CN200992706Y - Cast-in-place pile concrete casting-depth detecting device - Google Patents

Cast-in-place pile concrete casting-depth detecting device Download PDF

Info

Publication number
CN200992706Y
CN200992706Y CN 200620158672 CN200620158672U CN200992706Y CN 200992706 Y CN200992706 Y CN 200992706Y CN 200620158672 CN200620158672 CN 200620158672 CN 200620158672 U CN200620158672 U CN 200620158672U CN 200992706 Y CN200992706 Y CN 200992706Y
Authority
CN
China
Prior art keywords
cast
concrete
signal
backguy
place pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200620158672
Other languages
Chinese (zh)
Inventor
赵顺增
刘立
周聚光
曹淑萍
吴勇
杨伊静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Building Materials Academy CBMA
Original Assignee
China Building Materials Academy CBMA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Building Materials Academy CBMA filed Critical China Building Materials Academy CBMA
Priority to CN 200620158672 priority Critical patent/CN200992706Y/en
Application granted granted Critical
Publication of CN200992706Y publication Critical patent/CN200992706Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses a detecting device to detect the filling pile concrete casting depth, which comprises a detecting hammer (1), a measuring force sensor (2) and a signal receiving alarm device (3). The detecting hammer (1) is vertically arranged at underside of the concrete (10) cast in the filling pile hole (6) through a drawing line (11), the other end of the drawing line (11) connects firmly with the measuring force sensor (2), the upside of the measuring force sensor (2) connects firmly with a suspension fork (4) fixed on the ground through a drawing line (12); the signal receiving alarm device (3) is fixed on the ground and connects with the measuring force sensor (2) through a signal line (31). The device can save a lot of concrete, reduce the later period workload of filling pile, namely, improve the construction efficiency, reduce the construction fee, and also relieve the work intensity. The structure of the device is simple, the installation is easy, the operation is convenient, and is suitable to be spread.

