CN201187060Y - Vertical location apparatus of deep water steel hanging box - Google Patents

Vertical location apparatus of deep water steel hanging box Download PDF

Info

Publication number
CN201187060Y
CN201187060Y CNU2008200289312U CN200820028931U CN201187060Y CN 201187060 Y CN201187060 Y CN 201187060Y CN U2008200289312 U CNU2008200289312 U CN U2008200289312U CN 200820028931 U CN200820028931 U CN 200820028931U CN 201187060 Y CN201187060 Y CN 201187060Y
Authority
CN
China
Prior art keywords
steel
pile
hanging box
box
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008200289312U
Other languages
Chinese (zh)
Inventor
欧阳效勇
任回兴
贺茂生
聂青龙
孙克强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Highway Engineering Co Ltd
Original Assignee
CCCC Second Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Highway Engineering Co Ltd filed Critical CCCC Second Highway Engineering Co Ltd
Priority to CNU2008200289312U priority Critical patent/CN201187060Y/en
Application granted granted Critical
Publication of CN201187060Y publication Critical patent/CN201187060Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model relates to a vertical positioning device for a deep water steel hanging box applied in the construction of a tidal river. The vertical positioning device is characterized in that a steel hanging box (1) adopt an integrated jacket-type structure; an interlayer cavity is formed by the double-layered wall plate of the peripheral structure thereof; a well-shaped cross-span beam is arranged in the steel hanging box (1), so that a pile foundation steel protective sleeve (6) passes through the well-shaped cross-span beam; pile top reaction beams (3) are welded at the top ends of the pile foundation steel protective sleeve (6) and a temporary steel pipe pile (2); the top part of the wall plate of the steel hanging box (1) is connected with a back pressure steel beam (5); and the pile top reaction beams (3) are connected with the back pressure steel beam (5) through a positioning upright column (4); and welding stiffener plates (11) are arranged in the welded connection positions of the pile top reaction beams (3), as well as the temporary steel pipe pile (2) and pile foundation steel protective sleeve (6). The vertical positioning device has the advantages of short construction time, and high vertical positioning accuracy.

