CN201209710Y - Synthesis tube holder arrangement structure - Google Patents

Synthesis tube holder arrangement structure Download PDF

Info

Publication number
CN201209710Y
CN201209710Y CNU2008203009099U CN200820300909U CN201209710Y CN 201209710 Y CN201209710 Y CN 201209710Y CN U2008203009099 U CNU2008203009099 U CN U2008203009099U CN 200820300909 U CN200820300909 U CN 200820300909U CN 201209710 Y CN201209710 Y CN 201209710Y
Authority
CN
China
Prior art keywords
pipe support
breast wall
comprehensive
retaining wall
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008203009099U
Other languages
Chinese (zh)
Inventor
唐雄俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Sixth Metallurgical Construction Co., Ltd.
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CNU2008203009099U priority Critical patent/CN201209710Y/en
Application granted granted Critical
Publication of CN201209710Y publication Critical patent/CN201209710Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a layout structure for a comprehensive pipe support, which comprises a pipe support (1), a breast wall (2) and pipe support beams (3). One end of each pipe support beam (3) is connected with the pipe support (1), and the other end is connected with the breast wall (2). The breast wall (2) is provided with an embedded part (4). In the utility model, the comprehensive pipe support and the breast wall are arranged in a unified way when being designed; one end of each pipe support beam is fixed on the pipe support, and the other end is fixed on the breast wall. In this way, a pipe support and a foundation on one side can be omitted; the capital investment is saved. On the other hand, just one side of the breast wall is provided with the pipe support, thus saving the factory space. The breast wall is provided with the embedded part, thus fixing the pipe support beams conveniently and ensuring the safety of the pipe support beams; the pipe support beams are in the number of one layer or more than one layer. In this way, the factory space can be further saved.

Description

A kind of layout of comprehensive pipe support
Technical field
The utility model relates to a kind of comprehensive pipe support, particularly a kind of layout of comprehensive pipe support.
Background technique
In mountain area building industry enterprise, in order to reduce earth and rock works amount and foundation engineering amount, reduce investment, generally all need to be provided with a lot of retaining walls.Simultaneously, in industrial enterprise, because manufacturing technique requirent, need to arrange various pipelines and cable, in existing design, usually all various pipelines and cable arrangements on comprehensive pipe support, reach and save the area, reduce the purpose of investment.But existing comprehensive pipe support all is on two pipe support pillars the pipe support crossbeam to be set, retaining wall and comprehensive pipe support are independently arranged often, such method for arranging, comprehensive pipe support and retaining wall have the structure of oneself respectively, certainly exist the big shortcoming of investment and take up an area of many problems.
The model utility content:
The technical problems to be solved in the utility model is: the layout of the comprehensive pipe support that a kind of floor space is little, investment is low, rationally distributed is provided, can overcomes the deficiencies in the prior art.
The technical solution of the utility model: it comprises pipe support pillar 1, retaining wall 2 and pipe support crossbeam 3, and an end of pipe support crossbeam 3 is connected with pipe support pillar 1, and the other end is connected on the retaining wall 2.
Retaining wall 2 is provided with embedded part 4.
The quantity of pipe support crossbeam 3 is one or more layers.
Compared with the prior art, the utility model is by the unified planning layout when designing with comprehensive pipe support and retaining wall, pipe support crossbeam one end of comprehensive pipe support is fixed on the pipe support pillar, the other end is fixed on the retaining wall, so just can save a side pipe post setting and a basis, save construction investment, on the other hand, because comprehensive pipe support just is provided with the pipe support pillar in a side of retaining wall, can save factory site like this.Retaining wall is provided with embedded part, like this can be conveniently fixing pipe support crossbeam, guarantee the Security of pipe support crossbeam; The quantity of pipe support crossbeam is one or more layers, can further save factory site like this.Therefore the utlity model has superiority such as floor space is little, investment is low, rationally distributed.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Embodiment
Embodiment: as shown in Figure 1, when arranging comprehensive pipe support, the pipe support pillar 1 of comprehensive pipe support is arranged in a side of retaining wall 2 according to the width of pipe support crossbeam 3, simultaneously according to the comprehensively concrete condition and the requirement of pipe support, specified altitude assignment at retaining wall 2 is provided with embedded part 4, after arranging the embedded part 4 on pipe support pillar 1 and the retaining wall 2, the two ends of pipe support crossbeam 3 are fixedly welded on respectively on the embedded part 4 on pipe support pillar 1 and the retaining wall 2; Pipe support crossbeam 3 can be one or more layers, specifically decides according to the actual quantity situation of factory's pipeline and cable 5.

