CN201386997Y - Forced circulation type waste heat boiler of cement kiln - Google Patents

Forced circulation type waste heat boiler of cement kiln Download PDF

Info

Publication number
CN201386997Y
CN201386997Y CN200920069938U CN200920069938U CN201386997Y CN 201386997 Y CN201386997 Y CN 201386997Y CN 200920069938 U CN200920069938 U CN 200920069938U CN 200920069938 U CN200920069938 U CN 200920069938U CN 201386997 Y CN201386997 Y CN 201386997Y
Authority
CN
China
Prior art keywords
boiler
pipe
heating surface
top cover
forced circulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200920069938U
Other languages
Chinese (zh)
Inventor
王渭清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongjiang Energy Recovery (Shanghai) Co Ltd
Original Assignee
Zhongjiang Energy Recovery (Shanghai) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongjiang Energy Recovery (Shanghai) Co Ltd filed Critical Zhongjiang Energy Recovery (Shanghai) Co Ltd
Priority to CN200920069938U priority Critical patent/CN201386997Y/en
Application granted granted Critical
Publication of CN201386997Y publication Critical patent/CN201386997Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/25Process efficiency

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

A forced circulation type waste heat boiler of a cement kiln is used for a waste heat boiler of the cement kiln and installed at the tail part of a cement rotary kiln and consists of a boiler, a heating surface tube bundle, a connecting tube bundle, a dust-removing shaker, wherein the boiler is a horizontal passage type structure, the heating surface is a snake-shaped tubular structure which is assembled and vertically suspended in a flue through a top cover box, smoke gas horizontally punches the heating surface tube bundles which is provided with the dust-removing shaker, and boiler water is forcedly circulated by a hot water circulation pump. The forced circulation type waste heat boiler of the cement kiln has the advantages that: the waste heat boiler is the horizontal passage type structure; the heating surface is the snake-shaped tubular structure, and the smoke gas horizontally punches the heating surface tube, therefore, the sealing performance is good and the heat transferring effect is excellent; the heating surface tube bundle is provided with the special shaker, therefore, the ashes is easy to clean and is not easy to accumulate, and the probability of accumulating bridge does not exist; and the boiler water is forcedly circulated by the hot water circulation pump, therefore, the circulation effect of the boiler water is stable, the tube explosion of the boiler is prevented, the arrangement of the heating surface tube bundle structure of the boiler is compact, and the steel material and the occupied area are saved.

