CN201158938Y - Adjustable corbel out system - Google Patents
Adjustable corbel out system Download PDFInfo
- Publication number
- CN201158938Y CN201158938Y CNU2008200763031U CN200820076303U CN201158938Y CN 201158938 Y CN201158938 Y CN 201158938Y CN U2008200763031 U CNU2008200763031 U CN U2008200763031U CN 200820076303 U CN200820076303 U CN 200820076303U CN 201158938 Y CN201158938 Y CN 201158938Y
- Authority
- CN
- China
- Prior art keywords
- template
- steel plate
- adjustable
- fixed
- corbelling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model belongs to the architectural working used device technical field, in particular to an adjustable corbelling system which is used in die changing operations in a hydraulic sliding template system in architectural working and solves the problems in the prior art that a hydraulic sliding template die changing operation method is not economical and safe, and delays the working time. The adjustable corbelling system comprises two corbels which are connected with the template and is characterized in that slideways which are provided for the corbels to slide are arranged on the upper portion and the lower portion of the corbells, the slideways are fixed on a lifting frame, the outer ends of the two corbels are connected through a rectangular steel plate, a screw thread hole is arranged on the center of the rectangular steel plate and is threaded through by a screw bolt, and the head of the screw bolt is fixed on the lifting frame. The utility model has following beneficial effects that when the template is changed, the position of the template can be changed without building another falsework and only through using a hanging falsework in an original template system to adjust a corbelling screw bolt, the template movement can be finished with half a day, which saves labor budget for construction projects by 80%, the working time and the equipment and material cost, and the economic effects are prominent.
Description
Technical field
The utility model belongs to the building operations apparatus technology, is specifically related to a kind of being applicable to and changes the adjustable corbel system that the mould operation is used in the building operations in the hydraulic climbing template system.
Background technology
Existing hydraulic climbing template system, as shown in Figure 1, when the size of vertical structure changes, need stripping, install again, and many operations all belong to work high above the ground, needing to set up scaffold to template change position from the bottom operates, promptly uneconomical, dangerous again, but also delay the duration.When template position is regulated, even if operation on the platform of setting up in addition also approximately needs 4-5 days time.As shown in Figure 3, corbel system directly is fixed on the hoisting frame by bolt, and template, to take the lead, promote all to be relatively-stationary.
Summary of the invention
To change the mould operational method uneconomical, dangerous in order to solve in the prior art hydraulic climbing template for the utility model, and delay the problem of duration, and a kind of adjustable corbel system is provided.
The utility model adopts following technical scheme to realize: a kind of adjustable corbel system, comprise that two of being connected with template take the lead, the upper and lower slideway that slides for taking the lead that is provided with is characterized in that taking the lead, slideway is fixed on the hoisting frame, two outer ends of taking the lead connect by rectangular steel plates, the rectangular steel plates center is established screwed hole and is installed with screw rod, and screw head is fixed on the hoisting frame.
The fixed structure of screw rod is made of the steel plate one that is used for positioning screw, steel plate two, steel plate three, steel plate one and hoisting frame welding, steel plate three comprises upper plate, lower plate, and lower plate is welded to connect with steel plate one and steel plate two bottoms respectively, and upper plate is plugged between steel plate one top and steel plate two tops.
Now the corbel system in original hydraulic climbing template system is transformed, become the screw adjustable corbel system, translation in the slideway that is fixed in the hoisting frame corresponding site with the advance and retreat of control template, reaches the purpose that changes the vertical structure template size.
The relative prior art of the utility model has following beneficial effect: after adopting corbel system described in the utility model, when changing, template need not set up scaffold more in addition, only need utilize and hang the take the lead adjusting of screw rod of scaffold in the original template system, can change template position, change template and only need use time half a day, save labour cost 80%, saved the duration for work items, and saved equipment, cost of materials, economic benefit is obvious.
Description of drawings
Fig. 1 is a sliding form apparatus schematic diagram in the prior art
Fig. 2 gets the sliding form apparatus schematic diagram for using corbel system described in the utility model
Fig. 3 is the A-A sectional drawing of Fig. 1
Fig. 4 is the B-B sectional drawing of Fig. 2
Fig. 5 is the C-C sectional drawing of Fig. 4
Fig. 6 is the schematic diagram of steel plate 1
Fig. 7 is the schematic diagram of steel plate 2
Fig. 8 is the schematic diagram of steel plate 3
Among the figure: 1-bearing bar, 2-stop, 3-jack, 4-oil pipe, the 5-hoisting frame, the 6-reinforcing bar, the 7-operating platform, 8-takes the lead, the 9--enclosure, 10-template, 11-bolt, 12-slideway, the 13-screw rod, 14-rectangular steel plates, 15-steel plate one, 16-steel plate two, 17-steel plate three, 18-upper plate, the 19-lower plate, 20-changes vertical structure position, back, the former vertical structure of 21-position
The specific embodiment
In conjunction with the accompanying drawings the specific embodiment of the present utility model is described further, embodiment is used for illustrating of the present utility model, rather than it is imposed any restrictions.
