CN201362807Y - Track girder subgrade for large walking crane - Google Patents

Track girder subgrade for large walking crane Download PDF

Info

Publication number
CN201362807Y
CN201362807Y CNU2009200677488U CN200920067748U CN201362807Y CN 201362807 Y CN201362807 Y CN 201362807Y CN U2009200677488 U CNU2009200677488 U CN U2009200677488U CN 200920067748 U CN200920067748 U CN 200920067748U CN 201362807 Y CN201362807 Y CN 201362807Y
Authority
CN
China
Prior art keywords
concrete
track girder
subgrade
track beam
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2009200677488U
Other languages
Chinese (zh)
Inventor
曹辉
王萱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CNU2009200677488U priority Critical patent/CN201362807Y/en
Application granted granted Critical
Publication of CN201362807Y publication Critical patent/CN201362807Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The utility model relates to a track girder subgrade for a large walking crane. The track girder subgrade comprises a concrete bearing platform, and is characterized in that a concrete track girder is arranged above the concrete bearing platform, wherein wheel rails are placed at the upper end of the concrete track girder; and soft fiber boards are arranged between the concrete bearing platform and the concrete track girder. The track girder subgrade with the structure can achieve more rapid and convenient construction, lower the construction cost and provide conditions for large-area constructions.

Description

A kind of rail beam roadbed that is used for large-scale stepped type tower crane
Technical field:
The utility model relates to a kind of large-scale stepped type tower crane field, particularly a kind of rail beam roadbed that is used for large-scale stepped type tower crane.
Background technology:
In order to solve the large-scale stepped type tower crane of ZSL55145 (1060t.m) roadbed, as adopt the steel plate subgrade case must special subgrade case, cost on making or leasing is very expensive, adopt the steel plate subgrade case on the other hand, according to construction requirement, steel plate subgrade case total length reaches 1152 meters, does not have so many special subgrade case on the market at all.
Summary of the invention:
The purpose of this utility model is a kind of rail beam roadbed that is used for large-scale stepped type tower crane, can address the above problem.
To achieve these goals, the technical solution of the utility model is as follows: a kind of rail beam roadbed that is used for large-scale stepped type tower crane, comprise the concrete cushion cap, it is characterized in that concrete cushion cap top is provided with the concrete track beam, this concrete track beam upper end is provided with rail, is provided with soft fiberboard between concrete cushion cap and the concrete track beam.
Adopt such structure, make that construction is more convenient, more reduced construction cost, for large-area construction provides condition.
The utility model
Description of drawings:
Accompanying drawing is a structural representation of the present utility model
The specific embodiment:
Below in conjunction with drawings and Examples the utility model is elaborated.
A kind of rail beam roadbed that is used for large-scale stepped type tower crane comprises concrete cushion cap 1, it is characterized in that concrete cushion cap 1 top is provided with concrete track beam 2, and these concrete track beam 2 upper ends are provided with rail 3, are provided with soft fiberboard 4 between concrete cushion cap 1 and the concrete track beam 2.Rail 3 is as the walking rail of tower crane, soft fiberboard 4 be used between concrete track beam 2 and the concrete cushion cap 1 effective separation and as bed die.
According to an embodiment, be used for ZSL55145 (1060t.m) stepped type tower crane cast-in-situ concrete rail beam ground, the concrete track beam is in place builds, and the planeness of concrete track beam position and rail beam is just controlled by ZSL55145 (1060t.m) stepped type tower crane arrangement requirement and instructions for use.When finding that as rail beam sedimentation exceeds 60mm, the scene can adopt ZSL55145 (1060t.m) stepped type tower crane to adjust, and the every 12m segmentation of concrete track beam is built, deadweight 35t.ZSL55145 (1060t.m) stepped type tower crane is in the 26.5m radius of clean-up, and biggest lifting capacity 40t capable of hoisting satisfies the requirement of lifting capacity.The scene considers because the cast in situs of concrete track beam, soft fiberboard 4 that may adopt and concrete cushion cap 1 fail to isolate fully between reinforcing, therefore on-the-spot special small-sized portal frame, two ends at 12m concrete track beam, utilize the lifting built-in fitting of burying underground in advance as suspension centre, utilize the jack of 50t to carry the empty issuable settlement issues of concrete track beam that solves.

Claims (1)

1, a kind of rail beam roadbed that is used for large-scale stepped type tower crane comprises the concrete cushion cap, it is characterized in that concrete cushion cap top is provided with the concrete track beam, and this concrete track beam upper end is provided with rail, is provided with soft fiberboard between concrete cushion cap and the concrete track beam.
CNU2009200677488U 2009-02-16 2009-02-16 Track girder subgrade for large walking crane Expired - Lifetime CN201362807Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2009200677488U CN201362807Y (en) 2009-02-16 2009-02-16 Track girder subgrade for large walking crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2009200677488U CN201362807Y (en) 2009-02-16 2009-02-16 Track girder subgrade for large walking crane

Publications (1)

Publication Number Publication Date
CN201362807Y true CN201362807Y (en) 2009-12-16

Family

ID=41473467

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2009200677488U Expired - Lifetime CN201362807Y (en) 2009-02-16 2009-02-16 Track girder subgrade for large walking crane

Country Status (1)

Country Link
CN (1) CN201362807Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108277704A (en) * 2018-01-05 2018-07-13 中铁工程设计咨询集团有限公司 A kind of straddle-type monorail composite bridge track and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108277704A (en) * 2018-01-05 2018-07-13 中铁工程设计咨询集团有限公司 A kind of straddle-type monorail composite bridge track and its construction method
CN108277704B (en) * 2018-01-05 2023-08-08 中铁工程设计咨询集团有限公司 Straddle type monorail combined bridge rail bearing platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN201089696Y (en) Spar boom of explosion-proof suspension crane
CN202131563U (en) Combined gate type bridge pier for one-step suspension in position of steel crossbeam
CN201419626Y (en) hydraulic suspension mechanism
CN201619972U (en) Caterpillar crane provided with caterpillar type super-hoisting counterweight car
CN102060241A (en) Universal crane for construction process of high-speed railway sound barrier
CN201932846U (en) Universal crane used in construction process of high-speed railway noise barrier
CN201362807Y (en) Track girder subgrade for large walking crane
CN202880701U (en) Trackless gantry crane
CN210366808U (en) Lifting and dismantling device for rail walking
CN202000221U (en) Ballastless track structure for steep slope subgrade
CN204529248U (en) Vehicle-mounted mobile platform is installed in gobo lifting
CN201128876Y (en) Horizontal movement device for box girder segment of viaduct bridge
CN207373758U (en) A kind of big draw box mechanism in Novel clean intelligent mobile station
CN204530506U (en) End bay closing device
CN203904840U (en) Novel frame bridge jacking jigger
CN203891055U (en) Steel-structure base device for tower crane
CN201695287U (en) Ballastless track pouring trolley
CN202657861U (en) Pipeline assembly trolley
CN207312376U (en) A kind of stable big draw box mechanism in intelligent mobile station
CN202913360U (en) Bridge floor rotary hoisting device
CN205576656U (en) Rail that bridge floor railway was laid welds rail production line
CN201087075Y (en) Trackless portal jib crane
CN206345616U (en) A kind of building tower crane of stable safety
CN201971595U (en) Factory building crane beam height adjustment device
CN201024051Y (en) All-hydraulic rail-free type gantry crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20091216