CN201080793Y - Long spiral mud jacking bore rod - Google Patents

Long spiral mud jacking bore rod Download PDF

Info

Publication number
CN201080793Y
CN201080793Y CNU2007200919350U CN200720091935U CN201080793Y CN 201080793 Y CN201080793 Y CN 201080793Y CN U2007200919350 U CNU2007200919350 U CN U2007200919350U CN 200720091935 U CN200720091935 U CN 200720091935U CN 201080793 Y CN201080793 Y CN 201080793Y
Authority
CN
China
Prior art keywords
long spiral
grouting
grouting pipe
long
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200919350U
Other languages
Chinese (zh)
Inventor
王力纬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2007200919350U priority Critical patent/CN201080793Y/en
Application granted granted Critical
Publication of CN201080793Y publication Critical patent/CN201080793Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a novel long spiral pressure-grouting drill rod, which comprises a long spiral drill rod body 1, and a long spiral drill pit 4, protective plates 6 and reinforced plates 7 are evenly welded on radial circumference of the long spiral drill rod body 1 and the long spiral drill pit 4 so as to form a grouting pipe protection slot, according to the diameter variety of the drill rod, 1-3 grouting pipe protection slots can be evenly arranged on the circumference, the grouting pipe protection slots are filled with grouting pipes and nozzles. When the grouting pipes 2 and the long spiral pressure-grouting drill rod can be drilled to the design elevation synchronously by the utility model, first pressure grouting is performed and then concrete is filled, so as to improve bearing force of end-pile and reduce engineering cost.

Description

Novel long spiral press slurry drilling rod
Technical field:
The utility model relates to the long screw drill rod technical field that the concrete pile driving construction is used in the building machinery, especially a kind of novel long spiral press slurry drilling rod.
Background technology:
Stake normally is installed on the long-spiral drilling machine and holes with long spiral (CFG) drilling rod for long spiral (CFG) concrete when building operations at present, when creeping into to design elevation, long screw drill rod limit perfusion concrete is moved back on the limit, and the sinking reinforcing cage makes bearing capacity of pile tip lower then.Therefore, must improve bearing capacity by density or the length that increases stake, construction cost is higher.
The utility model content:
In order to solve the problem of above-mentioned existence, the purpose of this utility model provides a kind of novel long spiral press slurry drilling rod, in the time of Grouting Pipe and long spiral press can being starched drilling rod and creep into to design elevation synchronously, carries out earlier pouring into concrete again behind the mud jacking, effectively improve bearing capacity of pile tip, reduce construction costs.
Technical solution adopted in the utility model is: described a kind of novel long spiral press slurry drilling rod, comprise the long screw auger body of rod, long spiral drilling head, evenly be welded with backplate and stiffener towards periphery at the described long screw auger body of rod and long spiral drilling head footpath, constitute slip casting thus and manage and protect groove, manage and protect in its slip casting Grouting Pipe is housed in the groove.
Be welded with shower nozzle in described Grouting Pipe near the first end of long screw auger.
Described Grouting Pipe fixes on slip casting by the partial points solid welding and manages and protects in the groove.
Can manage and protect groove in even 1~3 slip casting that distributes of its circumference according to drilling rod bar footpath difference.
The utility model has the advantages that: the utility model combines long spiral (CFG) bored pile and pile base grouting technology, and the two is combined as a whole.Long spiral is in boring procedure, subsidiary Grouting Pipe enters in the stratum of being crept into together, when reaching design elevation, stop to creep into, carry out slip casing by pressure (cement paste or chemical treatment slurries), behind the mud jacking again the limit move back long screw drill rod limit perfusion concrete, physical or chemical treatment is carried out on stake end stratum, the stake end power of carrying is improved greatly, needn't improve bearing capacity of pile tip by density or the length that increases stake again, thereby reduce construction costs.
Description of drawings:
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is the A-A cutaway view Amplified image of Fig. 1.
The specific embodiment:
As shown in Fig. 1,2, the utility model mainly partly is made up of the long screw auger body of rod 1, long spiral drilling head 4 and Grouting Pipe 2 etc.The long screw auger body of rod 1 is connected with long spiral drilling head 4 by several bolts 3, evenly be welded with backplate 6 and stiffener 7 towards periphery at the long screw auger body of rod 1 and long spiral drilling head 4 footpaths, constitute slip casting thus and manage and protect groove, can manage and protect groove in even 1~3 slip casting that distributes of its circumference according to drilling rod bar footpath difference, slip casting is managed and protected groove and is run through whole long spiral press slurry drilling rod.The slip casting that each Grouting Pipe 2 penetrates separately from the drilling rod top is managed and protected in the groove, be fixed in slip casting by local spot welding and manage and protect in the groove.Each Grouting Pipe 2 all is welded with shower nozzle 5 near long spiral drilling head 4 one ends extrudes slurries to guarantee that Grouting Pipe 2 is not stopped up by earth smoothly in Grouting Pipe 2.During use, the utility model is installed on the long-spiral drilling machine, long screw drill rod is connected with the concrete pump truck, and the other end of Grouting Pipe 2 is connected with grouting equipment.Creep into according to construction requirement, Grouting Pipe 2 and shower nozzle 5 enter the stratum synchronously in company with the long screw auger body of rod 1 and long spiral drilling head 4 when creeping into, and stop to creep into when reaching design elevation when creeping into, and carry out slip casing by pressure by Grouting Pipe 2 and shower nozzle 5 this moment.After slip casting finished, the concrete pump truck was pressed into concrete, simultaneously the utility model was slowly extracted, then by former technology sinking reinforcing cage.After finishing this position construction, rig is moved to next position, carry out next working cycles.

