CN201089931Y - Pile-driving sink pipe for foundation construction - Google Patents

Pile-driving sink pipe for foundation construction Download PDF

Info

Publication number
CN201089931Y
CN201089931Y CNU2007200149613U CN200720014961U CN201089931Y CN 201089931 Y CN201089931 Y CN 201089931Y CN U2007200149613 U CNU2007200149613 U CN U2007200149613U CN 200720014961 U CN200720014961 U CN 200720014961U CN 201089931 Y CN201089931 Y CN 201089931Y
Authority
CN
China
Prior art keywords
pipe
pile head
metal
utility
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200149613U
Other languages
Chinese (zh)
Inventor
杨国龙
徐志明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2007200149613U priority Critical patent/CN201089931Y/en
Application granted granted Critical
Publication of CN201089931Y publication Critical patent/CN201089931Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses building foundation construction equipment, in particular a pile driving immersed pipe for building foundation construction. The utility model is formed by a hollow pipe shaped pipe body, a bottom circumferentially provided with at least two guide vanes and a metal pile head, the bottom is arranged on the lower end of the pipe body, the metal pile head is arranged inside the lower end of the bottom, wherein, the section of the pipe body is of a square, the pipe body has a multi-section type structure, two sections of adjoining pipe bodies (1) are riveted through rivets. The front end of the metal pile head is provided with a metal detecting stick. The utility model produces the pipe body into a multi-section type, which decreases the processing difficulty and the cost of the pile driving immersed pipe; the front end of the metal pile head is provided with one metal detecting stick, so the utility model can be used as a hard clay layer detector, and can also extrude out a very small space in the hard clay layer to contribute to the metal pile head to be extracted from the immersed pipe. The joints of the pipe bodies are firm, thereby assuring the operation stability of the equipment.

Description

Foundation construction piling immersed tube
Technical field
The utility model relates to a kind of construction foundation working equipment, particularly a kind of construction foundation working piling immersed tube.
Background technology
In the pile foundation engineering of soft foundation, generally adopt tube-sinking cast-in-situ pile, three kinds of preformed pile and large diameter bored piles at present.And what be most widely used is tube-sinking cast-in-situ pile, when executing immersed tube is passed the weak soil layer, takes out metal pile head after reaching the design elevation hardpan, and the bottom-expanding equipment of expanded bore pile being lowered in the immersed tube cuts the earth, fetches earth again forms the expanded bore pile base cavity pocket.
The pipe shaft of present piling immersed tube is all-in-one-piece structure, and pipe shaft is very long, and processing is difficulty very, and the cost height, can't detect immersed tube when present immersed tube is constructed at the scene and whether arrive hardpan.Also there is a kind of piling immersed tube at present, this immersed tube is a segmentation structure, between the segmentation pipe shaft by being threaded, but find that in practice the connection of thread between this immersed tube multisection type pipe shaft causes the junction insecure because falling into of soil arranged after use a period of time especially easily, and then influence the stability of entire equipment.For these reasons, immersed tube in the past has further improved necessity.
The utility model content
The problem that the utility model exists at above-mentioned prior art, and provide a kind of foundation construction with driving piles immersed tube, purpose is to improve the fastness of pipe shaft junction, simplified structure, increase bearing capacity of single pile, reduce cost, can detect immersed tube and arrived hardpan, convenient construction, immersed tube is easy to process.
The utility model realizes that the technical scheme of purpose is: foundation construction piling immersed tube, it is by the pipe shaft of hollow tubular, along circumferentially the bottom and the metal pile head of at least two guide vanes of setting constitute, the pipe shaft lower end is located in the bottom, metal pile head is arranged on the inside, lower end of bottom, the cross section of pipe shaft is square, the front end of metal pile head is provided with a metal probe, and pipe shaft is a multi-segment structure, connects by rivet between adjacent two sections pipe shafts.
The bottom of described bottom is provided with pin-and-hole.
The utility model compared with prior art, the rivet ways of connecting is adopted in the pipe shaft junction, has strengthened the fastness of junction, thereby has guaranteed the stability of equipment overall operation.And having guaranteed the proportionate relationship of pipe shaft and bottom internal diameter, it is simple and reasonable, practical, makes bearing capacity of single pile reach design standard.The utility model is made multisection type with pipe shaft, reduced piling immersed tube difficulty of processing and cost, be provided with a metal probe at the front end of metal pile head, it both can make ground hardpan survey meter, can in hardpan, extrude a very little sky again and ask, be beneficial to metal pile head and in immersed tube, extract.
Below in conjunction with the drawings and specific embodiments the utility model is described in further details.
Description of drawings
Fig. 1 is a main TV structure schematic diagram of the present utility model.
Among the figure 1, pipe shaft; 2, bottom; 3, guide vane; 4, metal pile head; 5, pin-and-hole; 6, metal probe; 7, rivet.
The specific embodiment
Below embodiment of the present utility model is described in detail in conjunction with the accompanying drawings, but protection domain of the present utility model is not limit by embodiment.
As shown in Figure 1, the utility model foundation construction piling immersed tube, it is by the pipe shaft 1 of hollow tubular, along circumferentially the bottom 2 and the metal pile head 4 of at least two guide vanes 3 of setting constitute, pipe shaft 1 lower end is located in bottom 2, metal pile head 4 is arranged on the inside, lower end of bottom 2, wherein the cross section of pipe shaft 1 is square, and pipe shaft 1 is a multi-segment structure, connects by rivet 6 between adjacent two sections pipe shafts 1.The bottom of bottom 2 is provided with to be convenient to combine and the pin-and-hole 5 of throwing off usefulness with its matching used metal pile head 4.The front end of metal pile head 4 is provided with a metal probe 6.

