CN201209251Y CNU2008201186915U CN200820118691U CN201209251Y CN 201209251 Y CN201209251 Y CN 201209251Y CN U2008201186915 U CNU2008201186915 U CN U2008201186915U CN 200820118691 U CN200820118691 U CN 200820118691U CN 201209251 Y CN201209251 Y CN 201209251Y
Authority
CN
China
Prior art keywords
rod
nut
embedded steel
anchor rod
anchor pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008201186915U
Other languages
English (en)
Inventor
杨建国
姚军战
邵进勇
王永政
张垣
卢川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Juli Sling Co Ltd
Original Assignee
Juli Sling Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Juli Sling Co Ltd filed Critical Juli Sling Co Ltd
Priority to CNU2008201186915U priority Critical patent/CN201209251Y/zh
Application granted granted Critical
Publication of CN201209251Y publication Critical patent/CN201209251Y/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型为高强度光圆锚杆,涉及土建工程用器具,随着建设规模的加大,高强度加固锚杆的需求越来越多,但都依赖于国外进口,本实用新型采用了在经热处理的锚杆杆体上套装波纹管,在其两端再套装预埋钢管,在头部依次装有预埋钢板、厚螺母、薄螺母,在尾部依次套装有柱脚、楔形垫板、锁紧顶板、厚螺母和薄螺母,本实用新型的力学性能显著提高,能满足高强度加固锚杆的要求,同时具有可进行两次灌浆,定位精确,操作方便,降低钢材的布置密度、降低工程的用钢量的有益效果。

Description

高强度光圆锚杆
技术领域
本实用新型涉及土建具领域,尤其是土建工程锚固用的拉杆器具。
背景技术
随着建设规模的加大,土建工程呈现大型化、复杂化,要求有配套的施工设备和器材来适应。本专利申请就是随着工程项目的要求越来越高,用于高速铁路、大型桥梁、地质状况复杂的隧道、核电站的地基、大型堤坝和护坡等工程需要大应力加固的锚杆。目前国内生产的光圆锚杆主要依照冶金行业标准“预应力混凝土用钢棒”(YB/T111)进行生产的,公称直径范围为Φ9.2—40mm。现在杆体结构为一端焊接预埋钢板,一端直接加工螺纹。采用此种结构考虑材料的焊接性能,强度级别只能应用于235级和345级。而且由于在杆体上直接加工螺纹,削弱了受力面积,降低了承载能力。施工过程中一次预埋到位,无法调节,定位精度不高。
目前高强度锚杆的需要量急剧上升,都依赖于从国外进口,因此开展高强度大规格锚杆的研制,并使之国产化已变得十分必要和刻不容缓。
发明内容
本实用新型的目的为在热处理的同时改变光圆锚杆的结构,使其成为高强度的光圆锚杆。
实现上述目的的技术方案如下:
高强度光圆锚杆,杆体为高强度光圆钢,在杆体中段套有波纹管,在波纹管两端在杆体上分别套有预埋钢管,在锚杆头部预埋钢管与拧在杆体上的薄螺母接触,杆体上再依次装有预埋钢板和厚螺母,在锚杆尾部预埋钢管与套在杆体上的柱脚接触,杆体上再依次装有楔形垫板、锁紧顶板、厚螺母和薄螺母。
杆体为经先锻造后热处理的光圆钢。
在锚杆头部预埋钢管与波纹管之间装有卡箍,在卡箍上开有灌浆口,灌浆口装有灌浆管,灌浆管与尾部灌浆口连通。
杆体直径为Φ20—100mm。
在制造过程中锚杆两端部,即头部和尾部进行局部加热,再镦锻加粗成型,保证螺纹加工成型后,螺纹底径不小于圆杆部分直径,达到等强。锻造后杆体再整体热处理,进一步提高屈服强度、抗拉强度、延伸率等综合力学性能。本实用新型分为“835”级和“1080”级两种强度级别,835级直径范围为Φ20—100mm,屈服强度≥835MPa;1080级直径范围为Φ20—80mm,屈服强度≥1080MPa。按照GB/T2975规定进行鉴定,从1/4直径处取Φ10mm标准试棒,测定屈服强度、抗拉强度和延伸率,各项性能均达到国外同类产品的技术要求。
本实用新型具有以下有益效果:
1、力学性能显著提高,达到了835级和1080级,直径范围为Φ20—100mm,超过了“预应力混凝土用钢棒”(YB/T111)最大直径Φ40mm范围,达到了国外同类产品的水平,可以作为进口产品的替代品。
2、现场施工时,在杆体和波纹管之间进行灌浆,经一次灌浆、二次灌浆和张拉后,很易达到设计要求的力值。
3、在锚杆尾部装有楔形垫板,能使锚杆精确定位,充分发挥锚杆的预应力加固作用。
4、因为锚杆的强度高可以降低锚杆的布置密度,降低工程的用钢量。
附图说明
图1为本实用新型高强度光圆锚杆结构示意图
图中各序号名称为:
1—厚螺母、2—薄螺母、3—锁紧顶板、4—楔形垫板、5—柱脚、6—杆体、7—波纹管、8—预埋钢管、9—预埋钢板、10—预埋钢管、11—薄螺母、12—厚螺母、13—卡箍、14—灌浆口
具体实施方式
图1显示了本实用新型的实施例。杆体为直径Φ100mm的光圆高强钢,杆体6外套有波纹管7,波纹管直径Φ140mm,在波纹管两端在杆体上分别套有预埋钢管8,在锚杆头部预埋钢管与拧在杆体上的薄螺母1接触,杆体上再依次装有预埋钢板9和厚螺母2,螺纹规格为M120×6,预埋钢管与波纹管之间装有卡箍13,在卡箍上开有灌浆口14,灌浆口装有灌浆管,灌浆管与尾部灌浆口连通。在锚杆尾部预埋钢管10与套在杆体上的柱脚5接触,杆体上再依次装有楔形垫板4,锁紧顶板3、厚螺母12和薄螺母11。螺纹规格为M120×6,装配完结后将锚杆整体放入工程的坑洞中,初步定位后经灌浆管、卡箍向锚杆头部进行一次灌浆,再精确定位后向波纹管内进行二次灌浆,使浆灌满杆体的周围,拧紧螺母拉张后即达到设计要求的力值。在杆体6制作过程中,端部局部加热,用模具镦锻成型,保证螺纹加工成型后螺纹底径不小于杆体圆杆直径,然后再整体热处理,提高综合力学性能,达到尺寸增大但其强度不会折减。端部螺纹采用成型刀块加工成型,用标准环规、塞规检验,保证互换性。