Description

The forced circulation type kiln heat recovery boiler
Technical field
The utility model relates to kiln heat recovery boiler, particularly a kind of forced circulation steam filtration-kiln heat recovery boiler, be installed in the cement rotary kiln afterbody, the heat of the low-temperature flue gas that the kiln tail is got rid of produces the device of low-pressure superheated steam for the wheel unit generation by this patent equipment.
Background technology
At the cement kiln afterbody, kiln heat recovery boiler need be set reclaim heat.Existing boiler structure all is the vertical or horizontal Natural Circulation type of furnace, and in the interbank dust stratification bridging phenomenon that is prone to, metal consumption is bigger, poor sealing performance.
Summary of the invention
Technical problem to be solved in the utility model is to provide a kind of forced circulation type kiln heat recovery boiler, and boiler is the horizontal channel formula, and heating surface is that the coiled pipe structure vertically is suspended in the flue flue gas transversal flow heating surface pipe by the assembling of top cover case; Heated surface bundle has special rapping apparatus, and stove water is made forced circulation with hot water circulating pump; Waste heat boiler heating surface is that the coiled pipe structure is assembled into integral body by the top cover case, and boiler does not have wall pipe, good airproof performance, and the heated surface bundle compact conformation reduces steel consumption and saves the area.
The technical scheme in the invention for solving the above technical problem is, forced circulation type kiln heat recovery boiler of the present utility model, form by boiler, heated surface bundle, connection tube bank, ash disposal vibrator four parts, wherein, the stove tube cylindrical shell of boiler is formed by the roll of steel plate weldering, and the manhole device of 425 * 320mm is all arranged on the end socket at two ends; Boiler is a horizontal channel formula structure, and heating surface is that the coiled pipe structure vertically is suspended in the flue by the assembling of top cover case, the horizontal punching out heated surface bundle of flue gas, and heated surface bundle is equipped with the ash disposal rapping apparatus, stove water hot water circulating pump forced circulation.
Described heated surface bundle, be followed successively by superheater, evaporimeter, economizer from front to back, vertically be suspended in the flue, the structure of superheater, evaporimeter, economizer is assembled into integral body respectively by collection case, top cover case, furred ceiling pipe, coiled pipe, rapping pipe, be welded by connecting tube bank, wherein, the collection case is installed in the top cover upper box part again, the coiled pipe and the furred ceiling pipe of drawing from the collection case are suspended under the top cover case, seal with sleeve pipe when passing the top cover case; The coiled pipe bottom is connected with the rapping pipe.
Described top cover case is a cuboid steel plate hermetically-sealed construction, middle filling refractory material and insulation material.
The beneficial effects of the utility model are:
1, waste heat boiler is the horizontal channel formula, and the dust that mechanical vibrator falls falls into ash bucket, avoids with the discarded high-temperature blower that enters;
2, to be the coiled pipe structure vertically be suspended in the flue by the assembling of top cover case heating surface, flue gas transversal flow heating surface pipe, and good seal performance, heat-transfer effect are good;
3, heated surface bundle has special rapping apparatus, and deashing is easy, is difficult for dust stratification, the possibility that does not exist accumulation to put up a bridge;
4, stove water is made forced circulation with hot water circulating pump, and stove water circulating effect is stable, prevents the boiler booster, and the boiler heating surface Pipe bundle structure is arranged compact, saves steel and occupation of land.
Description of drawings
Fig. 1 is the structural representation of the utility model waste heat boiler.
Fig. 2 is a vertical view of the present utility model.
Fig. 3 is a right view of the present utility model.
Fig. 4 is the structural representation of the utility model heated surface bundle.
Fig. 5 is the side view of Fig. 4.
Label declaration in the accompanying drawing
The 1-drum
2-superheater 2 '-superheater bank
The tube bank of 3-evaporimeter 3 '-evaporimeter
The tube bank of 4-economizer 4 '-economizer
5-boiler jacket 6-connects tube bank 7-hot water circulating pump
8-ash disposal rapping apparatus 9-rapping pipe 10-collection case
The snakelike tube bank of 11-top cover case 12-furred ceiling pipe 13-
The specific embodiment
Below in conjunction with accompanying drawing structure of the present utility model is further described.
See also shown in Fig. 1~5, forced circulation type kiln heat recovery boiler of the present utility model is formed (seeing shown in Fig. 1~3) by drum 1, superheater bank 2 ', evaporimeter tube bank 3 ', economizer tube bank 4 ', boiler jacket 5, connection tube bank 6, hot water circulating pump 7, ash disposal rapping apparatus 8.
Described drum 1 cylindrical shell is formed by the roll of steel plate weldering, and the manhole device of 425 * 320mm is all arranged on the end socket at two ends; Two water level meters on the spot are housed on the boiler, and quartz ampoule and double-colored each one also leave two pairs of water level balance container joints in addition, for report to the police, the indication of control room water level and steam water-level regulate control use automatically.
Drum 1 is provided with relief valve connection, guarantees the unlikely superpressure of drum 1 pressure.
For preventing that foreign material from entering hot water circulating pump, filter is housed at the decline mouth of pipe.
On steelframe, an end is a hold-down support to drum 1 by two bearing supports, and the other end is a movable bearing support, and drum is free wxpansion vertically.
Described heated surface bundle (seeing shown in Fig. 4,5), heated surface bundle are the general name of superheater bank 2 ', evaporimeter tube bank 3 ', gas saver tube bank 4 '.
Every group of heated surface bundle structure is basic identical, is made up of top cover case 11, collection case 10, snakelike tube bank 13, furred ceiling pipe 12 and rapping pipe more than 9 parts, is assembled into integral body respectively, only need put during installation in the square hole that is placed on furnace roof, all around with furnace roof steel construction seal welding.
Top cover case 11 is a cuboid, steel plate hermetically-sealed construction, middle filling refractory material and insulation material.
The collection case 10 of heated surface bundle is installed in top cover case 11 tops.The snakelike tube bank 13 and the furred ceiling pipe 12 of drawing from collection case 10 are hung in the top cover case 11 times, seal with sleeve pipe when passing top cover case 11.
Snakelike tube bank 13 and furred ceiling pipe 12 all participate in the circulation of stove water, connection between furred ceiling pipe 12 and the snakelike tube bank 13 is as hinge, snakelike tube bank 13 is freely swung in certain scope, the rapping pipe 9 that can be fixed under the effect of ash disposal rapping apparatus 8 in the tube bank obtains bump, reaches the dedusting purpose.When being heated, snakelike tube bank 13 can also freely expand downwards.
Described boiler jacket 5 is formed horizontal flue, heated surface bundle (with flue gas flow direction) from front to back is followed successively by superheater 2, evaporimeter 3, economizer 4, vertically be suspended in the flue, flue gas transversal flow hot side pipe, make the flue gas that passes through obtain the cooling cooling, the intrafascicular aqueous medium of heating surface tube is heated to heat up and produces steam.
Described connection tube bank 6 is the connecting pipe between boiler drum 1, hot water circulating pump 7 heated surface bundles.Boiler feedwater at first enters economizer 4 preheatings by connecting tube bank 6, enters drum 1 then, and the stove water in the drum 1 enters hot water circulating pump 7 by connecting piping 6, and stove water is depressed by connecting tube bank 6 in adding of hot water circulating pump 7 and entered evaporimeter 3; Become steam water interface by the stove water after the evaporimeter heating, go out evaporimeter and turn back to drum 1; Steam water interface is done carbonated drink separation in drum 1, the stove water after the separation enters hot water circulating pump 7 by connection tube bank 6 and circulates once more.Isolated steam enters superheater 2 in drum 1; Steam after heating sees the Turbo-generator Set generating off by pipeline or hot user uses.
Described ash disposal rapping apparatus 8, heated surface bundle adopt efficient elasticity rapping mode, and the tube bank of every group of heating surface all has special rapping apparatus, and the rapping pipe is the heat-resistance stainless steel pipe.Rapping is to hit the pipe row who shakes and can freely swing by motor drives spring hammering device, removes the dust stratification on the tube wall, and dust stratification falls into ash bucket and discharges body of heater.