Claims (4)

1. a novel long spiral press is starched drilling rod, comprise the long screw auger body of rod (1), long spiral drilling head (4), it is characterized in that: evenly be welded with backplate (6) and stiffener (7) towards periphery at the described long screw auger body of rod (1) and long spiral drilling head (4) footpath, constitute slip casting thus and manage and protect groove, manage and protect in its slip casting Grouting Pipe (2) is housed in the groove.
2. novel long spiral press slurry drilling rod according to claim 1 is characterized in that: be welded with shower nozzle (5) in described Grouting Pipe (2) near long spiral drilling head (4) one ends.
3. novel long spiral press slurry drilling rod according to claim 1, it is characterized in that: described Grouting Pipe (2) fixes on slip casting by the partial points solid welding and manages and protects in the groove.
4. novel long spiral press slurry drilling rod according to claim 1 is characterized in that: can manage and protect groove in even 1~3 slip casting that distributes of its circumference according to drilling rod bar footpath difference.
CNU2007200919350U 2007-09-21 2007-09-21 Long spiral mud jacking bore rod Expired - Fee Related CN201080793Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200919350U CN201080793Y (en) 2007-09-21 2007-09-21 Long spiral mud jacking bore rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200919350U CN201080793Y (en) 2007-09-21 2007-09-21 Long spiral mud jacking bore rod

Publications (1)

Publication Number Publication Date
CN201080793Y true CN201080793Y (en) 2008-07-02

Family

ID=39614467

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200919350U Expired - Fee Related CN201080793Y (en) 2007-09-21 2007-09-21 Long spiral mud jacking bore rod

Country Status (1)

Country Link
CN (1) CN201080793Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948768A (en) * 2017-04-05 2017-07-14 张腊琴 A kind of auger stem and steel pipe pile construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948768A (en) * 2017-04-05 2017-07-14 张腊琴 A kind of auger stem and steel pipe pile construction method

Similar Documents

Publication Publication Date Title
CN101173517A (en) Pile-pulling construction method
CN203452083U (en) Rotary expanding pile construction equipment and grout feeding device
KR101332848B1 (en) Method for constructing micro pile using deformed or screw steel pipe and pressure grouting
CN207436901U (en) A kind of rotary drilling rig
CN101614020A (en) Flexible bladder type anti-corrosive apparatus and use the anticorrosion stake and the job practices of this device
CN102535458A (en) Reinforced cement-soil anchor bolt and construction method thereof
CN108662281A (en) Conduit jacking and pipe jacking construction method
CN102839661A (en) Construction technology of reelingly stirring to eject anchor tube pile
CN201050303Y (en) Self-dumping cone type spiral anchor drill bit
CN104563126A (en) Rotary drill drilling cast-in-place pile construction method
RO134509A1 (en) Process and device for on-spot making a pile of variable diameter, decreasing in depth
CN101251020A (en) Subsection hole-drilling repeatedly slip-casting method
KR20100124028A (en) Construction method of lower end expanded type cast-in-place piles
CN102767337B (en) The construction method of a kind of sleeve type helical stake machine drill head and rid
CN201080793Y (en) Long spiral mud jacking bore rod
CN116291471A (en) Construction method and tunneling equipment for large-diameter vertical shaft of upper soft and lower hard stratum
CN110273413A (en) A kind of efficient construction method of prefabricated pile
KR100880365B1 (en) Excavating apparatus for excavating enlarged hole under the bottom of waters on which jacket facility structure is installed
CN110513534A (en) Municipal wastewater pipeline non-excavating construction method
CN103821137B (en) The construction method of guncreting pile at the bottom of the embedding rock of a kind of long auger, expansion
CN101153491A (en) Borehole wall-protection back cover and method for manufacturing large diameter hollow concrete pile
CN202989919U (en) Pressure-bearing water-sand-layer anchor rod mounting structure
CN107091053B (en) Underground engineering pile foundation pore-forming left and right displacement formula low clearance drilling machine
CN210530745U (en) Combined drilling bottom-expanding pile-planting system
CN102677724B (en) Mechanical steel sleeve installation device and mechanical steel sleeve installation method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080702