CN201388521Y CN200920089364U CN200920089364U CN201388521Y CN 201388521 Y CN201388521 Y CN 201388521Y CN 200920089364 U CN200920089364 U CN 200920089364U CN 200920089364 U CN200920089364 U CN 200920089364U CN 201388521 Y CN201388521 Y CN 201388521Y
Authority
CN
China
Prior art keywords
heat source
room
heat
heat pump
intensive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200920089364U
Other languages
Chinese (zh)
Inventor
王振海
谢德平
肖建国
罗秋全
邱龙宇
王广胜
李树坡
王太云
张要旭
李许涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PINGDINGSHAN BRANCH OF HENAN TOBACCO Co
Original Assignee
PINGDINGSHAN BRANCH OF HENAN TOBACCO Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PINGDINGSHAN BRANCH OF HENAN TOBACCO Co filed Critical PINGDINGSHAN BRANCH OF HENAN TOBACCO Co
Priority to CN200920089364U priority Critical patent/CN201388521Y/en
Application granted granted Critical
Publication of CN201388521Y publication Critical patent/CN201388521Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Central Heating Systems (AREA)

Abstract

The utility model relates to an intensive heat pump heat source kang room which carries out baking to the tobacco by arranging a heat pump on a circulating air duct of the kang room as a heat source. The intensive heat pump heat source kang room comprises a kang room and an insulating plate which divides the inner part the kang room into a baking chamber and a heat source chamber; the circulating air duct is formed between the baking chamber and the heat source chamber; the upper part of the insulating plate is provided with an upper circulating fan, and the lower part thereof is provided with a lower circulating fan; an air inlet of the lower circulating fan in the heat source chamber is provided with the heat pump connected with an outdoor machine; and an air exhaust port is also provided between the heat source chamber and the outside. The intensive heat pump heat source kang room has the advantages of easy temperature control, simple structure, low cost, good baking effect, energy conservation and high heat utilization rate.

Description

Intensive source heat pump heat a heatable brick bed room
Technical field
The utility model relates to a kind of by the intensive source heat pump heat a heatable brick bed room that heat pump toasts tobacco as thermal source is set on a heatable brick bed room circulation air path.
Background technology
Existing bulk curing barn all adopts coal to act as a fuel to the production of toasting of tobacco, and empty specification is 8m*2.7m*3.16m in the at present used bulk curing barn, is about 68m 3Barn can be adorned the bright cigarette of cigarette capacity: 3500~5000kg, and 1 barn can produce dried cigarette 405-578kg, and 1 barn coal consumption is 405-578Kg, and the calorific value of used coal is 20900KJ/kg, and the burning of coal utilization rate is 20%.Toast the bright cigarette of 1 barn and take 144-210h.According to above data, the heat that toasting the bright cigarette of 1 a heatable brick bed needs is: the calorific value * coal combustion utilization rate=578*20900*20%/4.2=575248Kcal=669Kw of Q=coal consumption * coal, promptly produce the heat of 669Kw, on average per hour need produce the heat of 4.6-3.1Kw in the 144-210h domestic demand of bakery running time.According to above data, select professional heat pump dryer PAKA-180G type for use, use the economy contrast of the coal heat source for baking tobacco different with heat pump: 1, the bright cigarette of baking 1 a heatable brick bed need be used coal: 578Kg, and the price of coal is: 0.8 yuan/Kg; 2, toasting the expense that the bright cigarette of 1 a heatable brick bed need consume with coal is: 462 yuan; 3, toast the bright cigarette of 1 a heatable brick bed with heat pump and need power consumption: 669/6*3=335Kw, the price of electricity is: 0.6 yuan/Kw; 4, toasting the expense that the bright cigarette of 1 a heatable brick bed need consume with heat pump is: 335*0.6=201 unit; From above data as can be seen with heat pump as the heat source for baking tobacco than saving about 261 yuan with the every room of coal tobacco, saved 56% expense.
Summary of the invention
The purpose of this utility model be to overcome the deficiencies in the prior art and provide that the control of a kind of temperature is easy, simple in structure, cost is low, cured effect good, save the energy, collection type source heat pump heat a heatable brick bed room that heat utilization ratio is high.
The purpose of this utility model is achieved in that the warming plate that comprises a heatable brick bed room, inside, a heatable brick bed room is separated formation baking vessel and heat source room, it is characterized in that: between baking vessel and heat source room, be formed with circulation air path, on warming plate top the cocycle blower fan is installed, circulating fan down is installed in the warming plate bottom, the air inlet place of circulating fan is provided with the heat pump that is connected with off-premises station down in heat source room, also has exhaust outlet between the heat source room and the external world.
Also have the hydrofuge ditch below the warming plate between baking vessel and heat source room.
The air outlet of corresponding cocycle blower fan also has exhaust outlet between the heat source room and the external world; The corresponding air outlet of circulating fan down also has air inlet between the heat source room and the external world.
The advantage that the utlity model has that temperature control is easy, simple in structure, cost is low, cured effect good, save the energy, heat utilization ratio is high.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Fig. 2 is a transversary cutaway view of the present utility model.
Fig. 3 is a vertical structure cutaway view of the present utility model.
The specific embodiment
As shown in Figure 1, 2, the utility model comprises a heatable brick bed room 1, inside, a heatable brick bed room is separated the warming plate 4 that forms baking vessel 2 and heat source room 3, it is characterized in that: between baking vessel 2 and heat source room 3, be formed with circulation air path 5, on warming plate 4 tops cocycle blower fan 6 is installed, circulating fan 7 down is installed in warming plate 2 bottoms, the air inlet place of circulating fan 7 is provided with the heat pump 8 that is connected with off-premises station 10 down in heat source room 3, also has exhaust outlet 9 between the heat source room 3 and the external world.
Also have hydrofuge ditch 11 below the warming plate 4 between baking vessel 2 and heat source room 3.The air outlet of corresponding cocycle blower fan also has exhaust outlet 9 between the heat source room 3 and the external world; The corresponding air outlet of circulating fan down also has air inlet 12 between the heat source room 3 and the external world.

