CN201158668Y - 高炉喷吹煤粉多级分段式加热输送管 - Google Patents

高炉喷吹煤粉多级分段式加热输送管 Download PDF

Info

Publication number
CN201158668Y
CN201158668Y CNU2008200764814U CN200820076481U CN201158668Y CN 201158668 Y CN201158668 Y CN 201158668Y CN U2008200764814 U CNU2008200764814 U CN U2008200764814U CN 200820076481 U CN200820076481 U CN 200820076481U CN 201158668 Y CN201158668 Y CN 201158668Y
Authority
CN
China
Prior art keywords
heating
blast furnace
coal
pipe
transfer lime
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008200764814U
Other languages
English (en)
Inventor
刘仁生
王宏强
刘新斌
房连增
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhi City Fang Sheng Injection Technology Co Ltd
Shanxi Luan Mining Group Co Ltd
Original Assignee
Changzhi City Fang Sheng Injection Technology Co Ltd
Shanxi Luan Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhi City Fang Sheng Injection Technology Co Ltd, Shanxi Luan Mining Group Co Ltd filed Critical Changzhi City Fang Sheng Injection Technology Co Ltd
Priority to CNU2008200764814U priority Critical patent/CN201158668Y/zh
Application granted granted Critical
Publication of CN201158668Y publication Critical patent/CN201158668Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

本实用新型涉及一种冶金行业的高炉喷吹煤粉输送装置,具体为一种高炉喷吹煤粉多级分段式加热输送管。解决了现有技术中存在的冷态的煤粉直接喷吹而影响燃烧率的问题。由至少一个加热单元组成,每个加热单元由内层的输送管和外层的加热管套接构成,输送管和加热管的两端之间为封闭状,加热管上分别开有介质进口和介质出口,在加热单元两端设有连接法兰,中部装配有膨胀节,以补偿受热后的变形量。本实用新型采用多级分段式加热方式即通过四个串联的加热单元逐级将煤粉加热至120~160℃。降低焦炭消耗和生铁成本,经济效益显著。同时加热后煤粉流动性增强,更有利于输送。

