CN201092521Y - Inner-climbing tower crane hydraulic supporting arrangement - Google Patents

Inner-climbing tower crane hydraulic supporting arrangement Download PDF

Info

Publication number
CN201092521Y
CN201092521Y CNU2007200727609U CN200720072760U CN201092521Y CN 201092521 Y CN201092521 Y CN 201092521Y CN U2007200727609 U CNU2007200727609 U CN U2007200727609U CN 200720072760 U CN200720072760 U CN 200720072760U CN 201092521 Y CN201092521 Y CN 201092521Y
Authority
CN
China
Prior art keywords
tower crane
climbing
hydraulic
climbs
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200727609U
Other languages
Chinese (zh)
Inventor
陈晓明
张宇
潘令誉
吴欣之
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CNU2007200727609U priority Critical patent/CN201092521Y/en
Application granted granted Critical
Publication of CN201092521Y publication Critical patent/CN201092521Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to a hydraulic support device of an internal climbing crane, which comprises two climbing beams, and is characterized in that each climbing beam is equipped with two hydraulic jacks, while the four hydraulic jacks on the two climbing beams are distributed on a vertical projected line at a tower placing leg, the hydraulic jacks are fixedly connected to the climbing beams via supports provided with baffle plates, and the hydraulic jacks are arranged at the inner side of the baffle plates. The hydraulic support device of the internal climbing crane has the advantages that the force on the placing leg of the crane body can be adjusted uniformly when the internal climbing crane climbs on the climbing beams to guarantee crane verticality.

Description

The inside-climbing tower crane hydraulic supporting device
Technical field
The utility model relates to a kind of hydraulic supporting device, particularly a kind of inside-climbing tower crane hydraulic supporting device.
Background technology
When building high-rise building, because it highly substantially exceeds the height that existing tower crane can reach, therefore adopted a kind of tower crane that can be installed on the side of buildings bearing support at present, rising along with the building height of building, hydraulic jacking system on the base section of tower crane dependence tower crane bottom is finished along building and is climbed, in the construction of reality, the installation of inside-climbing tower crane and climbing puts in place shelves four of all requiring the supporting tower crane and shelves a little on same horizontal surface, makes the stressed even as much as possible of each point.Otherwise the following beam that climbs stressed there is very big influence, if four of supporting tower crane shelve a unbalance stress, may cause inside-climbing tower crane dangerous situation when hoisting heavy, to occur, owing to often be difficult to accomplish four whole levels of turning over pin on framework, supporting-point, the body of the tower at the scene, be with certain degree of difficulty and risk to construction.Therefore demand inventing a kind of device that can solve the supporting discontinuity of inside-climbing tower crane urgently.
Summary of the invention
The purpose of this utility model is to solve inside-climbing tower crane to climb on the beam four to shelve the discrepancy in elevation is a little arranged, thereby makes four problems of shelving a discontinuity equalization of tower crane.A kind of inside-climbing tower crane hydraulic supporting device is provided.The utility model designs a kind of inside-climbing tower crane hydraulic supporting device, comprise two beams that climb, it is characterized in that: the every beam that climbs is provided with two hydraulic jacks, four hydraulic jacks on two beams that climb are distributed in body of the tower and shelve in the vertical projecting line of pin, hydraulic jack is fixedly connected on the beam that climbs by bearing, baffle plate is arranged on bearing, and hydraulic jack is positioned at the baffle plate inboard.The utility model has the advantages that can be at the inside-climbing tower crane Liang Shanghou that climbs that climbs to, regulate body of the tower shelve pin stressed evenly, guarantee the squareness of tower crane.
Description of drawings
Accompanying drawing 1 is the initial condition scheme drawing that climbs of the tower crane in the utility model,
Accompanying drawing 2 is the view that puts in place of climbing of the tower crane in the utility model,
Accompanying drawing 3 is returned to the initial condition scheme drawing for the tower crane in the utility model climbs,
Accompanying drawing 4 structural representations of the present utility model,
Accompanying drawing 5 is the running condition scheme drawing that is installed on the beam that climbs of the present utility model,
Below in conjunction with accompanying drawing and example the utility model is elaborated.
The specific embodiment
Tower crane 11 is positioned on the building 12 and prepares to climb among Fig. 1, and three road frameworks 13 are arranged on building 12, the beam (not marking among the figure) that wherein climbs on two frameworks below, the tower crane that the hydraulic efficiency pressure system on the base section under the tower crane can jacking top.Be located on the central frame 13 after tower crane 11 climbs among Fig. 2, finish once and climb.Comprise two beams 1 that climb among Fig. 3,4, it is characterized in that: every beam 1 that climbs is provided with climb four hydraulic jacks 2 on the beam 1 of 2, two of two hydraulic jacks and is distributed in body of the tower and shelves in the vertical projecting line of pin 4.Hydraulic jack 2 is fixedly connected on the beam 1 that climbs by bearing 5, and baffle plate 3 is arranged on bearing 5, and hydraulic jack 2 is positioned at baffle plate 3 inboards.
Four hydraulic jacks 2 corresponding to the beam 1 that climbs on the tower crane 11 have four bodies of the tower to shelve pin 4, when tower crane 11 is installed or climbed to when climbing beam 1, shelve pin 4 and can open on four hydraulic jacks 2 that set aside on the beam 1 that climbs for four on the tower crane 11, shelving of beam 1 a little has the discrepancy in elevation if at this moment climb, or the bottom surface Mismachining tolerance of shelving pin 4, the capital causes the body of the tower squareness not meet the demands, cause certain shelve pin 4 with shelve a little do not contact fully or four shelve a discontinuity, thereby have influence on the stressed of beam 1 and following structure that climb.It is to be shelved on four hydraulic jacks 2 that but present four bodies of the tower are shelved pin 4, can be earlier just calculate each shelve locate stressed, hydraulic jack 2 jack-up then, to tower crane shelve pin 4 apply each shelve a little should be stressed 30%~50%, can guarantee hydraulic jack 2 and shelve pin 4 and fully contact, again can jack-up tower crane 11.At this moment measure the squareness of tower crane 11, as long as by adjusting the top lifting height of four hydraulic jacks 2, just can make the squareness of tower crane 11 reach installation requirement, four of four hydraulic jack 2 places formation shelve a little stressed even substantially.Then the load of tower crane is transferred to fully the beam that climbs shelve a little on.
Because the deadweight and the lifted load of inside-climbing tower crane 11 are bigger, therefore adopt large-tonnage hydraulic jack 2, guaranteed the safety of practice of construction.Before inside-climbing tower crane 11 does not set aside on the beam that climbs as yet fully, the method of the both direction squareness by measuring body of the tower, guarantee that body of the tower is vertical, the suitable height of hydraulic jack 2 jack-up then, promptly defining identical supporting power acts on tower crane 11 and shelves on the pin 4, guarantee that support hydraulic jack 2 and body of the tower four shelve pin 4 and contact, avoided like this since on the beam that climbs four shelve the problem that load distribution that a discrepancy in elevation causes changes.

