CN201024426Y - Pile cage for pulling raft pile - Google Patents

Pile cage for pulling raft pile Download PDF

Info

Publication number
CN201024426Y
CN201024426Y CNU2007200690394U CN200720069039U CN201024426Y CN 201024426 Y CN201024426 Y CN 201024426Y CN U2007200690394 U CNU2007200690394 U CN U2007200690394U CN 200720069039 U CN200720069039 U CN 200720069039U CN 201024426 Y CN201024426 Y CN 201024426Y
Authority
CN
China
Prior art keywords
pile
cage
bamboo
channel
mattress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200690394U
Other languages
Chinese (zh)
Inventor
曹文根
晏汇民
滕云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai City No4 Building Co Ltd
Original Assignee
Shanghai City No4 Building Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai City No4 Building Co Ltd filed Critical Shanghai City No4 Building Co Ltd
Priority to CNU2007200690394U priority Critical patent/CN201024426Y/en
Application granted granted Critical
Publication of CN201024426Y publication Critical patent/CN201024426Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a pile pulling cage of a bamboo-mattress pile, which comprises a channel steel and a lace bar and is characterized in that: two channel steels are parallel arranged with face-to-face notches, flush head parts, different tail parts in different lengths and two sides of the two channel steels are fixed by lace bars connected to form a pile cage; lace bars are spacedly erected to a front section of a tail part along the two sides of the channel steels and oblique lace bars are fixedly connected between two erected lace bars; two sides of the tail parts of the two channel steels are connected by the lace bars crossly and fixedly. The pile formation cage is formed by channel steels and lace bars, so the bamboo-mattress pile and a surrounding silt can be pulled out by the means of the friction of steel plates, silt and bamboo-mattress as long as the pile cage is sleeved at the position of the bamboo-mattress, thus solving the difficulty of poor anti-pulling performance of the bamboo mattress.

Description

Bamboo raft dowel pile pulling cage
Technical field
The utility model relates to the pile pulling cage that uses in a kind of building operations, especially a kind of pile pulling cage that is used for bamboo raft dowel.
Background technology
The international harbour affairs of international bus hub building, PORT OF SHANGHAI is located in port, the Gaoyang harbour that is built in 1825, and through several generations' transformation, reinforcing and use, geological conditions is quite complicated.When engineering is gone along with sb. to guard him construction, in underground discovery bamboo raft dowel (shown in Figure 1).This employing bamboo raft 1 replaces the vertical reinforcement of engineering piles, and galvanized wire 2 replaces the stirrup of engineering piles, and its inside is concrete 3.Because the tensile property of bamboo raft dowel is poor, common pile pulling means easily cause the bamboo raft dowel fracture.
Summary of the invention
The utility model is the pile pulling technology problem that will solve bamboo raft dowel, and a kind of pile pulling cage that is used for bamboo raft dowel is provided.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is as follows:
A kind of bamboo raft dowel pile pulling cage comprises channel-section steel, and lacing is characterized in: two channel-section steel recesses are arranged in parallel face-to-face, and head flushes, and afterbody has length difference, and both sides are with the fixedly connected pile cage of lacing.
Lacing is erect along the both sides of channel-section steel and is spaced to afterbody the last period, erects between the lacing at two and is fixedly connected with oblique lacing; The place, afterbody both sides of two channel-section steels connects with the lacing cross fixation.
The utility model is owing to adopted channel-section steel and a lacing composition stake cage, extractor is as long as be inserted in the bamboo raft dowel position with the stake cage, utilize steel plate, mud just bamboo raft dowel and the mud around it can be extracted, solved the difficult point of bamboo raft dowel tensile property difference with the frictional force of bamboo raft dowel.
Description of drawings
Fig. 1 is the schematic cross-section of bamboo raft dowel;
Fig. 2 is a structural representation of the present utility model;
Fig. 3 is the utility model schematic cross-section.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is further described.Should be understood that these embodiment only to be used to the utility model is described and be not used in the restriction scope of the present utility model.Should be understood that in addition those skilled in the art can make various changes or modifications the utility model after the content of having read the utility model instruction, these equivalent form of values fall within the application's appended claims institute restricted portion equally.
As Fig. 2, shown in 3, bamboo raft dowel pile pulling cage of the present utility model is made of channel-section steel 10 and lacing 20.Two channel-section steel 10 recesses are arranged in parallel face-to-face, and head flushes, and afterbody has length difference, and promptly channel-section steel 10 length are greater than the length of another root channel-section steel 10, and the both sides of two channel-section steels 10 are fixedly connected into the stake cage that can be inserted in bamboo raft dowel with lacing 20 welding.
Lacing 20 is erect along the both sides of channel-section steel 10 and is spaced to afterbody the last period, erects between the lacing 20 with oblique lacing 30 fixedly connected at two.The place, afterbody both sides of two channel-section steels 10 connects with oblique lacing 40 cross fixation.
When the utility model used, extractor inserted in the mud of bamboo raft dowel periphery with channel-section steel earlier and loosens the soil, and after plug for several times, bamboo raft dowel descends with the bonding force of the mud of periphery.Extractor utilizes the pile pulling cage to be inserted in the bamboo raft dowel position again, utilizes the principle of the frictional force of steel plate, mud and bamboo raft dowel, and bamboo raft dowel and the mud around it are extracted together.Can successfully solve the difficult point of bamboo raft dowel tensile property difference.