Description

Cast-in-place pile concrete cast depth finding device
Technical field
The utility model relates to a kind of sniffer, specifically relates to a kind of sniffer of the cast-in-place pile concrete cast degree of depth.
Background technology
The cast-in-place pile concrete cast degree of depth is to survey by artificial portable weight at present, whether concrete builds is put in place, rely on operating personnel's feel and experience fully, for fear of the construction quality accident that produces the cast insufficient height, often excessive building, not only waste concrete in a large number, and cut the workload of stake after having increased.
The utility model content
The purpose of this utility model provides a kind ofly can accurately survey the device that cast-in-place pile concrete is built the degree of depth.
To achieve these goals, the utility model by the following technical solutions: a kind of cast-in-place pile concrete is built the depth finding device, and its characteristics are that it includes one and visits hammer, load cell and signal reception alarm; This spy hammer hangs down by a backguy and is located at the downside of the concrete surface of building in this hole for grout pile, and the other end of backguy and a load cell downside are affixed, and the upside of this load cell is affixed with the suspension that is fixed in ground by another backguy; Described signal receives alarm and rest on the ground; This signal receives alarm and is communicated with described load cell by a holding wire.
Above-mentioned spy hammer is for a kind of in cone-shaped, spherical, American football shape or the cylinder up and down, and the best is set to cone-shaped up and down.
Above-mentioned signal receives alarm and comprises shell body, is disposed with null-type bridge circuit, high-precision amplifying, A/D converter, cpu central processing unit, LCD display and a warning device in its housing; The cpu central processing unit output also connects a data storage, and is furnished with the RS232 interface, and the display location of LCD display is in this surface of shell; Wherein, the null-type bridge circuit input is connected with load cell by described holding wire, the analog signals of the stressed variation of load cell that reception is sent out by holding wire, through high-precision amplifying its signal is amplified again, amplifying signal is sent to A/D converter and converts analog signals to digital quantity signal, is delivered in the cpu central processing unit; Numerical value after cpu central processing unit is handled deposits in to data storage and by LCD display and shows; Cpu central processing unit instruction alarm activation is reported to the police.
Above-mentioned warning device is selected in display lamp, the phonetic alarm one or both combination for use, promptly provides to show that warning also sends audible alarm simultaneously.
When working, can not influence the accuracy that receives and send signal because of rocking in order to ensure load cell, the load cell connection is visited the backguy of hammering into shape and is all selected the low elasticity backguy for use with the backguy that load cell is connected with suspension.
Operating principle of the present utility model is:
According to Archimedes principle, the Media density difference, the buoyancy of its generation is also different, the spy hammer that this device adopts, the density of its material is greater than the coagulation upper density, and the volume of visiting hammer is certain value V, in use, to visit hammer probes in the cast-in-place concrete pile hole, the test degree of depth of visiting hammer is identical with the concrete absolute altitude of building, because have three kinds of media this moment in the priming concrete pile hole, be respectively concrete, mud and water, its density size is ρ successively Concrete>ρ Mud>ρ Water: concrete by perfusion cannula from stake hole bottom upwards the process of cast, the mud of bottom, stake hole, water can float over concrete top because density is littler than concrete, when water passes when visiting hammer, can produce V ρ to visiting hammer WaterBuoyancy, this moment, load cell can accurately detect this variation, and passed the signal to signal and receive alarm, display screen can show the variation of power value in the signal reception alarm, and with optical signal and voice signal prompting, same, when mud layer was hammered into shape by visiting, it was V ρ that the buoyancy of generation changes Mud, concrete arrives when visiting the hammer position, and it is V ρ that the buoyancy of generation changes Concrete, different signals can be passed to signal in good time and receive alarm, and signal reception alarm can be made corresponding prompt and warning, realizes the accurate control to the concreting absolute altitude.
The utility model adopts as above technical scheme, its advantage is as follows: 1, utilize concrete, the mud density value different with water, select the spy hammer of a kind of material density for use greater than concrete density, hang down be located in the cast-in-place concrete pile stake hole and the test degree of depth identical with the concrete absolute altitude of building, according to physical principle, can obtain concrete cast height exactly, the concrete degree of depth of building in the control priming concrete pile hole has solved and can't learn accurately in the prior art whether concrete builds the defective that puts in place; 2, because receiving alarm, signal can learn concrete cast height at any time, so, can save a large amount of concrete, reduced the workload that the later stage cuts, improved efficiency of construction; 3, this apparatus structure is simple, is easy to install, and is easy and simple to handle, do not need the operating personnel of professional skill, can also significantly reduce operating expenses and labour intensity simultaneously, overcome the disadvantage that needs artificial portable weight to survey in the prior art, is easy to apply.