Claims (2)

  1. Foundation construction with piling immersed tube, it is by the pipe shaft (1) of hollow tubular, along circumferentially the bottom (2) and the metal pile head (4) of at least two guide vanes of setting (3) constitute, pipe shaft (1) lower end is located in bottom (2), metal pile head (4) is arranged on the inside, lower end of bottom (2), the cross section of pipe shaft (1) is square, the front end of metal pile head (4) is provided with a metal probe (6), it is characterized in that pipe shaft (1) is a multi-segment structure, connects by rivet (6) between adjacent two sections pipe shafts (1).
  2. 2. foundation construction according to claim 1 is characterized in that with the piling immersed tube bottom of described bottom (2) is provided with pin-and-hole (5).
CNU2007200149613U 2007-09-29 2007-09-29 Pile-driving sink pipe for foundation construction Expired - Fee Related CN201089931Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200149613U CN201089931Y (en) 2007-09-29 2007-09-29 Pile-driving sink pipe for foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200149613U CN201089931Y (en) 2007-09-29 2007-09-29 Pile-driving sink pipe for foundation construction

Publications (1)

Publication Number Publication Date
CN201089931Y true CN201089931Y (en) 2008-07-23

Family

ID=39861690

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200149613U Expired - Fee Related CN201089931Y (en) 2007-09-29 2007-09-29 Pile-driving sink pipe for foundation construction

Country Status (1)

Country Link
CN (1) CN201089931Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622455A (en) * 2021-07-30 2021-11-09 华济建设工程集团有限公司 Tower crane foundation and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622455A (en) * 2021-07-30 2021-11-09 华济建设工程集团有限公司 Tower crane foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN201089931Y (en) Pile-driving sink pipe for foundation construction
CN201089936Y (en) Pile-driving sink pipe for construction foundation construction
CN201089938Y (en) Pile-forming sink pipe for club-footed pile
CN201087417Y (en) Piling immersed tube of prefabricated steel concrete bottom expanding pile for foundation construction
CN201089916Y (en) Sink pipe for construction foundation construction
CN201089932Y (en) Pile-forming sink pipe being suitable for coasting area
CN201089928Y (en) Pile-driving sink pipe for new type construction foundation construction
CN201089930Y (en) Pile-forming sink pipe
CN201089929Y (en) Pile-driving sink pipe for new type foundation construction
CN201089939Y (en) Pile-driving sink pipe
CN201089926Y (en) Pile-forming sink pipe for new type club-footed pile
CN200985509Y (en) Piling sinking pipe used for construction of bilding basic
CN201089911Y (en) Sink pipe of club-footed pile
CN201121330Y (en) Piling immersed pipe of prefabricated steel concrete pedestal pile
CN201137114Y (en) Novel pile-forming sinking pipe
CN201137115Y (en) Positioning accurate pile-forming sinking pipe
CN200978426Y (en) Piling sinking pipe for club-footed pile
CN201089915Y (en) Pile-forming sink pipe being suitable for coasting area
CN201137118Y (en) Positioning accurate sinking pipe or architecture
CN200978419Y (en) Piling sinking pipe for foundational construction
CN201137116Y (en) Architecture sinking pipe
CN201137119Y (en) Club-footed pile forming sinking pipe
CN201121329Y (en) Assorted immersed pipe of prefabricated steel concrete pedestal pile
CN201137138Y (en) Positioning accurate pile-forming sinking pipe
CN201137127Y (en) Sinking pipe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080723