Description

高炉喷吹煤粉多级分段式加热输送管
技术领域
本实用新型涉及一种冶金行业的高炉喷吹煤粉输送装置,具体为一种高炉喷吹煤粉多级分段式加热输送管。
背景技术
高炉喷吹技术是将磨细煤粉直接喷入高炉,以替代资源贫乏、价格昂贵的冶金焦炭,起发热剂和还原剂的作用,从而降低焦比和生铁成本,是钢铁企业节焦增产和改进冶炼工艺最有效的措施之一,约有90%以上的生铁是由喷吹燃料的高炉冶炼而成。
但随着喷吹量的提高,喷煤比增加到一定限度后,焦比降低的幅度会大大减少,主要原因是喷入的煤粉不能在风口前完全燃烧,未燃煤粉会被上升的煤气带出回旋区,至成渣带时被黏附在初渣中,增加了初成渣的黏度,恶化料柱透气性,使高炉顺行不利,甚至有部分炭粒被带出炉外浪费掉。因此,如何提高煤粉在风口前的燃烧率,成为喷煤比进一步提高的关键。
高炉喷吹煤粉的输送方式有两种,一种是采用煤粉罐装专用车,一种是采用管道气力输送,其中,气力输送连续性好,能力大且密闭性好,是高炉喷煤中普遍采用的煤粉输送方式。目前采用管道气力输送都是将煤粉通过管道直接喷入高炉,冷态的煤粉与1100℃以上的热风相遇,存在一个加热至着火的过程,同时冷态的煤粉对热风存在冷却效应,这些因素对煤粉的燃烧都造成了不利影响。
发明内容
本实用新型为了解决现有技术中存在的冷态的煤粉直接喷吹而影响燃烧率的问题提供了一种高炉喷吹煤粉多级分段式加热输送管。
本实用新型是由以下技术方案实现的,一种高炉喷吹煤粉多级分段式加热输送管,由至少一个加热单元组成,每个加热单元由内层的输送管和外层的加热管套接构成,输送管和加热管的两端之间为封闭状,加热管上分别开有介质进口和介质出口,在加热单元两端设有连接法兰,中部装配有膨胀节,以补偿受热后的变形量。
高炉喷吹煤粉气力输送过程中,在压缩气体的作用下,在输送管内处于高速流动状态(流速>10m/s),为了不降低同口径管路的输粉能力,同时对高速流动的煤粉进行有效加热,本实用新型采用多级分段式加热方式即通过四个串联的加热单元逐级将煤粉加热至120~160℃。分级分段式加热,既保证了每个加热单元的传热效率,同时也保证了煤粉有足够的加热长度和加热时间,解决了煤粉在高速输送过程中加热至120~160℃的技术问题。
采用多级分段式加热输送管,可以将目前不加热直接输送喷吹煤粉的温度提高至120~160℃,减轻喷吹煤对热风的冷却效应,缩短煤粉在高炉风口前加热至着火的时间,加速煤粉的燃烧,提高煤粉燃烧率,减少未燃煤粉对高炉的不良影响,提高煤焦置换比,扩大喷吹量。在同等风温和富氧条件下,可提高煤粉燃烧率15%,提高喷煤比20kg/t铁,降低焦炭消耗和生铁成本,经济效益显著。同时加热后煤粉流动性增强,更有利于输送。
附图说明
图1为本实用新型的结构示意图
图2为加热单元结构示意图
图3为图2的A向视图
图4为图2的B-B剖面图
图中:1-连接法兰,2-压力传感器,3-温度传感器,4-膨胀节,5-加热管,6-输送管,7-介质入口,8-连接法兰,9-介质出口
具体实施方式
如图1、2所示,一种高炉喷吹煤粉多级分段式加热输送管,该管有四个加热单元组成,每个加热单元由内层的输送管6和外层的加热管5套接构成,输送管6和加热管5的两端之间为封闭状,加热管5上分别开有介质入口7和介质出口9,在加热单元两端设有连接法兰1、8,中部装配有膨胀节4,以补偿受热后的变形量。
工质蒸汽由介质入口7通入,在输送管6、加热管5之间流动过程中将热量传递给内管煤粉,冷凝汽由介质出口9排出。加热单元的中部装配有膨胀节4以补偿受热后的变形量。
在输送管6和加热管5之间的夹层内装有压力传感器2,在输送管6内装有温度传感器3。
压力传感器2和温度传感器3可以对系统压力和温度参数进行实时监控。

Claims (3)

1、一种高炉喷吹煤粉多级分段式加热输送管,其特征在于:该管有至少一个加热单元组成,每个加热单元由内层的输送管(6)和外层的加热管(5)套接构成,输送管(6)和加热管(5)的两端之间为封闭状,加热管(5)上分别开有介质入口(7)和介质出口(9),在加热单元两端设有连接法兰(1、8),中部装配有膨胀节(4)。
2、根据权利要求1所述的高炉喷吹煤粉多级分段式加热输送管,其特征在于:在输送管(6)和加热管(5)之间的夹层内装有压力传感器(2),在输送管(6)内装有温度传感器(3)。
3、根据权利要求1或2所述的高炉喷吹煤粉多级分段式加热输送管,其特征在于:加热单元有四个。
CNU2008200764814U 2008-03-07 2008-03-07 高炉喷吹煤粉多级分段式加热输送管 Expired - Fee Related CN201158668Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200764814U CN201158668Y (zh) 2008-03-07 2008-03-07 高炉喷吹煤粉多级分段式加热输送管

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200764814U CN201158668Y (zh) 2008-03-07 2008-03-07 高炉喷吹煤粉多级分段式加热输送管

Publications (1)

Publication Number Publication Date
CN201158668Y true CN201158668Y (zh) 2008-12-03