Description of drawings
Fig. 1 is the utility model structural representation
Fig. 2 is the utility model user mode schematic diagram
Fig. 3 receives the alarm principle schematic for signal
The specific embodiment
As Fig. 1, shown in Figure 3, the utility model receives alarm 3 by spy hammer 1, load cell 2, signal and assembles, load cell 2 is hung on the suspension 4 that is fixed on ground by a backguy 11, probe 1 is hung at the below of load cell 2 by backguy 12, is connected with a holding wire 31 between load cell 2 and the signal reception alarm 3.Wherein, visit hammer 1 and can adopt spherical, American football shape, cylinder cone or go up shape such as lower cone, the best is set to lower cone; In order to guarantee to visit the application life of hammer 1, spy hammer 1 adopts stainless steel usually or the copper class is difficult for getting rusty or corrosion resistant metal material, also can select non-metallic material for use; It is the pulling force sensor of MCL-S150N that load cell 2 is selected the model of market sale for use;
Signal receives alarm 3 and comprises shell body, is disposed with null-type bridge circuit 32, high-precision amplifying 33, A/D converter 34, cpu central processing unit 35, LCD display 37 and a warning device 39 in its housing; Cpu central processing unit 35 outputs also connect a data storage 36, and are furnished with RS232 interface 38, and the display location of LCD display 37 is in this surface of shell; Wherein, null-type bridge circuit 32 inputs receive by holding wire 31 and transmit the analog signals of load cell 2 stressed variations, through high-precision amplifying 33 its signal is amplified, amplifying signal is sent to A/D converter 34 and converts digital quantity signal to by analog signals, delivers in the cpu central processing unit 35; Numerical value after cpu central processing unit 35 is handled is shown by LCD display 37; Cpu central processing unit 35 instruction warning devices 39 start reports to the police.
In above-mentioned data storage 36, can hold predefined experimental data, comprise the different densities value of water, mud, concrete etc.; Be provided with optical signal and/or voice suggestion signal in the warning device 39, the input of this warning device 39 is connected with the output of data storage 36, and different pieces of information is converted to optical signal or voice signal prompting, and optical signal can be selected light emitting diode for use; Voice signal can be selected loudspeaker for use, by the loudspeaker warning of sounding; It is the demonstration controller of MCK-Z series that the used LCD display 37 of the present invention is selected the model of market sale for use; Loudspeaker is selected the ventional loudspeakers of market sale for use, and the backguy of low elasticity is adopted in backguy 11,12, to guarantee to visit the degree of accuracy that hammer 1 is measured.
As Fig. 2, shown in Figure 3, the utility model in use, to visit hammer 1 earlier along probeing in the stake hole 6 of its concrete perfusion conduit 5 that in soil 13, inserts, the test degree of depth of visiting hammer 1 is identical with concreting absolute altitude 9, three kinds of media of general existence in stake hole 6, be respectively concrete 10, mud 7, water 8, its density size is ρ successively Concrete>ρ Mud>ρ Water: according to Archimedes principle, the Media density difference, the buoyancy of its generation is also different, pass through concrete perfusion conduit 5 from the process that upwards pour into a mould 6 bottoms, stake hole at concrete 10, the mud 7 of stake 6 bottoms, hole, water 8 are because density is littler than concrete 9, can float over concrete 10 tops,, can produce V ρ visiting hammer 1 when water 8 passes when visiting hammer 1 WaterBuoyancy, this moment, load cell 2 can accurately detect this variation, and signal is sent to signal by holding wire 31 receives in the alarm 3, receiving and be sent to high-precision amplifying 33 by the interior null-type bridge circuit of establishing 32 amplifies its signal, analog signals after the amplification is sent to A/D converter 34 and converts digital quantity signal to, be delivered to again in the cpu central processing unit 35, in have a predefined experimental data value data storage 36 its data are carried out record, show the variation of power values this moment again by LCD display 37; The warning device 39 that connects simultaneously starts reports to the police.
Equally, when mud layer hammered 1 into shape by visiting, it was V ρ that the buoyancy of generation changes Mud, concrete 10 arrives when visiting hammer 1 position, and it is V ρ that the buoyancy of generation changes Concrete, signal can send signal in good time to and receive alarm 3, makes prompting of corresponding optical signal and/or voice signal and warning, realizes the accurate control to concreting absolute altitude 9.