Claims (3)

1, a kind of intensive source heat pump heat a heatable brick bed room, comprise a heatable brick bed room (1), inside, a heatable brick bed room separated the warming plate (4) that forms baking vessel (2) and heat source room (3), it is characterized in that: between baking vessel (2) and heat source room (3), be formed with circulation air path (5), on warming plate (4) top cocycle blower fan (6) is installed, circulating fan (7) down is installed in warming plate (2) bottom, the air inlet place of circulating fan (7) is provided with the heat pump (8) that is connected with off-premises station (10) down in heat source room (3), also has exhaust outlet (9) between the heat source room (3) and the external world.
2, intensive source heat pump heat a heatable brick bed according to claim 1 room is characterized in that: also have hydrofuge ditch (11) below the warming plate (4) between baking vessel (2) and heat source room (3).
3, intensive source heat pump heat a heatable brick bed according to claim 1 room, it is characterized in that: the air outlet of corresponding cocycle blower fan also has exhaust outlet (9) between the heat source room (3) and the external world; The corresponding air outlet of circulating fan down also has air inlet (12) between the heat source room (3) and the external world.
CN200920089364U 2009-04-02 2009-04-02 Intensive heat pump heat source kang room Expired - Fee Related CN201388521Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920089364U CN201388521Y (en) 2009-04-02 2009-04-02 Intensive heat pump heat source kang room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920089364U CN201388521Y (en) 2009-04-02 2009-04-02 Intensive heat pump heat source kang room

Publications (1)

Publication Number Publication Date
CN201388521Y true CN201388521Y (en) 2010-01-27

Family

ID=41595335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920089364U Expired - Fee Related CN201388521Y (en) 2009-04-02 2009-04-02 Intensive heat pump heat source kang room

Country Status (1)

Country Link
CN (1) CN201388521Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102342579A (en) * 2011-09-30 2012-02-08 四川省烟草公司泸州市公司 Hybrid-power roasting barn

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102342579A (en) * 2011-09-30 2012-02-08 四川省烟草公司泸州市公司 Hybrid-power roasting barn

Similar Documents

Publication Publication Date Title
CN201467972U (en) Solar tobacco leaf drying device
CN201615681U (en) Drying oven
CN204329319U (en) Biomass Briquette Hot-blast Stove
CN201388521Y (en) Intensive heat pump heat source kang room
CN201467903U (en) Screen drum type high-efficiency energy-saving tealeaf roasting machine
CN202938633U (en) Biomass burning aluminum smelting all-in-one machine
CN203116157U (en) Solar heating device
CN101886818A (en) Energy-saving and efficient return air furnace
CN201251169Y (en) Highly-effective energy-saving steam generator
CN208319014U (en) A kind of air-supply passage of oven
CN204063573U (en) Energy-efficient heating equipment
CN202066062U (en) Multipurpose energy-saving stove
CN201541694U (en) Bulk curing barn of concatemer assembled type biomass gasification furnace
CN201282727Y (en) 'Double-system ventilation' sitting type lower moisture-discharging tobacco leaf bulk curing barn
CN205090426U (en) High and few living beings kitchen of smog of combustion efficiency
CN204629581U (en) A kind of multifunctional combustion oven
CN202361414U (en) Wood and coal oven furnace
CN203397247U (en) An aerobic temperature and humidity intelligent regulating and controlling case for black tea fermentation
CN202511330U (en) Separated type cooking and warming boiler
CN202868745U (en) Multifunctional biomass direct combustion furnace
CN204853563U (en) Energy -conserving heating stove of intercommunication
CN208458026U (en) A kind of energy saving gas range
CN201925955U (en) Dual-purpose furnace for cooking and warming
CN209399353U (en) A kind of biomass energy combustion gas enamelware pot furnace apparatus
CN2735188Y (en) Internal-external heat energy-saving cooking and heating dual purpose stove

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100127