CN200971471Y - Tie rod cable system with cable hole - Google Patents

Tie rod cable system with cable hole Download PDF

Info

Publication number
CN200971471Y
CN200971471Y CN 200620078098 CN200620078098U CN200971471Y CN 200971471 Y CN200971471 Y CN 200971471Y CN 200620078098 CN200620078098 CN 200620078098 CN 200620078098 U CN200620078098 U CN 200620078098U CN 200971471 Y CN200971471 Y CN 200971471Y
Authority
CN
China
Prior art keywords
steel strand
rope
separating ring
wire separating
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200620078098
Other languages
Chinese (zh)
Inventor
刘征宇
柏国清
祖祥胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
VSL ENGINEERING Co Ltd
Original Assignee
VSL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by VSL ENGINEERING Co Ltd filed Critical VSL ENGINEERING Co Ltd
Priority to CN 200620078098 priority Critical patent/CN200971471Y/en
Application granted granted Critical
Publication of CN200971471Y publication Critical patent/CN200971471Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Ropes Or Cables (AREA)

Abstract

A tie-bar cable device with a dividing ring is characterized in that a dividing ring is placed at the position of the supporting bracket in the coating pipe of the tie-bar cable; the dividing ring is of disc-type; a plurality of steel stranded wire holes for the steel stranded wire to go through are positioned on the dividing ring and the steel stranded wire holes are separated with each, of the same number with the steel stranded wire and with the axis parallel to the axis of the coating pipe; each steel stranded wire goes through the corresponding steel stranded wire on the dividing ring to form a parallel and independent relation between the steel stranded wires. The utility model can ensure that the steel stranded wires are independent to each other, which is convenient for the installation, pulling, monitoring and change of single steel stranded wire to avoid horizontal expansion and disfiguration of the HDPE coating pipe at the position of the supporting point of the supporting bracket.