Claims (7)

1, a kind of cast-in-place pile concrete is built the depth finding device, it is characterized in that, it includes one and visits hammer (1), load cell (2) and signal reception alarm (3); This spy hammer (1) hangs down by a backguy (11) and is located at the downside on concrete (10) surface of building in this hole for grout pile (6), the other end of backguy (11) and a load cell (3) downside are affixed, and the upside of this load cell (3) is affixed with the suspension (4) that is fixed in ground by a backguy (12); Described signal receives alarm (3) and is arranged on the ground; This signal receives alarm (3) and is communicated with described load cell (2) by a holding wire (31).
2, cast-in-place pile concrete as claimed in claim 1 is built the depth finding device, it is characterized in that: described spy hammer (1) is for cone-shaped up and down.
3, cast-in-place pile concrete as claimed in claim 1 is built the depth finding device, it is characterized in that: described spy hammer (1) is for a kind of in spherical, American football shape or the cylinder.
4, build the depth finding device as each described cast-in-place pile concrete of claim 1-3, it is characterized in that: described signal receives alarm (3) and comprises a shell body, is disposed with null-type bridge circuit (32), high-precision amplifying (33), A/D converter (34), cpu central processing unit (35), a LCD display (37) and a warning device (39) in its housing; Cpu central processing unit (35) output also connects a data storage (36), and is furnished with RS232 interface (38); The display location of LCD display (37) is in this surface of shell; Described null-type bridge circuit (32) input receives and transmits the analog signals of the stressed variation of described load cell (2) by described holding wire (31), through high-precision amplifying (33) its signal is amplified, amplifying signal is sent to A/D converter (34) and converts digital quantity signal to by analog signals, delivers in the cpu central processing unit (35); Numerical value after cpu central processing unit (35) is handled deposits in to memory (36) and by LCD display (37) and shows; Cpu central processing unit (35) instruction warning device (39) starts reports to the police.
5, cast-in-place pile concrete as claimed in claim 4 is built the depth finding device, it is characterized in that: described warning device (39) is one or both combinations in display lamp or the phonetic alarm.
6, cast-in-place pile concrete as claimed in claim 5 is built the depth finding device, it is characterized in that: described backguy (11,12) is the low elasticity backguy.
7, build the depth finding device as each described cast-in-place pile concrete of claim 1-3, it is characterized in that: described backguy (11,12) is the low elasticity backguy.
CN 200620158672 2006-12-01 2006-12-01 Cast-in-place pile concrete casting-depth detecting device Expired - Lifetime CN200992706Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620158672 CN200992706Y (en) 2006-12-01 2006-12-01 Cast-in-place pile concrete casting-depth detecting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620158672 CN200992706Y (en) 2006-12-01 2006-12-01 Cast-in-place pile concrete casting-depth detecting device

Publications (1)

Publication Number Publication Date
CN200992706Y true CN200992706Y (en) 2007-12-19

Family

ID=38945783

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620158672 Expired - Lifetime CN200992706Y (en) 2006-12-01 2006-12-01 Cast-in-place pile concrete casting-depth detecting device

Country Status (1)

Country Link
CN (1) CN200992706Y (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234094A (en) * 2014-07-23 2014-12-24 郑州市市政工程总公司 Underwater concrete spouting-height detecting device
CN105089083A (en) * 2015-07-16 2015-11-25 路桥华祥国际工程有限公司 Warning device for leakage of slurry in foundation construction of bridge pile
CN105928489A (en) * 2016-06-14 2016-09-07 山东大学 Handheld underwater grouting pile top-surface elevation control early-warning device and method
CN106545329A (en) * 2016-11-09 2017-03-29 武汉长盛工程检测技术开发有限公司 Drilled pile hole quality detection means and method
CN106638719A (en) * 2016-10-20 2017-05-10 武汉长盛工程检测技术开发有限公司 Automatic cast-in-place pile quality monitoring and controlling device and method
CN109556769A (en) * 2018-12-24 2019-04-02 成都尚德铁科智能科技有限公司 A kind of level type force cell device of slipping through the net for plastic concrete
CN110195448A (en) * 2019-07-05 2019-09-03 河南云平环保科技有限公司 Bored concrete pile probe device and stake top height and stake diameter method for real-time measurement
CN112127364A (en) * 2020-10-14 2020-12-25 广州市市政集团有限公司 Pile head over-filling monitoring device for cast-in-place pile
CN113882383A (en) * 2021-08-17 2022-01-04 山东大学 Device and method for controlling concrete pouring height of filtering and vibrating type bored pile

