CN201155906Y - Gas drying system for plaster board - Google Patents
Gas drying system for plaster board Download PDFInfo
- Publication number
- CN201155906Y CN201155906Y CNU2007201597015U CN200720159701U CN201155906Y CN 201155906 Y CN201155906 Y CN 201155906Y CN U2007201597015 U CNU2007201597015 U CN U2007201597015U CN 200720159701 U CN200720159701 U CN 200720159701U CN 201155906 Y CN201155906 Y CN 201155906Y
- Authority
- CN
- China
- Prior art keywords
- burner
- circulating fan
- thistle board
- mixing chamber
- gas drying
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Drying Of Solid Materials (AREA)
Abstract
The utility model discloses a thistle board fuel gas drying system which dries a thistle board by heating natural gas, is clean and environment-protective. The system essentially comprises a burner (1), a circulating fan (2), a mixing chamber (3) and a valve set regulating controller (4); the burner (1) is arranged in the box air duct (8) of a production line; the circulating fan (2) is subsequently connected with the box air duct (8) and the mixing chamber (3) to form a circuit; a fuel gas supply system (7) is subsequently connected with the valve set regulating controller (4) and the burner (1). The system uses a fuel gas drying process to replace the prior fuel coal drying process, saves energy and protects the environment with adjustable and controllable air feeding temperature and the flame length of the burner, meets the process requirement for large-scale continuous production, and improves the working efficiency of equipments and the product quality.
Description
Technical field
The utility model relates to building materials manufacturing machine field, especially a kind of Thistle board combustion gas drying system.
Background technology
At present, domestic production Paper-faced gyp board assembly line all adopts coal-fired dry, in the strict area of environmental protection condition, obviously can not reach requirement, utilize combustion gas to carry out drying to the Thistle board needs that become a reality like this, press for and develop a kind of device that utilizes combustion of natural gas, realize combining and satisfy the needs of Thistle board drying with the controlling of production process of Thistle board.
Summary of the invention
Provide a kind of Thistle board combustion gas drying system in order to solve the problems of the technologies described above the utility model, utilized heating to come dry Thistle board, cleaning, environmental protection natural gas.
For achieving the above object, the technical solution of the utility model is:
Mainly comprise burner, circulating fan, mixing chamber and valve group control set for adjusting, burner is installed in the casing air channel of production line, circulating fan and casing air channel, mixing chamber are in turn connected to form the loop, and gas supply device and valve group control set for adjusting, burner are linked in sequence;
Also be connected with combustion fan on the described burner;
Be provided with dehydrating unit between described circulating fan and the casing air channel.
According to the needs of production line, the gas supply device can be realized the plasterboard of a plurality of dry sections is carried out drying.
The utility model is existing coal-fired dry with the dry replacement of combustion gas, energy-saving and environmental protection, and the length of flame of wind pushing temperature and burner all can regulate and control, and is fit to the technological requirement of large-scale continuous production, has improved the operating efficiency of equipment and the quality of product.
Description of drawings
Accompanying drawing is a structural representation of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described in detail:
As shown be an embodiment of the present utility model, need to realize that the plasterboard to two dry sections carries out drying, burner 1 is installed in the casing air channel 8 of production line, circulating fan 2 is in turn connected to form the loop with casing air channel 8, mixing chamber 3, gas supply device 7 is linked in sequence with valve group control set for adjusting 4, burner 1, be connected with combustion fan 5 on the burner 1, be provided with dehydrating unit 6 between circulating fan 2 and the casing air channel 8.
The two-way natural gas is respectively through gas supply device 7, valve group control set for adjusting 4 double-filtrations, decompression enters burner 1, the wind that produces with circulating fan 2 mixes completing combustion in the casing air channel 8 of production line, the length of flame is controlled, thereby temperature is easily regulated, the hot blast that obtains fully mixes the clean hot blast of output through mixing chamber 3 and is used for dry I district of plasterboard and the dry II of plasterboard district are carried out drying, the hot blast temperature of output can be controlled in the 200-350 ℃ of scope, dried hot blast temperature is about 90-110 ℃, a part is used for dehumidifying through dehydrating unit 6 discharges, and another part is delivered in the casing air channel 8 through circulating fan 2 and heated by burner 1 circulation.Because burner 1 is to be directly installed in the casing air channel 8 of production line, abundant heat cycles wind, burner 1 external combustion fan 5 is with the 1 abundant smooth combustion of assurance burner.The hot blast temperature that burner 1 heating obtains can be regulated as requested, and it has higher load regulation rate, can accurate temperature controlling, be particularly suitable for the technological requirement of large-scale continuous production.
Claims (3)
1, a kind of Thistle board combustion gas drying system, it is characterized in that, mainly comprise burner (1), circulating fan (2), mixing chamber (3) and valve group control set for adjusting (4), burner (1) is installed in the casing air channel (8) of production line, circulating fan (2) is in turn connected to form the loop with casing air channel (8), mixing chamber (3), and gas supply device (7) is linked in sequence with valve group control set for adjusting (4), burner (1).
