CN201172821Y - Seamless joint impervious wall steel form - Google Patents

Seamless joint impervious wall steel form Download PDF

Info

Publication number
CN201172821Y
CN201172821Y CNU2007201871289U CN200720187128U CN201172821Y CN 201172821 Y CN201172821 Y CN 201172821Y CN U2007201871289 U CNU2007201871289 U CN U2007201871289U CN 200720187128 U CN200720187128 U CN 200720187128U CN 201172821 Y CN201172821 Y CN 201172821Y
Authority
CN
China
Prior art keywords
steel form
wall
impervious wall
mould
sheet steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007201871289U
Other languages
Chinese (zh)
Inventor
卢锡雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Fuli Construction Installation Engineering Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2007201871289U priority Critical patent/CN201172821Y/en
Application granted granted Critical
Publication of CN201172821Y publication Critical patent/CN201172821Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model relates to a seamless connection cutoff wall sheet steel form, which relates to a tool which is used for constructing by a cutoff wall, in particular to a sheet steel form which needs to be used when a sinking mould method is adopted to build the cutoff wall. The sheet steel form adopts a steel square outer frame 1 with a cavity structure 7 to be submerged in a designed impervious depth under the condition that a flap pile tip 2 is closed, materials such as concrete and the like which are pre-allocated are evenly injected through a material filling opening 6 on a mould body, the mould is pulled out through a vibration mode and the like, slurries are injected through a lubricating pipe 3 in the process of sinking and pulling out, the flap pile tip is automatically opened when the mould is pulled out, materials which are injected in the cavity are left in a ground layer, which form a consolidated pile body after hardening. Moulds are sleeved through 4, 5, one pile body is connected with another pile body without seam, and finally a wall body is formed, and the wall body plays the anti-seepage function. The sheet steel form excellently solves the quality problem of bad continuity of the wall body of an anti-seepage wall in long term, which has novel and special design and simple structure, and simultaneously solves the shortcomings of repeat procedures of the construction of the anti-seepage wall, bad progress and the like, and saves a great amount of production cost.

Description

Seamless link impervious wall steel form
Technical field
The utility model relates to the instrument that a kind of impervious wall uses, and is specially the steel form that need use when adopting heavy mould mode to construct impervious wall.
Background technology
Impervious wall is the requisite measure of a foundation construction on the engineering, uses very extensive.The water conservancy dykes and dams, reservoir seepage-proofing, the building foundation pit excavation, dock construction etc. all needs to utilize impervious wall to guarantee the success of excavation of foundation pit.The continuity of impervious wall then is the basic demand of antiseepage.The construction technology of impervious wall has: the heavy form walls of vibration, splitting curtain grouting, high pressure jet grouting, geomembrane anti-seepage, concrete cut or the like, various technologies have different compliance and limitation.In all these technologies, maximum problem is how to guarantee the continuity of leakage proof wall.The continuity that comprises length direction and depth direction.
Before the utility model is made, the thinking of this problem that solves is that the perpendicularity deviation when requiring the pile body construction is controlled in the very little scope, to guarantee the continuous of depth direction, length direction then adopts tenon formula joint, rigid joint, junction block method, overlaps drill hole, volume method of substitution etc., with the continuity of assurance impervious wall, these modes, cost is higher, complex process, work efficiency is lower, and relatively stricter to the requirement of geological conditions, actual effect is good inadequately.
Summary of the invention
The purpose of this utility model is at above-mentioned present situation, and the defective of the continuous assurance difference of existence aims to provide a kind of working steel form of impervious wall continuity that guarantees reliably.
Technical solutions of the utility model: two this programme design steel forms (1) that adopt same size, the bottom flap valve of closed steel form, become pointed, be positioned over design attitude,, be pressed in the soil with vibration or static pressure power, simultaneously, open lubrication management (3), inwardly inject clear water or mud, work the frictional force and the foundry loam phenomenon that reduce in pile sinking and the pile pulling process.After the degree of depth reaches, stop to sink.The connection back (4) of another one steel form is aimed at the connection sunny side (5) of one of front, after putting, sink.So continuously carry out, form the impervious wall of continuous seamless.
Advantage and effect: use the utility model, can build seamless impervious wall.Characteristics are simple in structure; Cost is low; The work efficiency height.Do not produce pollutions such as mud.
Description of drawings
Fig. 1 is that the utility model structural representation Fig. 2 is the utility model section of structure
The specific embodiment
With reference to Fig. 1,2, the utility model adopts the steel plate welding, forms rectangle steel sheet frame (1), in the one side, the connection back (4) is set, and opposite side is provided with and connects sunny side (5), and upper side has charging aperture (6), establishes lubricated water pipe (3) at sunny side.(1) bottom is provided with flapper pile tip (2).During construction, (1) is connected power source, opens (3), closed (2), sink to the degree of depth after, stop.Second steel form is in place, opens lubricated water pipe, and closed flap valve (2) adopts the mode of back snapping sunny side to be connected the sinking steel form with first steel form.When extracting first steel form, put into the material of capacity, after the curing, just formed the impervious wall of seamless link.