Description

The tie bar cable system of band wire separating ring
Technical field:
The utility model relates to and is applied to concrete or steel work, as the tie bar cable system in the steel tube arch structural bridge.
Background technology:
Arch bridge has long applicating history in bridge engineering, be to adopt a kind of very widely structural shape in the bridge.And the tie-rod rope is the key structure unit that is bearing by dead load and the caused horizontal thrust of mobile load in arch bridge, is the life place of bridge engineering.Along with modern bridge to stride greatly the footpath continuous development, the specification that is applied to the tie-rod rope in the arch bridge is also increasing.According to prior art, the steel strand tie-rod rope that is adopted is to cohere steel strand and the tie-rod cable anchorage is made by steel strand finished product rope or many nothings, and cable body wherein partly is to make by wearing the high strength low relaxed prestress steel strand bundle in the HDPE outer tube.The weight of cable body itself is that the Support bracket by per 3~5 meters intervals supports.
This form of structure has following defective and inconvenience in the construction of tie-rod rope and working service process:
1,, when passing the HDPE outer tube, steel strand can not guarantee between each root steel strand and be arranged in parallel that phase mutual interference friction also just can't realize single tendon stretch between each steel strand, can make troubles the increase construction cost to construction independent for the tie-rod rope.
2, for the bigger tie-rod rope of specification, even stretch-draw is to the proof stress of tie-rod rope, because the weight of self, will certainly cause the interior steel strand mutual extrusion of pipeline, overlapping, in this case, not only can't carry out single tendon stretch, also can't carry out the replacing of single steel strand in the future, bring very inconvenience for the maintenance of bridge in construction and the use.
3, because the contact surface of the HDPE outer tube of passive Support bracket and tie-rod rope is less; can cause the distortion of the Support Position HDPE of place outer tube generation lateral expansion; influence the attractive in appearance of construction and cable body; even cause damage; make tie-rod rope part lose the protection of outer tube, have influence on the application life of tie-rod rope.
The utility model content:
The utility model is for avoiding above-mentioned existing in prior technology weak point, a kind of tie bar cable system with wire separating ring is provided, separate to guarantee each root steel strand, be convenient to installation, stretch-draw, monitoring and the replacing of single steel strand, avoid the HDPE outer tube lateral expansion distortion to take place at place, Support bracket Support Position.
The utility model is that the technical scheme that the technical solution problem is adopted is:
The tie bar cable system of the utility model band wire separating ring, its design feature is in the outer tube of tie-rod rope, be positioned at place, Support bracket position wire separating ring is set, wire separating ring is a disc-shaped component, the steel strand through hole that is used for steel strand that wire separating ring has is separate, that equate with the quantity of steel strand, axis all parallels with the axis of outer tube, every steel strand independently are located in the steel strand through hole of wire separating ring corresponding position, form parallel and separate between each root steel strand.
The design feature of the tie bar cable system of the utility model band wire separating ring also is the periphery of wire separating ring, and a positioning rope hole and two guide rail rope holes are set respectively on the position triangular in shape.
Compared with the prior art, the beneficial effects of the utility model are embodied in:
1, the utility model utilizes wire separating ring to make in the tie-rod rope each root steel strand keep independence and be arranged in parallel, can realize single tendon stretch, controls the uniformity of each root steel strand Suo Li of every Shu Suozhong better, also is convenient to construction, saves construction cost.
2, the wire separating ring that is provided with at interval in the utility model makes that each root steel strand is spaced from each other in the tie-rod rope, not overlapped, mutual extrusion not makes bridge very convenient in the future working service, promptly can carry out monitoring and the replacing of Suo Li to any steel strand under the situation that does not influence traffic.
3, each wire separating ring is arranged on the Support bracket in the utility model, improved the rigidity of the tie-rod rope Support Position HDPE of place outer tube, effectively avoided the lateral expansion distortion of HDPE outer tube, the convenient construction of tie-rod rope, safeguard the attractive in appearance of tie-rod rope, guaranteed the ordinary life of outer tube.
4, the utility model can make construction equipment lighting, miniaturization, is convenient to construction, monitoring, safeguards, has saved human and material resources and engineering time, reduces construction and use cost.
Description of drawings:
Fig. 1 is the utility model wire separating ring end face structure schematic diagram.
Fig. 2 is the A-A cross-sectional schematic of Fig. 1.
Fig. 3 is an arc junction plate structural representation.
Fig. 4 is Fig. 3 plan structure schematic diagram.
Fig. 5 is the utility model wire separating ring, positioning rope and steel strand pull rope assembling schematic diagram.
Fig. 6 is by locating piece location structure schematic diagram between each wire separating ring of the utility model and the positioning rope.
Fig. 7 is the utility model outer tube scheme of installation.
Fig. 8 is Fig. 7 section structure schematic diagram.
Fig. 9 is that the utility model is introduced hoist engine wire rope and guide rail rope form attitude schematic diagram in outer tube.
Figure 10 pulls the wire separating ring view into for the utility model in outer tube.
Figure 11 makes wire separating ring schematic diagram in place in outer tube for the utility model adjustment and stationary positioned rope.
Figure 12 is Figure 11 section structure schematic diagram.
Figure 13 brings hoist engine wire rope schematic diagram into for the utility model utilizes pull rope.