Description

The vertical positioner of deep water steel box
Technical field
The utility model belongs to large bridge construction equipment technical field, especially a kind of vertical positioner of deep water steel box that is applied in the construction of morning and evening tides section.
Background technology
Along with the continuous development of Bridges in Our Country construction technology, deep water multi-column pier foundation, highrise pile cap obtain very using widely as the main base form of striding the river Oversea bridge.Such bearing platform construction mainly adopts the steel box to enclose the water constructing structure as it.In the morning and evening tides section, because tidal range can reach 2~3m, construction environment brings very big adverse effect for the vertical location construction of steel box.Therefore the location construction of bridge steel box on this class section generally is selected in the time of low water section and carries out.Vertical locate mode in the past often adopts between steel box wallboard and steel casing the welding location structure to position, but because large-scale steel box relative positioning point is more, workload is bigger, if in a time of low water section, finish the welding job of all location structures, just must drop into a large amount of man power and materials, concentrate and carry out simultaneously, not only waste resource, and the also difficult assurance of positioning accuracy, there is bigger construction risk.
Summary of the invention
In order to overcome the long and not high deficiency of positioning accuracy of existing vertical location working procedure duration, the purpose of this utility model provides short, the vertical high vertical positioner of deep water steel box of positioning accuracy of a kind of construction operation time.
The technical solution adopted in the utility model is: design the vertical positioner of a kind of deep water steel box, it is characterized in that: steel box 1 is whole chamber type structure, the double-deck wallboard of its peripheral structure forms the interlayer cavity, well word shape is arranged across beam 10 in the steel box 1, and pile foundation steel casing 6 is passed; Be welded with a top reaction beam 3 on the top of pile foundation steel casing 6 and temporary steel pile tube 2, be connected with back-pressure girder steel 5 in the top of panels of steel box 1, stake top reaction beam 3 is connected by locating column 4 with back-pressure girder steel 5; Stake top reaction beam 3 is provided with welding stiffener 11 with the place of being welded to connect of temporary steel pile tube 2 and pile foundation steel casing 6.
When adopting this device vertically to locate construction, at first select vertical anchor point, at the pile foundation steel casing 6 of anchor point correspondence and welded and installed stake top, the top reaction beam 3 of temporary steel pile tube 2, and utilize stiffener 11 to guarantee firm welding, make it be enough to resist vertical location counter-force; Next installs back-pressure beam 5, makes itself and box wallboard firm welding; According to the length of design elevation compute location column 4, and be transported to the job site in back court processing; When steel box 1 is transferred to floating certainly state, in box wallboard interlayer body cavity, add water rapidly in the low tide period, make steel box 1 sink down into design elevation, and rapid horizontal lock, while installing and locating column 4, make itself and stake top reaction beam 3 and back-pressure beam 5 firm welding, the vertical location of finishing the steel box.
The main feature of the vertical positioner of box of the present invention is that positioner is decomposed processing in advance, the accessory structure of mounting and positioning device in advance, in the time of low water section, only need to install main positioner, reduce workload with this, shorten the operation duration, the vertical positioning operation of box can be finished smoothly fast in the low tide stage; In addition, by calculating the vertical extension of determining the location column, by rigid support and the connection of welding the hierarchy of control, vertical positioning accuracy is enhanced.
Description of drawings
Below in conjunction with the embodiment accompanying drawing the utility model is described further.
Fig. 1 is the facade structures schematic diagram of the utility model device.
Fig. 2 is the vertical view of Fig. 1.
Among the figure: 1, steel box; 2, temporary steel pile tube; 3, stake top reaction beam; 4, location column; 5, back-pressure girder steel; 6, pile foundation steel casing; 7, construction water surface curve; 8, water surface curve in the steel box wallboard; 9, above-ground route; 10, well word shape is across beam; 11, welding stiffener.
The specific embodiment
As depicted in figs. 1 and 2, a top reaction beam 3 is arranged, back-pressure girder steel 5 is installed, between stake top reaction beam 3 and the back-pressure girder steel 5 column 4 of location is arranged in the top of panels of steel box 1 in the top welded and installed of pile foundation steel casing 6 and temporary steel pile tube 2.
Steel box 1 is whole chamber type structure, and the double-deck wallboard of its peripheral structure forms the interlayer body cavity, well word shape is arranged across beam 10 in the steel box 1, and pile foundation steel casing 6 is passed; Stake top reaction beam 3 is provided with welding stiffener 11 with the place of being welded to connect of temporary steel pile tube 2 and pile foundation steel casing 6; The vertical extension of location column 4 is calculated according to design elevation, and processes at back court in advance.
When adopting this device vertically to locate construction, adopt following construction sequence:
Box 1 transfer put in place before, select the vertical anchor point of box 1.And with temporary steel pile tube 2 top solder a stake top reaction beam 3 is installed on pile foundation steel casing 6 top of anchor point correspondence.Must utilize the stiffener firm welding between stake top reaction beam 3 and pile foundation steel casing 6 and the temporary steel pile tube 2, make it be enough to resist vertical location counter-force.
2. back-pressure beam 5 is installed at the vertical anchor point place of steel box 1 wallboard, back-pressure beam 5 must with box wallboard firm welding.
3. be transported to the job site according to the length of design elevation compute location column 4, and in back court processing.
Box 1 transfer to the construction water surface curve 7 below behind floating state, in steel box wallboard, add water to water surface curve 8 in the steel box wallboard in the low tide time, make box 1 sink down into above-ground route 9, design elevation, and rapid horizontal lock steel box 1.
5. utilize low slack period,, make itself and stake top reaction beam 3 and back-pressure beam 5 firm welding, the vertical location of finishing the steel box at each vertical anchor point while installing and locating column 4.

