CN200992509Y - Water treatment bamboo filler and its arrangement structure - Google Patents

Water treatment bamboo filler and its arrangement structure Download PDF

Info

Publication number
CN200992509Y
CN200992509Y CNU2006201419121U CN200620141912U CN200992509Y CN 200992509 Y CN200992509 Y CN 200992509Y CN U2006201419121 U CNU2006201419121 U CN U2006201419121U CN 200620141912 U CN200620141912 U CN 200620141912U CN 200992509 Y CN200992509 Y CN 200992509Y
Authority
CN
China
Prior art keywords
bamboo
cross tube
backstay
sheer pole
filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2006201419121U
Other languages
Chinese (zh)
Inventor
罗安程
贾华清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG HONGCHENG ENVIRONMENT ENGINEERING Co Ltd
Original Assignee
ZHEJIANG HONGCHENG ENVIRONMENT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG HONGCHENG ENVIRONMENT ENGINEERING Co Ltd filed Critical ZHEJIANG HONGCHENG ENVIRONMENT ENGINEERING Co Ltd
Priority to CNU2006201419121U priority Critical patent/CN200992509Y/en
Application granted granted Critical
Publication of CN200992509Y publication Critical patent/CN200992509Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W10/00Technologies for wastewater treatment
    • Y02W10/10Biological treatment of water, waste water, or sewage

Landscapes

  • Biological Treatment Of Waste Water (AREA)

Abstract

The utility model relates the bamboo filling for water treatment and the distribution structure. Said bamboo filling is consisted by strip bamboo sheets distributed and fixed in the connection fittings one by one. The connection fittings are soft cords and the neighboring bamboo sheets have clearances. The structure of the utility model is: an upper cross-bar is equipped in the flat nearing the water level and a lower cross-bar is equipped in the flat nearing water bottom. Both the upper and lower cross bars, which are equipped in the steel location bar, are respectively parallel with the water level. The neighboring upper cross bars are almost parallel, so are the lower cross bars. Said bamboo filling continuously distributed between the neighboring upper and lower cross bars and said location bar is in the water treatment pond. The utility model provide the environmental protection filling which has the characteristics of low cost, easy to transport and store, simple installation, seldom blockage and strong capacity of resisting impact load, with large effective ratio area.