Claims (5)

1, seamless link impervious wall steel form, it is characterized in that rectangle steel sheet frame (1) has cavity (7), rectangle frame minor face one side is the back (4) of linkage, opposite side is the sunny side (5) of linkage, the template bottom is flapper pile tip structure (2), top, side sprue (6), and the lubricated slurry pipe (3) that the linkage sunny side comprises is formed.
2, seamless link impervious wall steel form according to claim 1 is characterized in that rectangle steel sheet frame (1) cloudy (4) sun (5) linkage, distribution minor face both sides.
3,, it is characterized in that negative and positive linkage (4), (5) are " T type groove " type and " ∏ " type according to claim 1,2 described seamless link impervious wall steel forms.
4, seamless link impervious wall steel form according to claim 1 is characterized in that having lubricated slurry pipe in the linkage sunny side (5).
5, seamless link impervious wall steel form according to claim 1 is characterized in that rectangular steel plates frame bottom (2) is a flapper pile tip.
CNU2007201871289U 2007-12-14 2007-12-14 Seamless joint impervious wall steel form Expired - Lifetime CN201172821Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201871289U CN201172821Y (en) 2007-12-14 2007-12-14 Seamless joint impervious wall steel form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201871289U CN201172821Y (en) 2007-12-14 2007-12-14 Seamless joint impervious wall steel form

Publications (1)

Publication Number Publication Date
CN201172821Y true CN201172821Y (en) 2008-12-31

Family

ID=40199934

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201871289U Expired - Lifetime CN201172821Y (en) 2007-12-14 2007-12-14 Seamless joint impervious wall steel form

Country Status (1)

Country Link
CN (1) CN201172821Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094415A (en) * 2010-11-22 2011-06-15 张永忠 Semicircular pile plate
CN102174811A (en) * 2010-12-14 2011-09-07 张永忠 Wedge-shaped pile plate
CN103088817A (en) * 2013-02-14 2013-05-08 张璐 Seamless underground wall forming machine
CN107268601A (en) * 2017-06-16 2017-10-20 白希雁 A kind of construction method of underground continuous concrete board wall

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094415A (en) * 2010-11-22 2011-06-15 张永忠 Semicircular pile plate
CN102174811A (en) * 2010-12-14 2011-09-07 张永忠 Wedge-shaped pile plate
CN103088817A (en) * 2013-02-14 2013-05-08 张璐 Seamless underground wall forming machine
CN107268601A (en) * 2017-06-16 2017-10-20 白希雁 A kind of construction method of underground continuous concrete board wall

Similar Documents

Publication Publication Date Title
US20210348355A1 (en) Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN102900089B (en) With the combination piling bar cofferdam of hydro-expansive rubber waterproof fore shaft
CN203034467U (en) Combined steel pile cofferdam with water-proof fore shafts
CN101718099B (en) Automatic wall-forming device and method of static pressure continuous concrete wall
CN201172821Y (en) Seamless joint impervious wall steel form
CN203924085U (en) A kind of caisson structure that is applied to collecting well
CN109056650A (en) A kind of assembled sheet pile combination shore protection and its construction method
CN201172820Y (en) Tied joggle pile mould tube with lubricating valve pile toe
CN107268599B (en) Substrate buried type large-scale filling karst cave reinforcing structure and reinforcing method
CN103061348B (en) Sand-bag and steel sheet pile combined cofferdam for hard formation and construction method of cofferdam
CN112299796B (en) Wall pile inter-pile grouting material for building envelope and construction method thereof
CN201915414U (en) Spliced steel box coefferdam
CN203334295U (en) Large-diameter arc-shaped steel sheet pile foundation pit supporting structure
CN202359565U (en) Steel sheet pile cofferdam structure
CN204875755U (en) Drainage body and solidification stratum society foundation structure
CN204080750U (en) Box-type suction foundation sluice structure
CN203066089U (en) Cofferdam combined by mold bag sand and steel sheet piles and used for hard strata
CN212801549U (en) H-shaped double-row steel sheet pile supporting structure
CN212153449U (en) Bottom backfill structure of common-wall tunnel group
CN201526047U (en) Static pressure automatic constructing device for underground continuous wall
CN201873990U (en) Dry soil-withdrawing engaged rectangle cast-in-place pile piling device
CN202124857U (en) Splitting pile
CN207775807U (en) Concrete cut-off wall guide way structure
CN101225655A (en) Lateral vertically sealing method for vacuum pre-pressed soft soil foundation
CN202323934U (en) Hole forming device for cast-in-situ triangular composite foundation pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUANGZHOU FULI CONSTRUCTION INSTALLATION ENGINEERI

Free format text: FORMER OWNER: LU XILEI

Effective date: 20120529

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430071 WUHAN, HUBEI PROVINCE TO: 510308 GUANGZHOU, GUANGDONG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120529

Address after: 510308, Guangzhou, Guangdong, Haizhuqu District Province Road, No. 688, Poly International Plaza, 11 floor

Patentee after: GUANGZHOU FULI CONSTRUCTION & INSTALLATION ENGINEERING CO., LTD.

Address before: 430071, room 1, unit 1, Wu Kong hospital dormitory, 553 Democratic Road, Wuchang District, Hubei, Wuhan, 501

Patentee before: Lu Xilei

CX01 Expiry of patent term

Granted publication date: 20081231

CX01 Expiry of patent term