CN201407901Y - Tyre mold for wall of heating furnace - Google Patents

Tyre mold for wall of heating furnace Download PDF

Info

Publication number
CN201407901Y
CN201407901Y CN2009203028713U CN200920302871U CN201407901Y CN 201407901 Y CN201407901 Y CN 201407901Y CN 2009203028713 U CN2009203028713 U CN 2009203028713U CN 200920302871 U CN200920302871 U CN 200920302871U CN 201407901 Y CN201407901 Y CN 201407901Y
Authority
CN
China
Prior art keywords
construction
heating furnace
furnace wall
tyre mold
tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009203028713U
Other languages
Chinese (zh)
Inventor
邵长利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
MCC Shijiu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shijiu Construction Co Ltd filed Critical MCC Shijiu Construction Co Ltd
Priority to CN2009203028713U priority Critical patent/CN201407901Y/en
Application granted granted Critical
Publication of CN201407901Y publication Critical patent/CN201407901Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to an installation construction technology for a heating furnace in the metallurgical industry, in particular to a tyre mold suitable for the construction of a heating furnace wall. The utility model aims to solve the technical problem that a tyre mold with simple structure and high stability used for furnace wall construction is provided, the tyre mold adopts the schemethat at least one transverse support and a vertical support form a supporting frame, the supporting frame is connected with a furnace body steel plate through connecting bolts, and horizontal spacingis formed between the supporting frame and the furnace body steel plate. Since the tyre mold is made of light and flexible revolving material, adjustment can be performed during the construction as required by the construction, the installation is easy, the tyre mold can be reused, thereby reucing the construction revolving material and saving the construction cost. The tyre mold is convenient forthe mounting of a furnace wall anchor adapter, thereby enhancing the mounting quality and the construction progress.