Family

ID=40109261

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200764814U Expired - Fee Related CN201158668Y (zh) 2008-03-07 2008-03-07 高炉喷吹煤粉多级分段式加热输送管

Country Status (1)

Country Link
CN (1) CN201158668Y (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103589818A (zh) * 2012-08-14 2014-02-19 攀钢集团研究院有限公司 高炉喷煤管和降低高炉的焦比的方法
CN107447066A (zh) * 2017-09-21 2017-12-08 长治市方圣喷吹技术有限公司 一体式高炉喷吹煤粉预热器
CN115354097A (zh) * 2022-08-25 2022-11-18 付光明 一种节能型高炉煤气多级加热竖式煤粉加热装置和方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103589818A (zh) * 2012-08-14 2014-02-19 攀钢集团研究院有限公司 高炉喷煤管和降低高炉的焦比的方法
CN107447066A (zh) * 2017-09-21 2017-12-08 长治市方圣喷吹技术有限公司 一体式高炉喷吹煤粉预热器
CN115354097A (zh) * 2022-08-25 2022-11-18 付光明 一种节能型高炉煤气多级加热竖式煤粉加热装置和方法
CN115354097B (zh) * 2022-08-25 2023-10-31 付光明 一种节能型高炉煤气多级加热竖式煤粉加热装置和方法

Similar Documents

Publication Publication Date Title
CN100535127C (zh) 高炉喷吹煤粉喷前预热工艺
CN102605119B (zh) 一种高炉喷吹煤粉过程中的煤粉输送及预热工艺装置
CN104152618B (zh) 高炉软水冷却管路控制方法
CN201158668Y (zh) 高炉喷吹煤粉多级分段式加热输送管
CN107447066B (zh) 一体式高炉喷吹煤粉预热器
CN114634999A (zh) 一种氧气高炉煤气超高温加热冶炼方法
CN202482333U (zh) 一种高炉
CN204611770U (zh) 多孔介质喷射式烧嘴
CN207313541U (zh) 欧冶炉煤制气装置
CN103993110B (zh) 高炉喷吹煤粉预热工艺
CN103014205A (zh) 高炉富氧喷煤的供氧方法
CN207276638U (zh) 一种一体式高炉喷吹煤粉预热器
CN202092468U (zh) 高温陶瓷焊补冷却枪
CN203904371U (zh) 新型高炉喷吹煤粉多级分段式预热器
CN202576449U (zh) 一种高炉喷吹煤粉过程中的煤粉输送及预热工艺装置
CN201779366U (zh) 用于油炉法炭黑生产设备的热风管道
CN2804114Y (zh) 高炉进风装置
CN113430311A (zh) 一种高炉喷吹焦炉煤气的方法
CN218763502U (zh) 一种煤粉炉用煤粉预热喷吹装置
CN206109445U (zh) 一种热风炉废气余热利用装置
CN201074236Y (zh) 高炉送风支管
CN115011747B (zh) 一种高炉喷吹富氢燃料装置
CN220907527U (zh) 一种可喷吹还原气体的高炉风口小套
CN219829491U (zh) 一种节能再生炉
CN205368275U (zh) 一种新型鼓风口氧气烧嘴

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Shanxi Lu'an Environmental Energy Development Co., Ltd.

Assignor: Shanxi Lu'an Mining Industry (Group) Co., Ltd.|Changzhi City Fang Sheng injection technology company limited

Contract fulfillment period: 2009.8.1 to 2018.3.6

Contract record no.: 2009990001310

Denomination of utility model: Multilevel segmented heating transportation pipe for blast furnace coal injection

Granted publication date: 20081203

License type: Exclusive license

Record date: 20091207

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2009.8.1 TO 2018.3.6; CHANGE OF CONTRACT

Name of requester: SHANXI LUAN ENVIRONMENT PROTECTION ENERGY DEVELOPM

Effective date: 20091207

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081203

Termination date: 20140307