Description

A kind of water treatment bamboo filler and arrangement thereof
(1) technical field
What the utility model related to that a kind of water, waste water, sewage disposal uses is the filler that main raw material(s) is made with the bamboo, and in waste disposal plant arrangement.
(2) background technology
The utility model relates to the filler of using in all kinds of water treatment device.Existing filler mainly is that the fibrous material with synthetic such as plastics is that material is made, and is rounded, and its biofilm is slow, shortcoming such as even inadequately distributes.It is the filler of water treatment that CN02215007 discloses a kind of hollow ball with bamboo weaving system, this bamboo filler, though and the affinity between the microorganism strong, have the fast advantage of biofilm, but complex manufacturing technology, be difficult for transportation, storage space is big, the cost of manufacture height, must make by hand, making labour intensity is big, and the available ratio surface is little, shortcoming such as during mounting cost.
(3) summary of the invention
The purpose of this utility model is to solve bamboo filler complex manufacturing technology in the prior art, is difficult for transportation, and storage space is big, the cost of manufacture height, and it is big to make labour intensity, and the available ratio surface is little, problem such as during mounting cost.It is the new packing and the arrangement thereof of material with the bamboo that the utility model will provide a kind of, guarantees to make that the making adult is low, and can realize making automatization when making with use.Transport and deposit conveniently, improve its available ratio surface, be convenient to install.
For achieving the above object, the utility model adopts following technical scheme:
A kind of water treatment bamboo filler, described bamboo filler are arranged successively by the strip bamboo chip and are fixed on the web member, and described web member is a tightrope, leaves the gap between the adjacent bamboo chip.The shape of bamboo wood material can be a square shape sheet, and its cross section is square; Also can be strand shape, its cross section is a garden shape.
Described tightrope is nylon rope, PVC rope, caprone cable, the rope made of hemp or wire etc.The tightrope of every fixation with bamboo splints has two places at least.
Filler is to be main material by long strip shape bamboo wood material, is made into different shape, is fixed on tightrope and other upholder.
Preferably be parallel to each other to arrange successively and be fixed on the web member with the bamboo chip of strip.
Leave the gap between the further described bamboo chip.It is characterized in that the gap of staying between the described bamboo chip is 1~10 millimeter.
Further, described bamboo chip is wide to be 1~50 millimeter, preferred 5~50 millimeters.
Further more described bamboo chip is roughly wide, is convenient to suitability for industrialized production like this.
A kind of water treatment described in the utility model with the arrangement of bamboo filler is: on the close plane of the water surface of water treating pond cross tube is set under water, near on the plane of water-bed face sheer pole is being set, described cross tube two ends, the sheer pole two ends are fixed on the inflexible backstay respectively, cross tube, sheer pole is parallel with horizontal plane respectively, adjacent cross tube, the sheer pole almost parallel, almost parallel between the adjacent cross tube, almost parallel between the adjacent sheer pole, described bamboo filler is at adjacent cross tube, the sheer pole continuity is walked and is arranged, and described backstay is positioned in the water treating pond.
The bamboo filler being walked to arrange in the continuity of adjacent cross tube, sheer pole and can enlarge contacting between current, air-flow and filler.Backstay is selected the better rigidity material preparation usually for use, makes as metallic substance.
The utility model recommends described cross tube, sheer pole all parallel with horizontal plane.
Further, described backstay is divided into the last backstay of fixing cross tube and the fixing following backstay of sheer pole, described upward backstay, following backstay are parallel to each other, and be separately fixed on the pool wall of described treating pond, described cross tube arranges that perpendicular to last backstay described sheer pole is arranged perpendicular to following backstay.
As preferred case of the present utility model, described cross tube is that the hawser, the sheer pole that are stretched in backstay Zhi Inter are the hawser that is stretched in down backstay Zhi Inter.Cross tube and sheer pole also can adopt rigid rod, and rigid rod is fixed on the corresponding backstay.
Further again, adjacent cross tube and sheer pole staggered arrangement, described bamboo filler removably is fastened on the cross tube by mounting block, and the bamboo filler removably is fastened on the sheer pole by mounting block simultaneously.The bamboo filler has certain weight, if fix without mounting block, slippage goes out cross tube or sheer pole easily in water.
Further, described backstay, following backstay and cross tube, the sheer pole gone up arranged continuously, constitute grid structure, all be furnished with the bamboo filler between described every adjacent cross tube, each comfortable adjacent cross tube of described bamboo filler, sheer pole continuity are walked and are arranged.Water treating pond is generally bigger, so when the bamboo filler is arranged, the bamboo filler that many rows' continuities run in the guide cross tube, sheer pole is set usually works simultaneously.
The beneficial effects of the utility model are: but 1. make automatization.2. it is little to deposit shared place.3. convenient transportation.4. it is convenient to install.5. be difficult for when using stopping up.6. capacity of resisting impact load is strong.And the affinity between the microorganism strong, biofilm is fast.
(4) description of drawings
Fig. 1 is a bamboo filler synoptic diagram of the present utility model;
Fig. 2 is the fixedly synoptic diagram of strip bamboo chip of the utility model bamboo filler tightrope;
Fig. 3 is the utility model bamboo filler arrangement vertical view;
Fig. 4 is the utility model bamboo filler arrangement under water schematic side view;
Fig. 5 is that the utility model bamboo filler is walked the arrangement synoptic diagram of arranging with cross tube, sheer pole continuity under water.
(5) embodiment
Below in conjunction with accompanying drawing the utility model is further described, but technical parameter related in the scheme can not be interpreted as restriction of the present utility model.
Embodiment 1
The water treatment making of bamboo filler (6)
Accompanying drawing 2 in conjunction with the accompanying drawings 1,, arrange successively the strip bamboo chip (1) of 90-100 cm long is parallel, bamboo chip is wide 50 millimeters, with nylon rope (2) that the strip fixation with bamboo splints is in a row, the two ends of bamboo chip and bamboo chip and three places, middle part are connected and fixed by nylon rope respectively, leave gap (3) between the adjacent bamboo chip, about 15~20 millimeters of described gap.The length that the bamboo filler is made can determine that this length will make the bamboo filler walk and arrange in adjacent cross tube, sheer pole continuity according to the actual needs of water treating pond, and bamboo chip is made into square shape sheet, and its cross section is a rectangle.Such bamboo filler be difficult for to stop up in use, foldablely deposits and transports.Do not have overlapping between the bamboo chip, can utilize all surfaces of bamboo wood material, the available ratio surface is big.
Embodiment 2
The bamboo filler arranges during water treatment
During water treatment, make water treatment bamboo filler with embodiment 1, arrange by following mode: but the both sides pool wall below the water treating pond water surface is established the upper support frame and the lower supporting frame of load-bearing respectively, the supporting surface of upper support frame and lower supporting frame is all parallel with horizontal plane, again with some upward parallel distributions of backstay (7), and be fixed on the upper support frame, to descend on the corresponding one by one lower supporting frame that distributes and be fixed on of backstay (8) and last backstay, the adjacent distance that goes up between the backstay and leave strip bamboo chip length in the bamboo filler of being wider than embodiment 1 under adjacent between the backstay is set up, sheer pole.
Set up after the backstay, be stretched in one by one on backstay and fixed down the bar with thicker hawser or other rigid rod respectively, form cross tube (5) respectively, sheer pole (4): near the water surface below the water treating pond water surface is cross tube, planar near water-bed face below the water treating pond water surface is a sheer pole, cross tube, parallel between parallel with the horizontal plane respectively adjacent cross tube of sheer pole, parallel between the adjacent sheer pole, all cross tubes at grade, all sheer poles at grade, adjacent cross tube and staggered arrangement parallel with sheer pole, described bamboo filler is at adjacent cross tube, the sheer pole continuity is walked and is arranged, and sees Fig. 5.Described bamboo filler has 3 rows, walks at adjacent cross tube, sheer pole respectively and arranges, and sees Fig. 3.
And described bamboo filler removably is fastened on the cross tube, by mounting block simultaneously.Removably be fastened on the sheer pole by mounting block.
This arrangement guarantees can install easily when the bamboo filler uses, and working efficiency improves greatly, current or (with) aeration gas flow and filler contact surface be big, can effectively improve water treatment efficiency.

