CN201128917Y - Three-way cable working well - Google Patents
Three-way cable working well Download PDFInfo
- Publication number
- CN201128917Y CN201128917Y CNU200720198704XU CN200720198704U CN201128917Y CN 201128917 Y CN201128917 Y CN 201128917Y CN U200720198704X U CNU200720198704X U CN U200720198704XU CN 200720198704 U CN200720198704 U CN 200720198704U CN 201128917 Y CN201128917 Y CN 201128917Y
- Authority
- CN
- China
- Prior art keywords
- well
- member piece
- upper member
- connectivity mouth
- building block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The utility model discloses a tee-type cable working well in the technological field of underground engineering. The cable working well comprises a prefabricated part, a sealing component and a connecting component. The prefabricated part comprises an upper building block of a head end, a lower building block of the head end, an upper building block of a transition section, a lower building block of the transition section, an upper building block of a wellhead end, a lower building block of the wellhead end, and a building block of a water-accumulating well; the height of each piled pair of building blocks is the height of the well; the prefabricated part is used for assembling a straightthrough well body with two ends provided with a through-hole; any side of the well body is provided with a third through-hole; the seam of the assembling prefabricated parts is provided with the sealing component; and the prefabricated parts are connected through the connecting component. The cable working well has the third through-hole to expand the working space, and is suitable for cables that are arranged in different way. And the cable working well facilitates the first-acid repair of cable faults, reduces costs of the first-acid repair, and has the practicality for the laying of cables.
Description
Technical field
The utility model relates to a kind of active well of underground construction technical field, specifically is a kind of tee joint type cable working well.
Background technology
Existing underground utilities active well has several like this forms: active well and splicing prefabricated components formula active well that active well, cast-in-situ concrete active well, concrete block formula active well, splicing prefabricated components and the reinforced concrete cast-in-situ mode that adopts loam brick to be built into combines.Wherein, the active well of preceding four kinds of forms or have that intensity is low, easy to leak, non-resistant defective, or the deficiency of long, workmanship poor reliability of construction period is arranged.
Find by prior art documents, publication number is that (open day: Chinese utility model patent " precast splice type cable active well and job practices thereof " on December 20th, 2006) is disclosed to be a kind of straight cable work well to CN1880591A, only comprises two ports.Because of structure is too simple, the layout of underground utilities is restricted, can not satisfy the needs of various construction occasions.
The utility model content
The purpose of this utility model is to overcome deficiency of the prior art, and a kind of tee joint type cable working well is provided, and the utlity model has three ports and has enlarged working space, again can the different arrangement modes of appropriate cable.Be convenient to the cable fault repairing, reduce emergency repair cost, meet the practicality of cable laying.
The utility model is achieved through the following technical solutions, the utility model tee joint type cable working well comprises: prefabricated component blocks, seal and connector, described prefabricated component blocks comprises termination upper member piece, termination lower member piece, changeover portion upper member piece, changeover portion lower member piece, uphole end upper member piece, uphole end lower member piece, ponding well building block, and each upper and lower building block stack back of matching mutually highly is a well height degree; Be assembled into straight-through well body by prefabricated component blocks, respectively there is port at its two ends, also are provided with third connectivity mouth at the either side of well body; The seam crossing that all prefabricated component blocks are spliced mutually all is lined with seal, is connected by connector between the prefabricated component blocks.
Described third connectivity mouth is to be formed by stacking by third connectivity mouth upper member piece and the assembly unit of third connectivity mouth lower member piece; Third connectivity mouth upper member piece outstanding bucking ladder is arranged by the well side, with three changeover portion upper member pieces that third connectivity mouth splices mutually bucking ladder is arranged respectively also, the bucking ladder by complementation between third connectivity mouth upper member piece and the three changeover portion upper member pieces matches.
The corner that forms between third connectivity mouth and the well body, preferred arc.
The vertical height of the prefabricated component blocks that well body horizontal direction is adjacent is different, and the horizontal direction seam of promptly adjacent upper and lower building block is not in same horizon.