Claims (3)

1. a bamboo raft dowel pile pulling cage comprises channel-section steel (10), and lacing (20) is characterized in that, described two channel-section steels (10) recess is arranged in parallel face-to-face, and head flushes, and afterbody has length difference, and both sides are with the fixedly connected pile cage of lacing (20).
2. bamboo raft dowel pile pulling cage according to claim 1 is characterized in that, described lacing (20) is erect along the both sides of channel-section steel (10) and is spaced to afterbody the last period, erects between the lacings (20) at two and is fixedly connected with oblique lacing (30).
3. bamboo raft dowel pile pulling cage according to claim 1 is characterized in that, the place, afterbody both sides of described two channel-section steels (10) connects with oblique lacing (40) cross fixation.
CNU2007200690394U 2007-04-18 2007-04-18 Pile cage for pulling raft pile Expired - Fee Related CN201024426Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200690394U CN201024426Y (en) 2007-04-18 2007-04-18 Pile cage for pulling raft pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200690394U CN201024426Y (en) 2007-04-18 2007-04-18 Pile cage for pulling raft pile

Publications (1)

Publication Number Publication Date
CN201024426Y true CN201024426Y (en) 2008-02-20

Family

ID=39098280

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200690394U Expired - Fee Related CN201024426Y (en) 2007-04-18 2007-04-18 Pile cage for pulling raft pile

Country Status (1)

Country Link
CN (1) CN201024426Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383417A (en) * 2011-09-28 2012-03-21 马文旭 Combined framework pile
CN102587505A (en) * 2012-03-06 2012-07-18 中天建设集团有限公司 Wedge-type lacing bar connection node
CN105735318A (en) * 2016-03-25 2016-07-06 上海建工四建集团有限公司 Vibration sleeve pipe and application method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383417A (en) * 2011-09-28 2012-03-21 马文旭 Combined framework pile
CN102383417B (en) * 2011-09-28 2014-08-27 广州中煤江南基础工程公司 Combined framework pile
CN102587505A (en) * 2012-03-06 2012-07-18 中天建设集团有限公司 Wedge-type lacing bar connection node
CN102587505B (en) * 2012-03-06 2014-03-05 华南理工大学 Wedge-type lacing bar connection node
CN105735318A (en) * 2016-03-25 2016-07-06 上海建工四建集团有限公司 Vibration sleeve pipe and application method

Similar Documents

Publication Publication Date Title
CN102312481A (en) Reinforced concrete prefabricated member
CN206941608U (en) A kind of diaphram wall foundation pit supporting construction
CN103711135A (en) Anti-slide pile of jointed arch structure
CN210562157U (en) Post-grouting composite pile
CN201024426Y (en) Pile cage for pulling raft pile
CN202595728U (en) Prestressed concrete support pilling wall
CN205776250U (en) A kind of Double-row-piles Structure system being provided with dilazep anchor pattern
CN101666085B (en) Prefabricated part composite cement soil wall and construction method thereof
CN201232180Y (en) Novel sheet pile wall
CN102877473A (en) Skirt pile and soil coupled slid-resistant structure
CN207194228U (en) Wall is overlapped with overlapping the vertical openings connecting node of wall
CN212295682U (en) Novel precast concrete component hoisting point embedded part system
CN212248256U (en) Beam type connecting structure of front wall and rear pile combined support
CN205153144U (en) Joint construction of shear force corner portion and slant girder steel
CN214363527U (en) Administer miniature steel-pipe pile supporting construction of interpolation tendon of landslide
CN205000343U (en) Cross reinforced structure in landslide tunnel
CN109594464A (en) A kind of Wavelike steel webplate combined type shear connector
CN212248255U (en) Plate-type connecting structure for double-row supporting of front wall rear piles
CN110952787A (en) Novel precast concrete component hoisting point embedded part system
CN209162810U (en) H profile steel and reinforcing bar compound section SMW engineering method pilework
CN205742643U (en) Novel fabricated building connects node
CN208870054U (en) A kind of friction pile
CN207537868U (en) Wavelike steel webplate combined type shear connector
CN205894088U (en) Soil nail wall supporting construction that anchor pipe and channel -section steel stake combine
CN205421332U (en) Contrary coincide underground continuous wall that does of a core section of thick bamboo

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080220