Shown in Fig. 2,4,5, adjustable corbel system, comprise that two of being connected with template 10 take the lead 8, the 8 upper and lower slideways 12 that slide for taking the lead that are provided with is characterized in that taking the lead, slideway 12 is fixed on the hoisting frame 5, two take the lead 8 outer ends by rectangular steel plates 14 connections, and rectangular steel plates 14 centers are established screwed hole and are installed with screw rod 13, and screw rod 13 heads are fixed on the hoisting frame 5.
Shown in Fig. 5,6,7, the fixed structure of screw rod 13 is made of the steel plate 1 that is used for positioning screw 13, steel plate 2 16, steel plate 3 17, steel plate 1 and hoisting frame 5 welding, steel plate 3 17 comprises upper plate 18, lower plate 19, lower plate 19 is welded to connect with steel plate 1 and steel plate 2 16 bottoms respectively, and upper plate 18 is plugged between steel plate one 15 tops and steel plate 2 16 tops.
As shown shown in 2: screw rod 13 translation in the slideway 12 that is fixed in hoisting frame 5 corresponding sites with the advance and retreat of control template 10, reaches the purpose that changes the vertical structure template size.After adopting system described in the utility model, need not set up scaffold more in addition when template 10 is changed, only need utilize and hang the take the lead adjusting of screw rod of scaffold in the original template system, can change template position.
Claims (2)
1, a kind of adjustable corbel system, comprise two take the lead (8) being connected with template (10), (8) upper and lower slideway (12) that slides for taking the lead that is provided with is characterized in that taking the lead, slideway (12) is fixed on the hoisting frame (5), two take the lead (8) outer end by rectangular steel plates (14) connection, rectangular steel plates (14) center is established screwed hole and is installed with screw rod (13), and screw rod (13) head is fixed on the hoisting frame (5).
2, adjustable corbel system according to claim 1, the fixed structure that it is characterized in that screw rod (13) is made of the steel plate one (15) that is used for positioning screw (13), steel plate two (16), steel plate three (17), steel plate one (15) and hoisting frame (5) welding, steel plate three (17) comprises upper plate (18), lower plate (19), lower plate (19) is welded to connect with steel plate one (15) and steel plate two (16) bottoms respectively, and upper plate (18) is plugged between steel plate one (15) top and steel plate two (16) tops.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008200763031U CN201158938Y (en) | 2008-02-01 | 2008-02-01 | Adjustable corbel out system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008200763031U CN201158938Y (en) | 2008-02-01 | 2008-02-01 | Adjustable corbel out system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201158938Y true CN201158938Y (en) | 2008-12-03 |
Family
ID=40109528
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2008200763031U Expired - Lifetime CN201158938Y (en) | 2008-02-01 | 2008-02-01 | Adjustable corbel out system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201158938Y (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100549347C (en) * | 2008-02-01 | 2009-10-14 | 山西第六建筑有限公司 | Adjustable corbel system |
-
2008
- 2008-02-01 CN CNU2008200763031U patent/CN201158938Y/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100549347C (en) * | 2008-02-01 | 2009-10-14 | 山西第六建筑有限公司 | Adjustable corbel system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201865054U (en) | Hydraulic climbing formwork device for high bridge pier | |
CN110056374B (en) | Construction device and construction method for variable-section tunnel | |
CN204934670U (en) | A kind of electric drill auxiliary stand | |
CN202850484U (en) | Safety mechanism for building construction climbing template | |
CN205804939U (en) | template assembly for subway station side wall | |
CN100549347C (en) | Adjustable corbel system | |
CN209817430U (en) | Template supporting structure of tower crane reserved hole | |
CN202081640U (en) | Lifting formwork used for building of elevator shaft | |
CN202850497U (en) | Hydraulic telescopic device used for elevator shaft mold | |
CN202081427U (en) | Embedded bolt positioning device for tower crane foundation | |
CN201158938Y (en) | Adjustable corbel out system | |
CN109339722A (en) | A kind of guiding pipe clamp device | |
CN210066503U (en) | Thin-wall hollow pier die of sliding frame lifting die | |
CN204824004U (en) | Hydraulic pressure heavy load is from lift platform | |
CN203684664U (en) | Cast-in-place beam die for doors and windows | |
CN207583391U (en) | One kind two serves as a contrast plug steel end mould | |
CN202202260U (en) | Constructing device for bridge body | |
CN201539097U (en) | Full hydraulic climbing template | |
CN201195940Y (en) | Integral lifting template for elevator shaft | |
CN205223861U (en) | Capable system is walked to cast -in -place simple box girder centre form of high -efficient support | |
CN201447862U (en) | Instrumental operating platform used for elevator shaft shear wall shuttering erection | |
CN204074826U (en) | A kind of engineering steel form distortion adjusting device | |
CN202559747U (en) | Foot portion supporting and size control device of aluminum alloy shear wall template | |
CN207013761U (en) | A kind of energy-saving power cabinet wire inlet/outlet hole punches positioner | |
CN202023361U (en) | Hydraulic die plate for climbing in building construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Effective date of abandoning: 20080201 |
|
C25 | Abandonment of patent right or utility model to avoid double patenting |