2, Thistle board combustion gas drying system according to claim 1 is characterized in that, also is connected with combustion fan (5) on the described burner (1).
3, Thistle board combustion gas drying system according to claim 1 is characterized in that, is provided with dehydrating unit (6) between described circulating fan (2) and casing air channel (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007201597015U CN201155906Y (en) | 2007-12-29 | 2007-12-29 | Gas drying system for plaster board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007201597015U CN201155906Y (en) | 2007-12-29 | 2007-12-29 | Gas drying system for plaster board |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201155906Y true CN201155906Y (en) | 2008-11-26 |
Family
ID=40103688
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2007201597015U Expired - Lifetime CN201155906Y (en) | 2007-12-29 | 2007-12-29 | Gas drying system for plaster board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201155906Y (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102371621A (en) * | 2010-08-16 | 2012-03-14 | 北新集团建材股份有限公司 | Production system for thistle board |
CN103940208A (en) * | 2014-04-10 | 2014-07-23 | 山东六九矿业装备科技有限公司 | Gypsum board industrial waste heat drying system |
CN104422268A (en) * | 2013-09-10 | 2015-03-18 | 北新集团建材股份有限公司 | Drying kiln temperature control device and method |
CN110103332A (en) * | 2019-04-02 | 2019-08-09 | 北新集团建材股份有限公司 | A kind of heat source is the Thistle board drying device and drying process of natural gas |
CN114705056A (en) * | 2022-04-11 | 2022-07-05 | 泰山石膏有限公司 | Gypsum board production line heating system |
-
2007
- 2007-12-29 CN CNU2007201597015U patent/CN201155906Y/en not_active Expired - Lifetime
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102371621A (en) * | 2010-08-16 | 2012-03-14 | 北新集团建材股份有限公司 | Production system for thistle board |
CN102371621B (en) * | 2010-08-16 | 2013-07-31 | 北新集团建材股份有限公司 | Production system for thistle board |
CN104422268A (en) * | 2013-09-10 | 2015-03-18 | 北新集团建材股份有限公司 | Drying kiln temperature control device and method |
CN104422268B (en) * | 2013-09-10 | 2017-03-15 | 北新集团建材股份有限公司 | A kind of dry kiln temperature control equipment and method |
CN103940208A (en) * | 2014-04-10 | 2014-07-23 | 山东六九矿业装备科技有限公司 | Gypsum board industrial waste heat drying system |
CN103940208B (en) * | 2014-04-10 | 2015-12-02 | 山东六九矿业装备科技有限公司 | Plasterboard industrial exhaust heat drying system |
CN110103332A (en) * | 2019-04-02 | 2019-08-09 | 北新集团建材股份有限公司 | A kind of heat source is the Thistle board drying device and drying process of natural gas |
CN114705056A (en) * | 2022-04-11 | 2022-07-05 | 泰山石膏有限公司 | Gypsum board production line heating system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201155906Y (en) | Gas drying system for plaster board | |
CN101324399B (en) | Drying room waste gases incineration flue gas heating system with adjustable heat supply | |
CN103940221A (en) | Novel energy-saving kiln | |
CN102183129A (en) | Drying device for architectural ceramic roller table | |
CN201787823U (en) | Heat-power balancing device for sintering waste heat generating system | |
CN201413021Y (en) | Heating device of single-yarn shaping machine drying room | |
CN201284292Y (en) | Central heating system for gypsum board and construction gypsum production line | |
CN102494529A (en) | Constant-temperature drying box utilizing flue gas waste heat for heating | |
CN104164803B (en) | A kind of Gas Direct-fired heated oven | |
CN101349509B (en) | Preheating sintered mixture process utilizing heating furnace hot waste gas | |
CN110118100A (en) | Antifreezing of underground mine supply air system and method based on high temperature and high pressure electrical heating solid-state heat accumulation | |
CN203687075U (en) | Primary air system of coal mill of thermal power plant | |
CN203163478U (en) | Novel energy-saving kiln | |
CN202109736U (en) | Building ceramic roll table drying equipment | |
CN201399906Y (en) | Packing base material curing device | |
CN201467907U (en) | Tea baking machine | |
CN103940208B (en) | Plasterboard industrial exhaust heat drying system | |
CN203518513U (en) | Multi-channel heat supply drying system | |
CN202133106U (en) | Hot air device | |
CN2823942Y (en) | Hot air drier for paper face gypsum board | |
CN202993787U (en) | Energy-saving quick drying kiln | |
CN204730453U (en) | For mica slurrying provides the device of the energy | |
CN205262225U (en) | Hot flue gas recycle system | |
CN201301282Y (en) | Glass kiln residual heat yarn baking device | |
CN103693645B (en) | Switch load system for isolated power system operation in calcium carbide plant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Assignee: Taishan gypsum (Chongqing) Co., Ltd. Assignor: Taishan Gypsum Co., Ltd. Contract record no.: 2013370000177 Denomination of utility model: Gas drying system for plaster board Granted publication date: 20081126 License type: Exclusive License Record date: 20130726 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
CX01 | Expiry of patent term |
Granted publication date: 20081126 |
|
CX01 | Expiry of patent term |