Claims (1)

1, the vertical positioner of deep water steel box is characterized in that: steel box (1) is whole chamber type structure, and the double-deck wallboard of its peripheral structure forms the interlayer cavity, well word shape is arranged across beam (10) in the steel box (1), and pile foundation steel casing (6) is passed; Be welded with a top reaction beam (3) on the top of pile foundation steel casing (6) and temporary steel pile tube (2), be connected with back-pressure girder steel (5) in the top of panels of steel box (1), stake top reaction beam (3) is connected by locating column (4) with back-pressure girder steel (5); Stake top reaction beam (3) is provided with welding stiffener (11) with the place of being welded to connect of temporary steel pile tube (2) and pile foundation steel casing (6).
CNU2008200289312U 2008-04-24 2008-04-24 Vertical location apparatus of deep water steel hanging box Expired - Lifetime CN201187060Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200289312U CN201187060Y (en) 2008-04-24 2008-04-24 Vertical location apparatus of deep water steel hanging box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200289312U CN201187060Y (en) 2008-04-24 2008-04-24 Vertical location apparatus of deep water steel hanging box

Publications (1)

Publication Number Publication Date
CN201187060Y true CN201187060Y (en) 2009-01-28

Family

ID=40310078

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200289312U Expired - Lifetime CN201187060Y (en) 2008-04-24 2008-04-24 Vertical location apparatus of deep water steel hanging box

Country Status (1)

Country Link
CN (1) CN201187060Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140801A (en) * 2010-02-02 2011-08-03 中交二公局第五工程有限公司 Cofferdam construction method in construction of deepwater pier bearing platform
CN110409477A (en) * 2019-07-12 2019-11-05 中铁大桥勘测设计院集团有限公司 A kind of steel lifted trunk anti-surge interior support system and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140801A (en) * 2010-02-02 2011-08-03 中交二公局第五工程有限公司 Cofferdam construction method in construction of deepwater pier bearing platform
CN110409477A (en) * 2019-07-12 2019-11-05 中铁大桥勘测设计院集团有限公司 A kind of steel lifted trunk anti-surge interior support system and its construction method
CN110409477B (en) * 2019-07-12 2021-05-04 中铁大桥勘测设计院集团有限公司 Steel suspension box anti-surge internal support system and construction method thereof

Similar Documents

Publication Publication Date Title
CN103132537A (en) Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method
US20140215953A1 (en) Solar panel mounting stand installation method, pile and solar panel mounting stand
CN111119213A (en) Double-wall steel cofferdam with open edge feet and construction method thereof
CN104711931B (en) Temporary underwater pier manufacturing, assembling and disassembling method suitable for bridge erection
CN106088120B (en) A kind of cofferdam decentralization construction method
CN217580865U (en) Large-diameter steel casing drilling platform under deep water slope bare rock geological condition
CN114809062A (en) Integral bottom plate-integral vertical ring combined concrete bearing platform foundation and construction process thereof
CN201187060Y (en) Vertical location apparatus of deep water steel hanging box
CN103669359A (en) Pre-buried grout pipe truss device of impervious wall
CN202266034U (en) Fixing device for anchor bolts of embedded type diamond combined steel and concrete column feet
CN201272969Y (en) Guiding facility for putting down steel protection barrel in deep water torrent
CN202265906U (en) Fixing device for anchor bolts of embedded type steel tube concrete column feet
CN203834809U (en) Steel pipe column structure for steel pipe column concrete side pouring method
CN114277818B (en) Rectangular steel sheet pile cofferdam structure of deepwater bearing platform and construction method thereof
CN204385743U (en) A kind of pile foundation in deep water steel pile casting construction system
CN205742125U (en) A kind of work platform for boring
CN201326380Y (en) Drill cushion block suitable for component with circular surface
CN201187051Y (en) Deep water bridge foundation construction multifunctional drill platform top board
JP2014051780A (en) Connection structure between steel pipe and foundation of building structure
CN205100224U (en) Integrated configuration of pre -buried steel sheet and steel reinforcement cage
CN202627538U (en) Floor concrete control elevation line horizontal measurement auxiliary frame body
CN102926555B (en) Prefabricated detachable foundation pit ladder rest platform and diaphragm wall connection structure
CN206337605U (en) Prefabricated two-layer equation Homofloor drainage system
CN218233537U (en) Single double-wall steel cofferdam for bridge construction
CN217204082U (en) Civil engineering pile foundation construction structures

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20090128