Claims (2)

1. an inside-climbing tower crane hydraulic supporting device comprises two beams that climb, and it is characterized in that: the every beam that climbs is provided with two hydraulic jacks, and four hydraulic jacks on two beams that climb are distributed in body of the tower and shelve in the vertical projecting line of pin.
2. by the described a kind of inside-climbing tower crane hydraulic supporting device of claim 1, it is characterized in that: hydraulic jack is fixedly connected on the beam that climbs by bearing, and baffle plate is arranged on bearing, and hydraulic jack is positioned at the baffle plate inboard.
CNU2007200727609U 2007-07-23 2007-07-23 Inner-climbing tower crane hydraulic supporting arrangement Expired - Fee Related CN201092521Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200727609U CN201092521Y (en) 2007-07-23 2007-07-23 Inner-climbing tower crane hydraulic supporting arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200727609U CN201092521Y (en) 2007-07-23 2007-07-23 Inner-climbing tower crane hydraulic supporting arrangement

Publications (1)

Publication Number Publication Date
CN201092521Y true CN201092521Y (en) 2008-07-30

Family

ID=39900485

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200727609U Expired - Fee Related CN201092521Y (en) 2007-07-23 2007-07-23 Inner-climbing tower crane hydraulic supporting arrangement

Country Status (1)

Country Link
CN (1) CN201092521Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575071B (en) * 2009-06-04 2010-12-08 同济大学 Rubber clearance bearing device of girder or arm support pitching hinged-support of large-scale machinery equipment
CN114057120A (en) * 2021-10-29 2022-02-18 上海建工四建集团有限公司 Non-turnover type inner climbing tower crane climbing beam and lifting method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575071B (en) * 2009-06-04 2010-12-08 同济大学 Rubber clearance bearing device of girder or arm support pitching hinged-support of large-scale machinery equipment
CN114057120A (en) * 2021-10-29 2022-02-18 上海建工四建集团有限公司 Non-turnover type inner climbing tower crane climbing beam and lifting method
CN114057120B (en) * 2021-10-29 2023-05-26 上海建工四建集团有限公司 Turnover-free type climbing beam of inner climbing tower crane and lifting method

Similar Documents

Publication Publication Date Title
US10041270B2 (en) Utility tower lifting apparatus and method
CN105858536A (en) Electric power overhaul lifting platform
CN205634820U (en) Electric power overhauls lift platform
CN106812328B (en) The whole two step lifting construction methods of string prestressed steel structure rack with hanging layer
CN110965470A (en) Main tower cross brace structure system capable of bearing three-way load and construction method
CN102996062A (en) Maintenance lifting platform and application method thereof
US9440820B2 (en) Escalator lifting frame and method of using the same
CN201092521Y (en) Inner-climbing tower crane hydraulic supporting arrangement
CN110748178A (en) Auxiliary mounting platform for shock insulation support and using method of auxiliary mounting platform
CN103967263A (en) Novel hydraulic automatic climbing discharging platform
CN204057856U (en) Job platform on new-type bar
CN211173157U (en) Bracket for mounting ultrahigh steel beam
CN113264459A (en) Tower crane and jacking and balancing method thereof
CN211772852U (en) Main tower cross brace structure system capable of bearing three-way load
CN205955171U (en) Fall to ground scaffold collet device
CN108589905B (en) Truss corridor integral post-lifting construction system and construction method thereof
CN209651673U (en) A kind of construction elevator attaching structure of lifting platform
CN103741603B (en) The large height of bridge raise after gapless to fall beam method and adjustable height device thereof
CN103743581B (en) Internal-climbing tower crane test platform device and test method
CN109797964A (en) A kind of lifting platform system of integrated tower crane
CN205116883U (en) Mast hoisting device of superelevation layer steel construction launching tower
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN202519621U (en) Steel hoop used for suspending support system
CN205369948U (en) Lifting device for daylighting top is used for installing
CN210369846U (en) Operating platform capable of being clamped on elevator shaft shear wall surface and lifted layer by layer

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080730

Termination date: 20150723