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234094A (en) * 2014-07-23 2014-12-24 郑州市市政工程总公司 Underwater concrete spouting-height detecting device
CN104234094B (en) * 2014-07-23 2016-08-24 郑州市市政工程总公司 Underwater gliders height detecting device
CN105089083A (en) * 2015-07-16 2015-11-25 路桥华祥国际工程有限公司 Warning device for leakage of slurry in foundation construction of bridge pile
CN105928489B (en) * 2016-06-14 2018-05-25 山东大学 A kind of handheld water bottom fills stake elevation of top surface control prior-warning device and method
CN105928489A (en) * 2016-06-14 2016-09-07 山东大学 Handheld underwater grouting pile top-surface elevation control early-warning device and method
CN106638719A (en) * 2016-10-20 2017-05-10 武汉长盛工程检测技术开发有限公司 Automatic cast-in-place pile quality monitoring and controlling device and method
CN106545329A (en) * 2016-11-09 2017-03-29 武汉长盛工程检测技术开发有限公司 Drilled pile hole quality detection means and method
CN106545329B (en) * 2016-11-09 2019-04-23 武汉长盛工程检测技术开发有限公司 Drilled pile hole quality detection device and method
CN109556769A (en) * 2018-12-24 2019-04-02 成都尚德铁科智能科技有限公司 A kind of level type force cell device of slipping through the net for plastic concrete
CN110195448A (en) * 2019-07-05 2019-09-03 河南云平环保科技有限公司 Bored concrete pile probe device and stake top height and stake diameter method for real-time measurement
CN110195448B (en) * 2019-07-05 2024-01-19 河南云平环保科技有限公司 Probe rod device for cast-in-place pile and pile top height and pile diameter real-time measurement method
CN112127364A (en) * 2020-10-14 2020-12-25 广州市市政集团有限公司 Pile head over-filling monitoring device for cast-in-place pile
CN113882383A (en) * 2021-08-17 2022-01-04 山东大学 Device and method for controlling concrete pouring height of filtering and vibrating type bored pile

Similar Documents

Publication Publication Date Title
CN200992706Y (en) Cast-in-place pile concrete casting-depth detecting device
CN101165278A (en) Grout pile concrete station ultrasonic wave checking method and checking system
CN107675734B (en) A kind of underwater directional vehicle construction dynamic monitoring method
CN204919631U (en) Automatic monitoring underwater concrete fills device of elevation
CN205898118U (en) River course section surveying instrument
CN212674018U (en) Concrete filling pile sediment measuring device
CN203053483U (en) Sludge detecting instrument
CN201392303Y (en) On-line electronic hydrometer
CN202255522U (en) Irregular object volume measurement device
CN206945698U (en) A kind of instrument for detecting concrete vibrating density
CN203271724U (en) Multifunctional hole detector
CN206095356U (en) Differential pressure water level measuring apparatu
CN202583040U (en) Rock ore porosity measuring instrument
CN209459635U (en) A kind of water level monitoring device for hydrogeological test
CN204240908U (en) Sediment thickness survey instrument at the bottom of priming concrete pile hole
CN206583430U (en) Cast-in-situ bored pile sediment thickness detection device
CN109695261A (en) Underwater gliders interface pressure difference monitoring device and method
CN201751537U (en) Monitoring and early-warning device for tunnel water-burst mud-irruption sudden geologic hazards
CN209293082U (en) A kind of influx height detector of cast-in-situ bored pile
CN212845390U (en) Device for measuring compactness of reinforced concrete under vibration condition
CN204238266U (en) For detecting the combination plummet of stake holes sediment thickness
CN101561268A (en) Apparatus for measuring inclination angle of inclined plane
CN202372425U (en) Testing device for submerged unit weight
CN207688934U (en) A kind of portable field multiparameter measuring device
CN210342019U (en) Device for measuring thickness of sediment at base of cast-in-situ bored pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20071219

EXPY Termination of patent right or utility model