Compared with prior art, the utlity model has three ports and enlarged working space, again can the different arrangement modes of appropriate cable.Third connectivity mouth matches with three changeover portion upper member pieces of well dignity by being provided with the bucking ladder structure, can remove on the well body upper surface adding crossbeam from.Corner between third connectivity mouth and the well body is curved, on the corner weares and teares to prevent cable.The vertical height of the prefabricated component blocks that well body horizontal direction is adjacent is different, and the horizontal direction seam of promptly adjacent upper and lower building block is not in same horizon, to strengthen the assembly unit intensity of well body.
Description of drawings
Fig. 1 is the utility model overall structure schematic diagram;
Fig. 2 is the structural representation of third connectivity mouth upper member piece;
Fig. 3 is the structural representation of three changeover portion upper member pieces;
The cross section structure schematic diagram of Fig. 4 for matching between third connectivity mouth upper member piece and the changeover portion upper member piece.
Mark is as follows:
1-termination upper member piece, 2-changeover portion upper member piece, 3-uphole end upper member piece, 4-third connectivity mouth upper member piece, 1 '-termination lower member piece, 2 '-changeover portion lower member piece, 3 '-uphole end lower member piece, 4 '-third connectivity mouth lower member piece.
The specific embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is elaborated: present embodiment is being to implement under the prerequisite with technical solutions of the utility model; provided detailed embodiment and process, but protection domain of the present utility model is not limited to following embodiment.
As shown in Figure 1, present embodiment comprises: prefabricated component blocks, seal and connector, prefabricated component blocks comprises termination upper member piece 1, termination lower member piece 1 ', changeover portion upper member piece 2, changeover portion lower member piece 2 ', uphole end upper member piece 3, uphole end lower member piece 3 ', ponding well building block, and each upper and lower building block stack back of matching mutually highly is a well height degree; Be assembled into straight-through well body by prefabricated component blocks, respectively there is port at its two ends, also are provided with third connectivity mouth at the either side of well body; The seam crossing that all prefabricated component blocks are spliced mutually all is lined with seal, is connected by connector between the prefabricated component blocks.
Third connectivity mouth as shown in Figure 1, Figure 2, Figure 3 and Figure 4 is to be formed by stacking by third connectivity mouth upper member piece 4 and the 4 ' assembly unit of third connectivity mouth lower member piece; There is outstanding bucking ladder on the well side of leaning at third connectivity mouth upper member piece 4, with three changeover portion upper member pieces 2 that third connectivity mouth splices mutually bucking ladder is arranged respectively also, the bucking ladder by complementation between third connectivity mouth upper member piece 4 and the three changeover portion upper member pieces 2 matches.
Form the arc corner between third connectivity mouth and the well body.
The vertical height of the prefabricated component blocks that well body horizontal direction is adjacent is different, and the horizontal direction seam of promptly adjacent upper and lower building block is not in same horizon.
If will need to change well body length longitudinally, can realize by the number of the upper and lower building block of increase and decrease changeover portion.
Compared with prior art, present embodiment has three ports and has enlarged working space, again can the different arrangement modes of appropriate cable.Third connectivity mouth matches with three changeover portion upper member pieces 2 of well dignity by being provided with the bucking ladder structure, can remove on the well body upper surface adding crossbeam from.Corner between third connectivity mouth and the well body is curved, on the corner weares and teares to prevent cable.The vertical height of the prefabricated component blocks that well body horizontal direction is adjacent is different, and the horizontal direction seam of promptly adjacent upper and lower building block is not in same horizon, to strengthen the assembly unit intensity of well body.
Claims (4)
1. tee joint type cable working well, comprise: prefabricated component blocks, seal and connector, described prefabricated component blocks comprises termination upper member piece, termination lower member piece, changeover portion upper member piece, changeover portion lower member piece, uphole end upper member piece, uphole end lower member piece, ponding well building block, each highly is a well height degree after the upper and lower building block of pairing superposes mutually, it is characterized in that, be assembled into straight-through well body by prefabricated component blocks, respectively there is port at its two ends, also are provided with third connectivity mouth at the either side of well body; The seam crossing that all prefabricated component blocks are spliced mutually all is lined with seal, is connected by connector between the prefabricated component blocks.