Description

Heating furnace furnace wall loose tool tool
Affiliated technical field
The utility model relates to heating furnace installation Technology in the metallurgy industry, particularly is suitable for the heating furnace furnace wall employed fetal membrane tool of constructing.
Background technology
Generally adopt heating furnace to improving its temperature for material heating in metallurgy industry, satisfy the requirement of subsequent technique, form generally adopts three kinds of pusher-type furnaces, rotary heating furnace, walking beam furnace.
Reheat furnace system is mainly formed complex structure by systems such as furnace bottom, furnace wall, furnace roof, Shui Liang, flues.And the heating furnace furnace wall mainly is with castable refractory and moldable composition, and its proportion is more generally at 2.3 3.3t/m 3Between, in furnace wall, be provided with the furnace wall anchored brick of spacing simultaneously at 300mm~600mm.At present when installing and keep in repair, furnace wall construction fetal membrane often adopts steel scaffold and flitch to support the mode of setting up, its poor stability, influenced the flatness control requirement of furnace wall, can not solve the installation quality of furnace wall anchored brick effectively, and the circulation material that uses is more, running is inconvenient, corresponding artificial input is bigger, has increased the input of construction cost.
The utility model content
Technical problem to be solved in the utility model provides a kind of high furnace wall construction fetal membrane tool simple in structure, stable.
The heating furnace furnace wall loose tool tool that its technical problem that solves the utility model adopts is formed bracing frame by at least one horizontal support and upright the support, and above-mentioned bracing frame is connected by connecting bolt with the body of heater steel plate, and is formed with level interval each other.
As further improvement of the utility model, between bracing frame and body of heater steel plate, be provided with anchored brick, connecting bolt passes the connecting hole on the above-mentioned anchored brick.
Because what fetal membrane tool of the present utility model adopted is light-duty circulation material flexibly, in construction, can regulate, and install conveniently according to the needs of construction, can use repeatedly, thereby reduce construction turnover material, saved construction cost.And the installation of adopting this fetal membrane prodigiosin enough to make things convenient for the furnace wall anchoring to change, improve installation quality and construction speed.
Description of drawings
Fig. 1 is a structure scheme of installation of the present utility model.
Fig. 2 is the side cross-sectional schematic diagram of Fig. 1.
The horizontal support of mark among the figure: 1-, 2-is upright to support 3-anchored brick, 4-connecting screw rod, 5-cast wall, 6-template, 7-body of heater steel plate, 8-connecting hole.
The specific embodiment
Need construction to form cast wall 5 in the outside of the body of heater steel plate 7 of heating furnace, therefore be provided with heating furnace furnace wall loose tool tool.This furnace wall loose tool tool is connected to form the bracing frame of frame-like as shown in Figure 1 by at least one horizontal support 1 and upright support 2, bracing frame is connected by connecting screw rod 4 with body of heater steel plate 7 again, and be formed with level interval each other, the consistency of thickness of this spacing and cast wall 5, cast wall 5 thickness that cast is formed satisfy construction requirement.
In order to save and easy construction, connecting screw rod 4 and bracing frame link position are in horizontal support 1 and uprightly support 2 infall, and pass horizontal support 1 and uprightly support 2, and same like this connecting screw rod 4 just links together horizontal support 1, upright support 2 and body of heater steel plate 7.As depicted in figs. 1 and 2, be provided with prefabricated anchored brick 3 between bracing frame and body of heater steel plate 7, connecting screw rod 4 passes the connecting hole 8 on the anchored brick 3, and in the casting process of cast wall 5, anchored brick 3 forms integrative-structure with cast wall 5.
In order to satisfy the bulk strength of bracing frame, horizontal support 1 and upright 2 employing I-steel, channel-section steel or the angle steel that support.
Installed inside at bracing frame has facade template 6, guarantees the glacing flatness of cast wall 5, satisfies construction requirement.
Embodiment:
Construction requirement according to the heating furnace body of wall, at the outside of body of heater steel plate 7 unwrapping wire upright support 2 is installed, in horizontal support 1 and the upright connection crossover location boring of supporting between 2, connecting screw rod 4 is passed horizontal support 1 and upright support 2, pass the connecting hole 8 on the prefabricated profiled anchored brick 3 then, be connected on the body of heater steel plate 7, anchoring makes horizontal support 1, upright support 2, anchored brick 3 and body of heater steel plate 7 connect into integral body again.In a horizontal support 1 and a upright side that supports 2 bracing frames that form and body of heater steel plate 7 template 6 is installed, makes the casting space that forms cast wall 5 between template 6 and the body of heater steel plate 7, then the casting and constructing of casting complete cast wall 5.Remove horizontal support 1, upright support 2 and template 6, finish the construction of cast wall 5, horizontal support 1, upright support 2 and template 6 can be used for the use of next time constructing.

Claims (5)

1. heating furnace furnace wall loose tool tool is characterized in that: form bracing frame by at least one horizontal support (1) and upright support (2), above-mentioned bracing frame is connected by connecting bolt (4) with body of heater steel plate (7), and is formed with level interval each other.
2. heating furnace furnace wall loose tool tool as claimed in claim 1 is characterized in that: described connecting bolt (4) and the infall of bracing frame link position in horizontal support (1) and upright support (2), and pass horizontal support (1) and upright support (2).
3. heating furnace furnace wall loose tool tool as claimed in claim 1 or 2 is characterized in that: be provided with anchored brick (3) between bracing frame and body of heater steel plate (7), connecting bolt (4) passes the connecting hole (8) on the above-mentioned anchored brick (3).
4. heating furnace furnace wall loose tool tool as claimed in claim 1 is characterized in that: I-steel, channel-section steel or angle steel are adopted in described horizontal support (1) and upright support (2).
5. heating furnace furnace wall loose tool tool as claimed in claim 1 is characterized in that: the installed inside at bracing frame has facade template (6).
CN2009203028713U 2009-05-06 2009-05-06 Tyre mold for wall of heating furnace Expired - Lifetime CN201407901Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203028713U CN201407901Y (en) 2009-05-06 2009-05-06 Tyre mold for wall of heating furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203028713U CN201407901Y (en) 2009-05-06 2009-05-06 Tyre mold for wall of heating furnace