Figure 14 brings the steel strand schematic diagram into for the utility model utilizes the hoist engine wire rope.
Number in the figure: 1 outer tube, 2 Support brackets, 3 wire separating rings, 4 steel strand, 5 steel strand through holes, 6 positioning rope holes, 7 guide rail rope holes, 8 positioning ropes, 9 steel strand pull ropes, 10 strops, 11 arc junction plates, 12 hoist engine wire rope, 13 guide rail ropes, 14 hoist engines, 15 locating pieces.
Below also the utility model is described in further detail in conjunction with the accompanying drawings by the specific embodiment.
The specific embodiment:
Referring to Fig. 1, Fig. 2 and Figure 14, the tie bar cable system of band wire separating ring is in the outer tube 1 of tie-rod rope in the present embodiment, is positioned at place, Support bracket 2 positions wire separating ring 3 is set.Fig. 1, shown in Figure 2, wire separating ring 3 is a disc-shaped component, wire separating ring 3 has each steel strand through hole 5 separate, that equate with the quantity of steel strand 4, that axis all parallels with the outer tube axis, every steel strand 4 independently are located in the steel strand through hole 5 of wire separating ring 3 corresponding positions, form parallel and separate between each root steel strand 4.For the ease of construction, should a positioning rope hole 6 and two guide rail rope holes 7 be set on the position triangular in shape respectively in the periphery of wire separating ring 3.
Concrete construction is carried out as follows:
1, runs through positioning rope hole 6 on each wire separating ring 3 with a positioning rope 8, form the series connection (shown in Figure 5) of each wire separating ring 3 on positioning rope 8, and in outer tube 1, set the requirement of spacing according to adjacent wire separating ring 3, each wire separating ring 3 is positioned (shown in Figure 6) by the locating piece 15 that is positioned at its both sides on positioning rope 8;
2, in the steel strand through hole 5 of wire separating ring 3,, introduce each root only steel strand pull rope 9 (Fig. 5, shown in Figure 6) mutually according to the threading setting of each root steel strand 4 in each wire separating ring 3;
3, in outer tube 1, reserve a strop 10 (shown in Figure 7), and with outer tube 1 installation in position (Fig. 7, shown in Figure 8) on Support bracket 2, Support bracket 2 is the roller carriage; Adopt Fig. 3, arc junction plate 11 shown in Figure 4, as Fig. 3, Fig. 4 and shown in Figure 9, side at arc junction plate 11 connects strop 10, opposite side at its plate connects hoist engine wire rope 12 and two guide rail ropes 13 respectively, by traction to strop 10, use hoist engine wire rope 12 and two guide rail ropes 13 to run through the two ends of outer tube 1, shed strop 10 subsequently;
4, two guide rail ropes 13 are introduced guide rail rope hole 7 on the correspondence position on each wire separating ring 3 respectively, guide rail rope 13 is tightened wire separating ring 3 and guide rail rope 13 sliding fits (shown in Figure 10) at the two ends of its rope;
5, under the traction of hoist engine 14, with guide rail rope 13 is directive slide track, to pull in the outer tube 1 by each wire separating ring 3 of positioning rope 8 series connection by hoist engine wire rope 12, then at the two ends of outer tube 1 tensioning positioning rope 8, the spacing that each wire separating ring 3 is determined by positioning rope 8 is in Support bracket 2 positions (Figure 10, Figure 11 and shown in Figure 12) in place in outer tube 1;
6, successively each root steel strand 4 is connected correspondingly the end of each pull rope 9, at first hoist engine wire rope 12 is introduced (shown in Figure 13) by pull rope 9, be connected with steel strand 4 on the correspondence position by the hoist engine wire rope of introducing 12 again, draw by 12 pairs of steel strand 4 of hoist engine wire rope by hoist engine 14, thereby each root steel strand 4 is introduced in the steel strand through hole 5 corresponding on the wire separating ring 3 (shown in Figure 14) successively;
7, by hoist engine 14 for the steel strand 4 single Suo Li that apply one by one, until reaching final Suo Li requirement.
In concrete the enforcement, the setting of each member comprises:
Outer tube 1: adopt the HDPE pipe, can be pulled into smoothly in the outer tube 1 in order to guarantee wire separating ring 3, external diameter that can wire separating ring 3 is set to the little 4~6mm of internal diameter than outer tube 1.
Wire separating ring 3: drawing materials is HDPE.
Positioning rope 8: drawing materials is high tensile steel wire, and before coming into operation, the distance according to equating with adjacent supports tray chamber distance marks mark with meter counter, and positioning rope is used to guarantee correct spacing and the position of wire separating ring in the HDPE outer tube.
Steel strand pull rope 9: material is a nylon, and quantity is identical with the steel strand radical, and its effect is that an end connects hoist engine wire rope 12, one ends connection steel strand 4, under the driving of hoist engine 14, respectively with the wire separating ring 3 of each root steel strand 4 perforating position in outer tube 1.
Arc junction plate 11: material is a steel plate, its exterior arc surface can not have torsional slip at the endoporus of outer tube 1, its intrados one end has the connector that is connected in strop 10, the other end has the connector that is connected in guide rail rope 13 and hoist engine wire rope 12, strop 10, two parallel guide rail ropes 13 and hoist engine wire rope 12 are connected on the corresponding interface of arc junction plate 11, traction by strop 10, can guarantee parallel between two guide rail ropes 13, (Fig. 3, shown in Figure 4) can not twist.
Guide rail rope 13: material is a high tensile steel wire, has two, and guide rail is made in parallel tensioning in the HDPE outer tube, wire separating ring 3 is entered in the outer tube along this guide rail can not twist.
In the working service of bridge, can carry out the single rope that changes, that is: can change the steel strand 4 of wherein arbitrary damage, its method is that the end with steel strand to be changed 4 links to each other with hoist engine wire rope 12, the other end links to each other with new steel strand, starting hoist engine, to bring new steel strand in place, again to this root steel strand tension to the Suo Li that wants.

