concrete pipe (1A) of going up, all be embedded with the drainage tube (4) that low outer height diagonally distributes in being on the sidewall of middle concrete pipe (1B) and following concrete pipe (1C).
2, the prefabricated concrete of hand excavated pile according to claim 1 is managed and protected wall, it is characterized in that: the low bit plane of going up the outer cascaded surface (2A) of concrete pipe (1A), middle concrete pipe (1B) and following concrete pipe (1C) is provided with embedded iron parts (3),
CN2009200519272U 2009-02-25 2009-02-25 Breast wall of prefabricated concrete pipe of manual hole digging pile Expired - Fee Related CN201420263Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200519272U CN201420263Y (en) 2009-02-25 2009-02-25 Breast wall of prefabricated concrete pipe of manual hole digging pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200519272U CN201420263Y (en) 2009-02-25 2009-02-25 Breast wall of prefabricated concrete pipe of manual hole digging pile

Publications (1)

Publication Number Publication Date
CN201420263Y true CN201420263Y (en) 2010-03-10

Family

ID=41806915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200519272U Expired - Fee Related CN201420263Y (en) 2009-02-25 2009-02-25 Breast wall of prefabricated concrete pipe of manual hole digging pile

Country Status (1)

Country Link
CN (1) CN201420263Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101956390A (en) * 2010-09-27 2011-01-26 攀钢集团冶金工程技术有限公司 Bored pile channel partition method
CN102425156A (en) * 2011-09-08 2012-04-25 广东省基础工程公司 Cross section-variable underground continuous wall and construction method thereof
CN103758123A (en) * 2014-01-24 2014-04-30 江苏建筑职业技术学院 Method for constructing protecting wall lining of cast-in-place manual hole digging pile
CN105421339A (en) * 2015-12-14 2016-03-23 中冶集团武汉勘察研究院有限公司 Novel combined concrete protection wall for manual rectangular anti-slide digging pile and installation method of novel combined concrete protection wall
CN106168034A (en) * 2015-09-30 2016-11-30 洛阳武轩重工机械有限公司 A kind of retaining wall plate
CN107326901A (en) * 2016-04-29 2017-11-07 中国电建集团贵阳勘测设计研究院有限公司 A kind of prefabricated bamboo formula retaining wall of stake holes
CN113266011A (en) * 2021-04-28 2021-08-17 李俊飞 Novel composite pile enclosure device

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101956390A (en) * 2010-09-27 2011-01-26 攀钢集团冶金工程技术有限公司 Bored pile channel partition method
CN101956390B (en) * 2010-09-27 2012-02-08 东北金城建设股份有限公司 Bored pile channel partition method
CN102425156A (en) * 2011-09-08 2012-04-25 广东省基础工程公司 Cross section-variable underground continuous wall and construction method thereof
CN103758123A (en) * 2014-01-24 2014-04-30 江苏建筑职业技术学院 Method for constructing protecting wall lining of cast-in-place manual hole digging pile
CN103758123B (en) * 2014-01-24 2015-12-09 江苏建筑职业技术学院 The construction method of manually digging hole filling pile retaining wall lining
CN106168034A (en) * 2015-09-30 2016-11-30 洛阳武轩重工机械有限公司 A kind of retaining wall plate
CN105421339A (en) * 2015-12-14 2016-03-23 中冶集团武汉勘察研究院有限公司 Novel combined concrete protection wall for manual rectangular anti-slide digging pile and installation method of novel combined concrete protection wall
CN107326901A (en) * 2016-04-29 2017-11-07 中国电建集团贵阳勘测设计研究院有限公司 A kind of prefabricated bamboo formula retaining wall of stake holes
CN113266011A (en) * 2021-04-28 2021-08-17 李俊飞 Novel composite pile enclosure device

Similar Documents

Publication Publication Date Title
CN201420263Y (en) Breast wall of prefabricated concrete pipe of manual hole digging pile
CN105114105A (en) Steel-concrete composite tunnel lining supporting structure and manufacturing and construction method thereof
CN106761768B (en) A kind of steel pipe curtain structure support system and its construction method
CN110331727B (en) Support structure combining cast-in-place pile and underground diaphragm wall and construction method
CN110593890B (en) Tunnel corrugated steel double-layer primary lining supporting method
CN101503882A (en) Construction method for underground continuous wall with conjoined reinforcing cage by topdown construction method
KR101751418B1 (en) Grouting device using a reinforced network is equipped with a small steel pipe
CN102493446B (en) Steel tube column capable of preventing concrete spillover and method for mounting steel tube column
KR100850028B1 (en) Construction method using concrete mould for concrete piles cast in position
CN107740427A (en) A kind of construction method of interpolation concrete prefabricated square stake foundation pit enclosure structure
CN201605599U (en) Integrated prefabricated inspection well
CN208472717U (en) A kind of depth back filled region bored concrete pile steel pile casting retaining wall
JP5919675B2 (en) Composite foundation pile and construction method of composite foundation pile
CN108086307B (en) Steel pipe concrete hole digging and pouring composite miniature pile
JP2011017188A (en) Demolition method of existing building
JP2010209645A (en) Foundation pile structure and construction method for the foundation pile
CN101525875B (en) Reinforced concrete bifurcated pipe structure under action of high pressure water and construction method
CN103911986B (en) A kind of construction method combining strike-on steel pipe pile
CN217325391U (en) Construction tool for high-speed rail line deep foundation pit secant pile
CN105350547A (en) Method applicable to inter-pile soil support of slope protection pile
KR101884663B1 (en) Construction method for soil retaining wall using cap slab
CN101979777A (en) Cast-in-place hollow square pile and combined underground continuous wallboard and construction method thereof
CN101691753B (en) Pile mould for PCC pile and construction method for overlong PCC pile
CN103397650B (en) A kind of large-scale steel cylinder cofferdam structure
CN113957880A (en) Construction method of steel-concrete underground continuous wall

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Free format text: FORMER OWNER: YE ZHANGQING

Effective date: 20110829

Free format text: FORMER OWNER: ZHU KUI

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20110829

Address after: 325000 Fairview Road, Fairview Midtown tower, Wenzhou, 6F-7F

Patentee after: Wenzhou Zhongcheng Building Group Co., Ltd.

Address before: 325000 No. 4, Jinchuan Road, Longwan District, Zhejiang, Wenzhou

Co-patentee before: Zhu Kui

Patentee before: Ye Changqing

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100310

Termination date: 20130225