CN201277042Y - Shaft-well digger - Google Patents

Shaft-well digger Download PDF

Info

Publication number
CN201277042Y
CN201277042Y CNU2008201382198U CN200820138219U CN201277042Y CN 201277042 Y CN201277042 Y CN 201277042Y CN U2008201382198 U CNU2008201382198 U CN U2008201382198U CN 200820138219 U CN200820138219 U CN 200820138219U CN 201277042 Y CN201277042 Y CN 201277042Y
Authority
CN
China
Prior art keywords
operating room
digger
well
digger blade
machine hammer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008201382198U
Other languages
Chinese (zh)
Inventor
魏万军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
URUMQI DABANREN METALLURGICAL CHEMICAL CO Ltd
Original Assignee
URUMQI DABANREN METALLURGICAL CHEMICAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by URUMQI DABANREN METALLURGICAL CHEMICAL CO Ltd filed Critical URUMQI DABANREN METALLURGICAL CHEMICAL CO Ltd
Priority to CNU2008201382198U priority Critical patent/CN201277042Y/en
Application granted granted Critical
Publication of CN201277042Y publication Critical patent/CN201277042Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a shaft-well digger, which belongs to excavating machinery. A lifting frame of the shaft-well digger is formed by connecting three layers of level racks, the surface of each level rack is paved with an annular guard board, and well wall fixed cylinders are uniformly distributed circumferentially on each level rack. A digging shovel operating room and a mechanical hammer operating room are suspended on an annular track below the bottom level rack, and a digging shovel and a mechanical hammer are connected to a frame of respective operating room. Each operating room is equipped with a rotary disc at the top, a track traveling wheel connected to the rotary disc is fixed on the annular track, and the rotary disc is connected with the traveling wheel via a driving element and a hydraulic motor. A space safety switch and an interlocked brake are arranged between the digging shovel operating room and the mechanical hammer operating room. The shaft-well digger can effectively avoid safety accidents, and increases working efficiency hundred times compared with manual digging, thereby fundamentally improving well digging operation.