Claims (3)

1, a kind of forced circulation type kiln heat recovery boiler is characterized in that:
Form by boiler, heated surface bundle, connection tube bank, ash disposal vibrator four parts, wherein, boiler is a horizontal channel formula structure, heating surface is that the coiled pipe structure vertically is suspended in the flue by the assembling of top cover case, the horizontal punching out heated surface bundle of flue gas, heated surface bundle is equipped with the ash disposal rapping apparatus, stove water hot water circulating pump forced circulation.
2, forced circulation type kiln heat recovery boiler according to claim 1 is characterized in that:
Described heated surface bundle, be followed successively by superheater, evaporimeter, economizer from front to back, vertically be suspended in the flue, the structure of superheater, evaporimeter, economizer is assembled into integral body respectively by collection case, top cover case, furred ceiling pipe, coiled pipe, rapping pipe, be welded by connecting tube bank, wherein, the collection case is installed in the top cover upper box part again, the coiled pipe and the furred ceiling pipe of drawing from the collection case are suspended under the top cover case, seal with sleeve pipe when passing the top cover case; The coiled pipe bottom is connected with the rapping pipe.
3, forced circulation type kiln heat recovery boiler according to claim 1 is characterized in that:
Described top cover case is a cuboid steel plate hermetically-sealed construction, middle filling refractory material and insulation material.
CN200920069938U 2009-04-03 2009-04-03 Forced circulation type waste heat boiler of cement kiln Expired - Fee Related CN201386997Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920069938U CN201386997Y (en) 2009-04-03 2009-04-03 Forced circulation type waste heat boiler of cement kiln

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920069938U CN201386997Y (en) 2009-04-03 2009-04-03 Forced circulation type waste heat boiler of cement kiln

Publications (1)

Publication Number Publication Date
CN201386997Y true CN201386997Y (en) 2010-01-20

Family

ID=41579531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920069938U Expired - Fee Related CN201386997Y (en) 2009-04-03 2009-04-03 Forced circulation type waste heat boiler of cement kiln

Country Status (1)