Claims (10)

1. water treatment bamboo filler is characterized in that described bamboo filler is arranged successively by the strip bamboo chip to be fixed on the web member that described web member is a tightrope, leaves the gap between the adjacent bamboo chip.
2. water treatment bamboo filler as claimed in claim 1 is characterized in that described tightrope is nylon rope, caprone cable, PVC rope, the rope made of hemp or wire.
3. water treatment bamboo filler as claimed in claim 2 is characterized in that described bamboo chip is parallel to each other to arrange successively to be fixed on the web member.
4. water treatment bamboo filler as claimed in claim 3 is characterized in that the gap of staying between the described bamboo chip is 1~20 millimeter, and described bamboo chip is wide 5~50 millimeters, and described bamboo chip is roughly wide.
5. a water treatment as claimed in claim 1 is with the arrangement of bamboo filler, it is characterized in that described structure is: on the close plane of the water surface of water treating pond, cross tube is set under water, near on the plane of water-bed face sheer pole is being set, described cross tube two ends, the sheer pole two ends are fixed on the inflexible backstay respectively, cross tube, sheer pole is parallel with horizontal plane respectively, adjacent cross tube and sheer pole almost parallel, almost parallel between the adjacent cross tube, almost parallel between the adjacent sheer pole, described bamboo filler is at adjacent cross tube, the sheer pole continuity is walked and is arranged, and described backstay is positioned in the water treating pond.
6. water treatment as claimed in claim 5 is characterized in that with the arrangement of bamboo filler described cross tube, sheer pole are all parallel with horizontal plane.
7. the water treatment as claimed in claim 6 arrangement of bamboo filler, it is characterized in that, described backstay is divided into the last backstay of fixing cross tube and the fixing following backstay of sheer pole, described upward backstay, following backstay are parallel to each other, and be separately fixed on the pool wall of described treating pond, described cross tube arranges that perpendicular to last backstay described sheer pole is arranged perpendicular to following backstay.
8. the water treatment as claimed in claim 7 arrangement of bamboo filler, it is characterized in that described cross tube is that hawser, the sheer pole that is stretched in backstay Zhi Inter is the hawser that is stretched in down backstay Zhi Inter, cross tube and sheer pole also can adopt rigid rod, and rigid rod is fixed on the corresponding backstay.
9. the water treatment as claimed in claim 7 arrangement of bamboo filler, it is characterized in that adjacent cross tube and sheer pole staggered arrangement, described bamboo filler removably is fastened on the cross tube by mounting block, and the bamboo filler removably is fastened on the sheer pole by mounting block simultaneously.
10. the water treatment as claimed in claim 7 arrangement of bamboo filler, it is characterized in that described last backstay, descend backstay and cross tube, sheer pole to arrange continuously, constitute grid structure, all be furnished with the bamboo filler between described every adjacent cross tube, each comfortable adjacent cross tube of described bamboo filler, sheer pole continuity are walked and are arranged.
CNU2006201419121U 2006-12-31 2006-12-31 Water treatment bamboo filler and its arrangement structure Expired - Lifetime CN200992509Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2006201419121U CN200992509Y (en) 2006-12-31 2006-12-31 Water treatment bamboo filler and its arrangement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2006201419121U CN200992509Y (en) 2006-12-31 2006-12-31 Water treatment bamboo filler and its arrangement structure