Description

Shaft-well digger
1, technical field:
The utility model belongs to excavation machinery, especially a kind of excavator of the usefulness of digging well.
2, background technology:
The excavation of vertical shaft and to slag tap be by manually carrying out always, for the quickening progress need cooperate explosion, this just causes the loose falling rocks that forms of well bore wall rock easily, and therefore personnel casualty accidents often takes place.As time goes on, though excavate and the instrument of slagging tap improves to some extent, but want manually-operated.Not only progress is slow, and the safety of excavating personnel still is topmost problem.
3, summary of the invention:
The purpose of this utility model is a kind of shaft-well digger of design, and it can be fixed on borehole wall differing heights and be excavated downwards and upwards promoted by machinery, prevents falling object injury personnel and goods and materials, and improves excavation speed greatly.In order to realize this goal, adopted following technical scheme: the excavator lifting frame is formed by connecting by three layers of level frame up and down, all is covered with annular guard board on the frame face of every layer of level frame, and leaving a blank in the frame center becomes the dirt-excluding bucket hoist trunk.On three layers of level frame the borehole wall fixed oil cylinder that is uniformly distributed along the circumference is arranged all, the oil cylinder piston boom end has borehole wall positioning tooth.The wire rope that is connected with the ground elevator is arranged on the level frame at top.Below the level frame of bottom circular orbit is arranged, lifting the operating room of digger blade and machine hammer on the track, digger blade and machine hammer are connected on the framework of operating room separately.Rotating disk is arranged at each operating room top, connects the track travel wheel above the rotating disk, and road wheel is positioned on the circular orbit.Rotating disk is connected with hydraulic motor by driving member with road wheel.The swing arm and the scraper bowl that connect digger blade on the framework of digger blade operating room, the swing arm and the tup of connection machine hammer on the framework of machine hammer operating room have spacing discharge cock and interlock brake between digger blade operating room and machine hammer operating room.Another kind of scheme is: lifting the mounting seat of digger blade and machine hammer on the circular orbit below the level frame of lifting frame bottom, rotating disk is arranged at the mounting seat top, connects the track travel wheel above the rotating disk, and road wheel is positioned on the circular orbit.Rotating disk is connected with hydraulic motor by driving member with road wheel, and digger blade and machine hammer are connected on separately the mounting seat; Spacing discharge cock and interlock brake are arranged between digger blade mounting seat and machine hammer mounting seat; On circular orbit inboard, the mounting seat and on the swing arm of digger blade illuminating lamp and monitoring camera are being installed, the operating room of the operating mechanism that display screen and the work of control digging element are installed is being arranged on well head ground.
Shaft-well digger can be stopped security incident effectively, and compares into hundred times of ground and improved operating efficiency with manually digging well, and makes the work of digging well that the change of essence take place.
4, description of drawings:
Fig. 1 is the structural representation that has the shaft-well digger of digger blade part.Fig. 2 is the machine hammer structural representation partly that shaft-well digger has.Fig. 3 is the structural representation of the operatorless shaft-well digger in down-hole.
5, the specific embodiment:
Be further described below in conjunction with accompanying drawing.Clear in order to illustrate, shaft-well digger is described in Fig. 1 and Fig. 2 respectively with digger blade and machine hammer that machine is equipped with.As shown in Figure 1, the lifting frame of excavator in pit shaft is formed by connecting by the level frame 4 of three layers of hollow section making up and down, on the frame face of every layer of level frame annular guard board is arranged all, backplate can stop falling object and as the mechanical arrangements platform, can reinforce or safeguard the usefulness of the borehole wall simultaneously for the staff.Leaving a blank in the level frame center becomes the dirt-excluding bucket hoist trunk.Four borehole wall fixed oil cylinders 3 that are uniformly distributed along the circumference are all arranged on the crossbeam of three layers of level frame, and the oil cylinder among Fig. 1 is installed in the hollow section crossbeam, and the oil cylinder piston boom end has borehole wall positioning tooth 2, makes excavator fixing so that carry out digging operation on pit shaft.The oscilaltion of excavator is moved, be fixed oil cylinder remove fixing back by the wire rope 1 on the top, horizontal frame by the ground hoister control.Below the level frame of bottom circular orbit 5 is arranged, lifting the operating room of digger blade and machine hammer on the track, digger blade and machine hammer are connected on the framework of operating room separately.The swing arm 7 and the scraper bowl 8 that connect digger blade on the framework of digger blade operating room 6, the motor 12 of the swing arm 11 of connection machine hammer, tup 13 and driving tup on the framework of machine hammer operating room 14.Rotating disk 9 is arranged at each operating room top, connects track travel wheel 10 above the rotating disk, and road wheel is positioned on the circular orbit.Rotating disk is connected with hydraulic motor by driving member with road wheel, and under fluid motor-driven, operating room can move along circular orbit by road wheel, also can realize rotation by rotating disk, to make things convenient for the operation from different perspectives of digger blade and machine hammer.The operating mechanism that hydraulic pressure and other equipment are arranged in the operating room.Spacing discharge cock and interlock brake are arranged between digger blade operating room and machine hammer operating room, can guarantee that when digger blade and machine hammer are worked simultaneously they can not collide, make their operating rooms when digging operation fixing motionless in orbit simultaneously again.Digger blade and machine hammer can be simultaneously or alternately operating, by two operators at downhole operations.The another embodiment of shaft-well digger is: lifting the mounting seat 17 of digger blade and machine hammer on the circular orbit 5 below the lifting frame bottom level frame, digger blade and machine hammer are connected on separately the mounting seat; Rotating disk 9 is arranged at the mounting seat top, connects track travel wheel 10 above the rotating disk, and road wheel is positioned on the circular orbit.Rotating disk is connected with hydraulic motor by driving member with road wheel, and under fluid motor-driven, mounting seat can move along circular orbit by road wheel, also can realize rotation by rotating disk, to make things convenient for the operation from different perspectives of digger blade and machine hammer.Spacing discharge cock and interlock brake are arranged between digger blade mounting seat and machine hammer mounting seat; Monitoring camera 15 and illuminating lamp 16 are being installed on circular orbit inboard, the mounting seat and on the swing arm of digger blade, the operating room of the operating mechanism that display screen and the work of control digging element are installed is being arranged on well head ground.The down-hole can unattended digging operation, and operating personnel can control shaft-well digger work in the terrestrial operation chamber.