Claims (3)

  1. The layout of [claim 1] a kind of comprehensive pipe support, it comprises pipe support pillar (1), retaining wall (2) and pipe support crossbeam (3), it is characterized in that: an end of pipe support crossbeam (3) is connected with pipe support pillar (1), and the other end is connected on the retaining wall (2).
  2. The layout of [claim 2] comprehensive pipe support according to claim 1 is characterized in that: retaining wall (2) is provided with embedded part (4).
  3. The layout of [claim 3] comprehensive pipe support according to claim 1 is characterized in that: the quantity of pipe support crossbeam (3) is one or more layers.
CNU2008203009099U 2008-05-29 2008-05-29 Synthesis tube holder arrangement structure Expired - Fee Related CN201209710Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008203009099U CN201209710Y (en) 2008-05-29 2008-05-29 Synthesis tube holder arrangement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008203009099U CN201209710Y (en) 2008-05-29 2008-05-29 Synthesis tube holder arrangement structure

Publications (1)

Publication Number Publication Date
CN201209710Y true CN201209710Y (en) 2009-03-18

Family

ID=40480446

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008203009099U Expired - Fee Related CN201209710Y (en) 2008-05-29 2008-05-29 Synthesis tube holder arrangement structure

Country Status (1)

Country Link
CN (1) CN201209710Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781231A (en) * 2016-04-15 2016-07-20 中国能源建设集团陕西省电力设计院有限公司 Combining structure for power plant pipeline support and enclosing wall and construction method of combining structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781231A (en) * 2016-04-15 2016-07-20 中国能源建设集团陕西省电力设计院有限公司 Combining structure for power plant pipeline support and enclosing wall and construction method of combining structure

Similar Documents

Publication Publication Date Title
CN105972313B (en) One kind is across base pit engineering conduit wiring suspension method and overhung construction
CN102444224A (en) Concrete composite shear wall
CN205806684U (en) A kind of across base pit engineering conduit wiring suspension structure
CN105756089A (en) Transverse laminated connection type single compartment precast multiple-compartment assembled comprehensive pipe gallery
CN102425099B (en) Large cantilever wave-purlin combined PC bridge and manufacture method thereof
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN202787330U (en) Post-cast strip template
CN201972417U (en) Lightweight wood structure roof system
CN201209710Y (en) Synthesis tube holder arrangement structure
CN203640061U (en) Node connecting structure of reinforced concrete column of basement
CN203347203U (en) Multi-functional super-thick bulked concrete steel tube support system
CN202611223U (en) Recyclable bolt type scaffold wall connection piece
CN204491883U (en) A kind of assembling energy consumption steel plate shear wall
CN103046743A (en) High-rise conversion layer type steel concrete girder hanging type template supporting system and construction method
CN202850041U (en) Reinforcing steel support for colligation of large-scale raft plate and ribbed beam base reinforcing steel
CN201972271U (en) Novel precast reinforced concrete shear wall
CN203273033U (en) Multifunctional piping support structure
CN202790959U (en) Steel pipe truss structure based on aloft lateral support
CN203393721U (en) Inner support main purlin component
CN206846097U (en) A kind of Men Gangyu frameworks separately-loaded pipeline support structure
CN205172031U (en) Can space -saving building sandwich structure
CN204960366U (en) Tunnel passes through device that underpins of existing large diameter pile building
CN203080919U (en) Formwork support steel channel beam connecting system for construction of cast-in-situ concrete large cross-sectional beams
CN202500221U (en) Connection system of combined floor board and side face of concrete wall
CN202416840U (en) Reinforcing mesh frame plate of external scaffold

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP03 Change of name, title or address

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

ASS Succession or assignment of patent right

Owner name: CHINA SIXTH METALLURGICAL CONSTRUCTION CO., LTD.

Free format text: FORMER OWNER: GUIYANG ALUMINIUM MAGNESIUM DESIGN + RESEARCH INSTITUTE

Effective date: 20121123

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 550081 GUIYANG, GUIZHOU PROVINCE TO: 450000 ZHENGZHOU, HENAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20121123

Address after: 450000 No. 36 West Huaihe Road, Henan, Zhengzhou

Patentee after: China Sixth Metallurgical Construction Co., Ltd.

Address before: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee before: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090318

Termination date: 20160529