Publications (1)

Publication Number Publication Date
CN200992509Y true CN200992509Y (en) 2007-12-19

Family

ID=38945584

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2006201419121U Expired - Lifetime CN200992509Y (en) 2006-12-31 2006-12-31 Water treatment bamboo filler and its arrangement structure

Country Status (1)

Country Link
CN (1) CN200992509Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107352639A (en) * 2017-09-05 2017-11-17 苏州淡林环境科技有限公司 One kind exposes oneself air supporting suspension type biologic packing material system
CN107399809A (en) * 2017-09-05 2017-11-28 苏州淡林环境科技有限公司 A kind of efficiently diaphragm suspension soft quick-mount system entirely

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107352639A (en) * 2017-09-05 2017-11-17 苏州淡林环境科技有限公司 One kind exposes oneself air supporting suspension type biologic packing material system
CN107399809A (en) * 2017-09-05 2017-11-28 苏州淡林环境科技有限公司 A kind of efficiently diaphragm suspension soft quick-mount system entirely

Similar Documents

Publication Publication Date Title
CN201674877U (en) Combined copper alloy netting cage
CN200992509Y (en) Water treatment bamboo filler and its arrangement structure
CN107453689A (en) A kind of modularization floatation type photovoltaic array
CN205754137U (en) Fish belly type many ropes photovoltaic bracket
CN110845014A (en) Artificial floating island
CN106533334A (en) Novel single-layer parallel suspension cable photovoltaic support system
CN215957401U (en) Sawtooth type multi-span greenhouse for hills
CN204152046U (en) Cast-in-place concrete hollow building roof structure
CN211313062U (en) Reed board
CN212050746U (en) Artificial floating island
CN208046507U (en) A kind of cable truss formula flexible photovoltaic carrier unit and photovoltaic bracket
KR20120044815A (en) Belt type glass fiber reinforcements and retaining walls using the same
KR20130003008U (en) Belt type glass fiber reinforcements and retaining walls using the same
CN200964645Y (en) Large span large cantilever roof oblique-pulling type double-layer prestress steel grid roof
CN109750631A (en) A kind of underwater Ecological Retaining Wall
CN102027865B (en) Environmental protection energy-saving type combined greenhouse
CN206706849U (en) A kind of cushion cap foundation discharge structure
CN216983150U (en) Square net cage of high density polyethylene and connecting piece thereof
CN2709521Y (en) Vertical string hanging sand-protecting barrier of 3D foldable connecting wide-strip polymer net piece
CN211497081U (en) Three-dimensional ecological plant filler
JP4792579B2 (en) Draft run-up equipment in drainage channel of paddy field
CN108365798A (en) A kind of cable truss formula flexible photovoltaic carrier unit and photovoltaic bracket
CN212129226U (en) Pin-connected panel utility tunnel
CN217446265U (en) Modularized oyster cultivation buoyant raft
CN201275425Y (en) Three-dimensional X-shaped evaporation rack for evaporating brine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20071219

EXPY Termination of patent right or utility model