Publications (1)

Publication Number Publication Date
CN201407901Y true CN201407901Y (en) 2010-02-17

Family

ID=41678836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203028713U Expired - Lifetime CN201407901Y (en) 2009-05-06 2009-05-06 Tyre mold for wall of heating furnace

Country Status (1)

Country Link
CN (1) CN201407901Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101900486A (en) * 2010-04-02 2010-12-01 攀钢集团冶金工程技术有限公司 Multilayer roaster building method and hearth replacing method
CN103727792A (en) * 2012-10-15 2014-04-16 中国石油化工集团公司 Process for installing furnace body of tube-type heating furnace

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101900486A (en) * 2010-04-02 2010-12-01 攀钢集团冶金工程技术有限公司 Multilayer roaster building method and hearth replacing method
CN103727792A (en) * 2012-10-15 2014-04-16 中国石油化工集团公司 Process for installing furnace body of tube-type heating furnace

Similar Documents

Publication Publication Date Title
CN103628680B (en) Large steel space truss hanging layer construction method
CN104912320B (en) The method for synchronously constructing of subsiding crack both sides shear wall
CN106801510A (en) Plastic formwork early removing system
CN201407901Y (en) Tyre mold for wall of heating furnace
CN101845890B (en) Formwork suspending method of heating furnace top plastic material
CN201138139Y (en) Roof structure of continuous furnace
CN201406843Y (en) Adjustable flue arch stuffing supporting frame
CN207749421U (en) A kind of regulating device for controlling prefabricated stand column installation verticality
CN103437292B (en) The lifting combination unit of inclined in two-way A shape king-tower cable stayed bridge template
CN202853348U (en) Kiln head-kiln tail lining-resistant masonry structure of pelletizing rotary kiln
CN203501785U (en) Suspended precast block and one-piece casting combined furnace top construction
CN104989015B (en) The insulation mounting structure of stone curtain wall
CN102809282A (en) Refractory lining building structure for front end and back end of rotary kiln for pellet production
CN105910442A (en) Refractory brick hanging device and furnace top brickwork hanging method
CN208763436U (en) A kind of PC component supporting apparatus
CN206016262U (en) A kind of civil engineering building template link
CN201819553U (en) Furnace roof of pellet grate preheat smoke hood chamber
CN201358267Y (en) Installation rack of revolving furnace
CN104848693A (en) Quick construction method for lining layer of heating furnace
CN202024595U (en) Easy-built, easy-assembled and easy-disassembled feeding device of rotary kiln
CN106017104B (en) The offline building method of baking furnace flame path wall
CN203393634U (en) Lifting and combining device of cable-stayed bridge formworks of bidirectional tilting A-shaped main pylon
CN209817467U (en) Connecting structure of steel mould arch tire and support frame
CN205222001U (en) Coke chute sill plate structure
CN209341836U (en) A kind of suspension type running gate system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA 19TH METALLURGICAL CORPORATION

Free format text: FORMER OWNER: MCC SHIJIU CONSTRUCTION CO., LTD.

Effective date: 20110330

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 617000 MCC SHIJIU CONSTRUCTION CO., LTD., NO. 350, RENMIN STREET, PANZHIHUA CITY, SICHUAN PROVINCE TO: 617000 NO. 350, RENMIN STREET, EAST DISTRICT, PANZHIHUA CITY, SICHUAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110330

Address after: 617000 Panzhihua, Sichuan, East Street, No. 350

Patentee after: China 19th Metallurgical Corporation

Address before: 617000, Sichuan province Panzhihua City People's Street No. 350 MCC Long Construction Co., Ltd.

Patentee before: MCC Shijiu Construction Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20100217

CX01 Expiry of patent term