Claims (5)

1, shaft-well digger is made up of lifting frame, digger blade and machine hammer, it is characterized in that: the excavator lifting frame is formed by connecting by three layers of level frame (4) up and down, all be covered with annular guard board on the frame face of every layer of level frame, leaving a blank in the level frame center becomes the dirt-excluding bucket hoist trunk; On three layers of level frame the borehole wall fixed oil cylinder (3) that is uniformly distributed along the circumference is arranged all, the oil cylinder piston boom end has borehole wall positioning tooth (2); The wire rope (1) that is connected with the ground elevator is arranged on the level frame at top; Below the level frame of bottom circular orbit (5) is arranged, lifting operating room (6) and (14) of digger blade and machine hammer on the track, digger blade and machine hammer are connected on the framework of operating room separately; Spacing discharge cock and interlock brake are arranged between digger blade operating room and machine hammer operating room.
2, shaft-well digger is made up of lifting frame, digger blade and machine hammer, it is characterized in that: the excavator lifting frame is formed by connecting by three layers of level frame (4) up and down, all be covered with annular guard board on the frame face of every layer of level frame, leaving a blank in the level frame center becomes the dirt-excluding bucket hoist trunk; On three layers of level frame the borehole wall fixed oil cylinder (3) that is uniformly distributed along the circumference is arranged all, the oil cylinder piston boom end has borehole wall positioning tooth (2); The wire rope (1) that is connected with the ground elevator is arranged on the level frame at top; Below the level frame of bottom circular orbit (5) is arranged, lifting the mounting seat (17) of digger blade and machine hammer on the track, digger blade and machine hammer are connected on separately the mounting seat; Spacing discharge cock and interlock brake are arranged between digger blade mounting seat and machine hammer mounting seat; Monitoring camera (15) and illuminating lamp (16) are being installed on circular orbit inboard, the mounting seat and on the swing arm of digger blade, the operating room of the operating mechanism that display screen and the work of control digging element are installed is being arranged on well head ground.
3, shaft-well digger as claimed in claim 1 is characterized in that: the lifting connected mode of operating room and track is that rotating disk (9) is arranged at operating room (6) and (14) top, connects track travel wheel (10) above the rotating disk, and road wheel is positioned on the circular orbit; Rotating disk is connected with hydraulic motor by driving member with road wheel.
4, shaft-well digger as claimed in claim 1, it is characterized in that: digger blade and machine hammer and the framework ways of connecting of operating room separately are swing arm (7) and the scraper bowl (8) that is connected digger blade on the framework of digger blade operating room (6), connect the swing arm (11) and the tup (13) of machine hammer on the framework of machine hammer operating room (14).
5, shaft-well digger as claimed in claim 2, it is characterized in that: it is that rotating disk (9) is arranged at the mounting seat top that mounting seat is connected with the lifting of track, connect track travel wheel (10) above the rotating disk, road wheel is positioned on the circular orbit, and rotating disk is connected with hydraulic motor by driving member with road wheel.
CNU2008201382198U 2008-09-28 2008-09-28 Shaft-well digger Expired - Fee Related CN201277042Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201382198U CN201277042Y (en) 2008-09-28 2008-09-28 Shaft-well digger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201382198U CN201277042Y (en) 2008-09-28 2008-09-28 Shaft-well digger