Country Link
CN (1) CN201386997Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103512017A (en) * 2013-09-25 2014-01-15 欧萨斯能源环境设备(南京)有限公司 Screen-type evaporator of Isa furnace
CN103542731A (en) * 2013-10-30 2014-01-29 江西自立资源再生有限公司 Device and method for cooling smoke of anode furnace
CN104154513A (en) * 2014-04-23 2014-11-19 盐城市锅炉制造有限公司 Waste heat boiler of can-type calcinator
CN109631596A (en) * 2018-11-28 2019-04-16 无为华塑矿业有限公司 A kind of limekiln flue gas heat recovery system
CN113882922A (en) * 2021-09-16 2022-01-04 华润水泥(陆川)有限公司 Automatic power generation control system of boiler waste heat

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103512017A (en) * 2013-09-25 2014-01-15 欧萨斯能源环境设备(南京)有限公司 Screen-type evaporator of Isa furnace
CN103512017B (en) * 2013-09-25 2016-03-30 欧萨斯能源环境设备(南京)有限公司 A kind of Screen-type evaporator of Isa furnace
CN103542731A (en) * 2013-10-30 2014-01-29 江西自立资源再生有限公司 Device and method for cooling smoke of anode furnace
CN104154513A (en) * 2014-04-23 2014-11-19 盐城市锅炉制造有限公司 Waste heat boiler of can-type calcinator
CN109631596A (en) * 2018-11-28 2019-04-16 无为华塑矿业有限公司 A kind of limekiln flue gas heat recovery system
CN113882922A (en) * 2021-09-16 2022-01-04 华润水泥(陆川)有限公司 Automatic power generation control system of boiler waste heat

Similar Documents

Publication Publication Date Title
CN201386997Y (en) Forced circulation type waste heat boiler of cement kiln
CN100559076C (en) Subcritical pressure pouring boiler furnace
CN201382702Y (en) Power generation boiler for low-temperature flue gas waste heat in avasite heat furnace
CN202349976U (en) Waste heat boiler for zinc concentrate acid-making
CN103868043A (en) Exhaust heat boiler equipment of coal gasification device
CN103900410B (en) A kind of phase change heat exchange device and heat-exchange method thereof
US4398501A (en) System for recovering latent and sensible heat of effluent gases from a melting installation
CN210424994U (en) Siphon type drainage device of horizontal boiler snakelike tubular economizer
CN104406144A (en) Double-medium waste heat boiler
CN204372879U (en) A kind of two medium waste heat boiler
CN207230919U (en) A kind of chain grate hot-water boiler with boiler tail afterheat energy-saving environmental protecting device
CN206036985U (en) High ash content low -temperature exhaust -heat boiler
CN214038332U (en) Power generation system is collected in melting reduction waste heat circulation
CN205825033U (en) High parameter garbage burning boiler with reheating
CN205388305U (en) Novel low temperature second grade economizer
CN206377842U (en) A kind of boilers and pressure vessel blowdown waste-heat recovery device
CN202048555U (en) Sensible heat afterheat recycling device with special heating surface structure
CN201050774Y (en) Subcritical pressure steam injection boiler
CN110578916A (en) Siphon type drainage device of horizontal boiler snakelike tubular economizer
CN101187467A (en) Low discharge high energy efficiency vertical shell type water-fire tube boiler
CN110630995A (en) Positive pressure horizontal water pipe waste heat boiler
CN201259206Y (en) Glass kiln power generation boiler by waste heat
CN213930893U (en) Boiler flue waste heat recycling device
CN204880727U (en) Water pipe wherein heart integrative stove of condensation that strile -backs
CN210891593U (en) Positive pressure horizontal water pipe waste heat boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Zhongjiang energy recovery (Yangzhou) Co., Ltd.

Assignor: Zhongjiang Energy Recovery (Shanghai) Co., Ltd.

Contract record no.: 2012310000058

Denomination of utility model: Forced circulation type waste heat boiler of cement kiln

Granted publication date: 20100120

License type: Exclusive License

Record date: 20120518

EE01 Entry into force of recordation of patent licensing contract

Assignee: Zhongjiang energy recovery (Yangzhou) Co., Ltd.

Assignor: Zhongjiang Energy Recovery (Shanghai) Co., Ltd.

Contract record no.: 2012310000058

Denomination of utility model: Forced circulation type waste heat boiler of cement kiln

Granted publication date: 20100120

License type: Exclusive License

Record date: 20120518

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100120

Termination date: 20170403