2. tee joint type cable working well as claimed in claim 1 is characterized in that, described third connectivity mouth is to be formed by stacking by third connectivity mouth upper member piece and the assembly unit of third connectivity mouth lower member piece; Third connectivity mouth upper member piece outstanding bucking ladder is arranged by the well side, with three changeover portion upper member pieces that third connectivity mouth splices mutually bucking ladder is arranged respectively also, the bucking ladder by complementation between third connectivity mouth upper member piece and the three changeover portion upper member pieces matches.
3. tee joint type cable working well as claimed in claim 1 is characterized in that, forms the arc corner between third connectivity mouth and the well body.
4. as the arbitrary described tee joint type cable working well of claim 1 to 3, it is characterized in that the vertical height of described prefabricated component blocks between well body horizontal direction is adjacent is different.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU200720198704XU CN201128917Y (en) | 2007-11-30 | 2007-11-30 | Three-way cable working well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU200720198704XU CN201128917Y (en) | 2007-11-30 | 2007-11-30 | Three-way cable working well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201128917Y true CN201128917Y (en) | 2008-10-08 |
Family
ID=40016755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU200720198704XU Expired - Lifetime CN201128917Y (en) | 2007-11-30 | 2007-11-30 | Three-way cable working well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201128917Y (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101451361B (en) * | 2007-11-30 | 2010-08-25 | 上海久隆电力(集团)有限公司 | Tee joint type cable working well |
CN102409699A (en) * | 2010-09-25 | 2012-04-11 | 河南省电力公司焦作供电公司 | Integrated three-way cable working well |
-
2007
- 2007-11-30 CN CNU200720198704XU patent/CN201128917Y/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101451361B (en) * | 2007-11-30 | 2010-08-25 | 上海久隆电力(集团)有限公司 | Tee joint type cable working well |
CN102409699A (en) * | 2010-09-25 | 2012-04-11 | 河南省电力公司焦作供电公司 | Integrated three-way cable working well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105256838B (en) | Pipe gallery prefabricated members and prefabricated comprehensive pipe gallery | |
CN205171549U (en) | Piping lane prefab and prefabricated formula utility tunnel | |
CN204174787U (en) | The syndeton of precast concrete exterior wall and steel work | |
CN204290230U (en) | Assembled high voltage single-core cable concrete groove | |
CN201128917Y (en) | Three-way cable working well | |
CN205116417U (en) | Box -shaped fast -assembling house | |
CN207553133U (en) | A kind of underground pipe gallery structure | |
CN106356796A (en) | Multipurpose electric power channel | |
CN106356768A (en) | Electricity paving device for rapidly and smooth pavement along curvilinear path | |
CN101451361B (en) | Tee joint type cable working well | |
CN211850362U (en) | Plug-in cross column | |
CN206956775U (en) | A kind of cabin pipe gallery of plain type underground three | |
CN103790156A (en) | Square buckle plate mechanical pile splicing method for precast square piles | |
CN2778930Y (en) | Armored concrete hollow prefabricated component plate | |
CN208690872U (en) | A kind of pre-fabricated electric cables comb | |
CN205509439U (en) | Swiftly install type cable ditch | |
CN211446883U (en) | Underground continuous wall antiseep connection structure | |
CN204418433U (en) | A kind of adjustable masonry filler wall and frame column flexible connecting structure | |
CN209621335U (en) | Prefabricated film connection component and inverted arch structure with it | |
CN203656365U (en) | Combination-type transition cable leading cage based on cable leading towards lower bridge surface | |
CN210031455U (en) | Small box girder bridge floor connecting structure | |
CN205051311U (en) | Cable groove that used in loose area of earthquake region and soil property | |
CN201794092U (en) | Integral three-way type cable work well | |
CN203296039U (en) | Connector for connecting precast piles | |
CN1482304A (en) | Method of laying, welding and construction of canal seepage proof film |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20081008 Effective date of abandoning: 20071130 |