Publications (1)

Publication Number Publication Date
CN201277042Y true CN201277042Y (en) 2009-07-22

Family

ID=40894628

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201382198U Expired - Fee Related CN201277042Y (en) 2008-09-28 2008-09-28 Shaft-well digger

Country Status (1)

Country Link
CN (1) CN201277042Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374603A (en) * 2019-08-21 2019-10-25 中铁工程装备集团有限公司 A kind of collection slag device and its implementation method for open caisson shaft excavation machine
CN111720122A (en) * 2020-05-25 2020-09-29 浙江中智物联科技集团有限公司 Vertical shaft tunneling device of three-dimensional parking garage
CN114033385A (en) * 2021-11-09 2022-02-11 中铁工程装备集团有限公司 Shaft boring machine and shaft boring method
CN114320306A (en) * 2022-01-14 2022-04-12 湘潭大学 Hoisting mechanical arm for shaft slag removal and using method thereof
CN115773116A (en) * 2023-02-10 2023-03-10 中国建筑西南勘察设计研究院有限公司 Circular track type drilling equipment and drilling method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374603A (en) * 2019-08-21 2019-10-25 中铁工程装备集团有限公司 A kind of collection slag device and its implementation method for open caisson shaft excavation machine
CN111720122A (en) * 2020-05-25 2020-09-29 浙江中智物联科技集团有限公司 Vertical shaft tunneling device of three-dimensional parking garage
CN111720122B (en) * 2020-05-25 2022-04-29 浙江中智物联科技集团有限公司 Vertical shaft tunneling device of three-dimensional parking garage
CN114033385A (en) * 2021-11-09 2022-02-11 中铁工程装备集团有限公司 Shaft boring machine and shaft boring method
CN114320306A (en) * 2022-01-14 2022-04-12 湘潭大学 Hoisting mechanical arm for shaft slag removal and using method thereof
CN115773116A (en) * 2023-02-10 2023-03-10 中国建筑西南勘察设计研究院有限公司 Circular track type drilling equipment and drilling method

Similar Documents

Publication Publication Date Title
CN201277042Y (en) Shaft-well digger
CN202467844U (en) Silo excavator
CN201723151U (en) Downhole excavator
KR101617174B1 (en) Diaphragm wall excavator
CN206721958U (en) A kind of full-automatic open caisson digging system of major diameter
CN101205728A (en) Endless-tracked multifunctional rotary excavating driller
CN201400901Y (en) Multifunctional hoisting and excavating machine
CN101839003A (en) Multifunctional crane excavator
CN201865563U (en) Multifunctional rotary drilling rig
JP3818519B2 (en) Drilling tool for earth drill
CN201598980U (en) Full hydraulic multifunctional machine for drilling and excavation
CN103103997A (en) Hydraulic excavator in coal mine
CN104234031A (en) Full-automatic hooking and unhooking dynamic compactor
CN204851264U (en) Shaft construction is slagged tap and is dug all -in -one with grabbing
CN101736764B (en) Impact type excavating device
CN202925582U (en) Coal mine underground hydraulic excavator
CN212249847U (en) Rotary drilling bit and rotary drilling machine with same
CN201486562U (en) Mine and tunnel excavator
CN204510303U (en) Multi-arm combination amplitude variation type excavates and bores dress all-in-one
CN211777162U (en) Suspension arm down-the-hole hammer drilling equipment
CN111648426B (en) Drilling and grabbing device and winch for underground diaphragm wall construction
JP6150486B2 (en) Grab dredger
CN213296462U (en) Self-adaptive scraper device for rotary digging machine
CN202466659U (en) Hydraulic rotary grab bucket of piling machine
CN107761938B (en) Transverse sewer dredging system and dredging method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090722

Termination date: 20110928