Claims (4)

1、高强度光圆锚杆,其特征为杆体为高强度光圆钢,在杆体中段套有波纹管,在波纹管两端在杆体上分别套有预埋钢管,在锚杆头部预埋钢管与拧在杆体上的薄螺母接触,杆体上再依次装有预埋钢板和厚螺母,在锚杆尾部预埋钢管与套在杆体上的柱脚接触,杆体上再依次装有楔形垫板、锁紧顶板、厚螺母和薄螺母。
2、根据权利要求1所述的高强度光圆锚杆,其特征为杆体为经先锻造后热处理的光圆钢。
3、根据权利要求1或2所述的高强度光圆锚杆,其特征为在锚杆头部预埋钢管与波纹管之间装有卡箍,在卡箍上开有灌浆口,灌浆口装有灌浆管,灌浆管与尾部灌浆口连通。
4、根据权利要求1或2所述的高强度光圆锚杆,其特征为杆体直径为Φ20—100mm。
CNU2008201186915U 2008-06-02 2008-06-02 高强度光圆锚杆 Expired - Lifetime CN201209251Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201186915U CN201209251Y (zh) 2008-06-02 2008-06-02 高强度光圆锚杆

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201186915U CN201209251Y (zh) 2008-06-02 2008-06-02 高强度光圆锚杆

Publications (1)

Publication Number Publication Date
CN201209251Y true CN201209251Y (zh) 2009-03-18

Family

ID=40479980

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201186915U Expired - Lifetime CN201209251Y (zh) 2008-06-02 2008-06-02 高强度光圆锚杆

Country Status (1)

Country Link
CN (1) CN201209251Y (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691819B (zh) * 2009-09-28 2011-01-19 郑州大学 生土窑居裂缝控制嵌梁加固系统及其施工工艺
CN105863696A (zh) * 2016-05-17 2016-08-17 太原理工大学 一种高强度大变形波纹锚杆装置
CN111305202A (zh) * 2020-03-18 2020-06-19 陕西省引汉济渭工程建设有限公司 一种基于锚杆用于锚索快速受力的应急装置及其使用方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691819B (zh) * 2009-09-28 2011-01-19 郑州大学 生土窑居裂缝控制嵌梁加固系统及其施工工艺
CN105863696A (zh) * 2016-05-17 2016-08-17 太原理工大学 一种高强度大变形波纹锚杆装置
CN111305202A (zh) * 2020-03-18 2020-06-19 陕西省引汉济渭工程建设有限公司 一种基于锚杆用于锚索快速受力的应急装置及其使用方法

Similar Documents

Publication Publication Date Title
CN102383420B (zh) 一种掺纤维增强塑料筋的高强混凝土预制桩
CN102817422B (zh) 一种预应力混凝土约束的防屈曲支撑
CN103867019B (zh) 装配式体外预应力活性粉末混凝土风电塔架
CN101570969B (zh) 水平力承载桩及其生产工艺
CN201762717U (zh) 预应力管桩与承台的连接结构
CN203755778U (zh) 装配式体外预应力活性粉末混凝土风电塔架
CN104328744B (zh) 一种地锚式悬索桥锚碇钢拉杆锚固系统施工方法
CN101538939A (zh) 预置螺母式型钢混凝土组合柱模板固定装置及施工方法
CN201209251Y (zh) 高强度光圆锚杆
CN201713959U (zh) 新型可拉压钢筋混凝土支撑
CN202208916U (zh) 一种高强混凝土预制桩
CN201794217U (zh) 一种先张法预应力钢筋砼预制梁
CN102304919B (zh) 设置于锚杆锚固段或/和自由段杆体上的器件及锚杆
CN103306495B (zh) 木结构截柱加固施工方法
CN201209252Y (zh) 高强度带肋螺纹钢锚杆
CN104563103A (zh) 一种复合配筋部分预应力混凝土实心方桩及其制作方法
CN102528924A (zh) 一种高强度环形部分预应力混凝土电杆及其生产方法
CN202338347U (zh) 一种新型锚索
CN201512788U (zh) 水平承载增强型预应力混凝土管桩
CN202787241U (zh) 混凝土管桩
CN202644531U (zh) 锚杆静压桩预加压力封桩装置
CN104652430A (zh) 复合配筋部分预应力混凝土实心方桩及其制作方法
CN201474703U (zh) 一种水工隧洞固结圈承力结构
CN111254956A (zh) 一种危岩体预应力栓锚加固结构及实现该加固结构的方法
Chen et al. Experimental study on flexural behavior of splicing concrete-filled GFRP tubular composite members connected with steel bars

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20090318