Claims (2)

1, the tie bar cable system of band wire separating ring, it is characterized in that in the outer tube (1) of described tie-rod rope, be positioned at place, Support bracket (2) position wire separating ring (3) is set, described wire separating ring (3) is a disc-shaped component, wire separating ring (3) has separate, equate with the quantity of steel strand (4), the steel strand through hole (5) that is used for steel strand (4) that axis all parallels with the axis of outer tube (1), every steel strand (4) independently are located in the steel strand through hole (5) of wire separating ring (3) corresponding position, form parallel and separate between each root steel strand (4).
2, the tie bar cable system of band wire separating ring according to claim 1 is characterized in that the periphery in described wire separating ring (3), and a positioning rope hole (6) and two guide rail rope holes (7) are set respectively on the position triangular in shape.
CN 200620078098 2006-09-27 2006-09-27 Tie rod cable system with cable hole Expired - Lifetime CN200971471Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620078098 CN200971471Y (en) 2006-09-27 2006-09-27 Tie rod cable system with cable hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620078098 CN200971471Y (en) 2006-09-27 2006-09-27 Tie rod cable system with cable hole

Publications (1)

Publication Number Publication Date
CN200971471Y true CN200971471Y (en) 2007-11-07

Family

ID=38882728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620078098 Expired - Lifetime CN200971471Y (en) 2006-09-27 2006-09-27 Tie rod cable system with cable hole

Country Status (1)

Country Link
CN (1) CN200971471Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589539A (en) * 2018-04-27 2018-09-28 广西路桥工程集团有限公司 A kind of interim tie-rod is across installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589539A (en) * 2018-04-27 2018-09-28 广西路桥工程集团有限公司 A kind of interim tie-rod is across installation method
CN108589539B (en) * 2018-04-27 2019-12-31 广西路桥工程集团有限公司 Crossing installation method for temporary tie bar

Similar Documents

Publication Publication Date Title
CN102444086B (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN1251953C (en) Elevator rope and elevator apparatus
CN108660946B (en) Method for replacing main cable of suspension bridge
CN113937665B (en) Cable tensioning device for overhead laying of cables based on electric power engineering
CN1721314A (en) Equipment for suspension of a cage or counterweight in a lift installation and methods for mounting and for maintenance of suspension means
CN112411374A (en) Manufacturing and construction method of carbon fiber inhaul cable
CN213802263U (en) Cable traction device for electric power construction
CN200971471Y (en) Tie rod cable system with cable hole
CN1944795A (en) Tie bar cable system with wire separating ring and its construction method
CN103410125A (en) Integral U-shaped anchor rope embedded duct and mounting method thereof
CN105507149A (en) Arrangement method for cable-hanging of single parallel steel strand wires
CN110735401A (en) overall pulling method for ultra-long prestressed steel strand
CN115506265B (en) Multipoint walking pushing equipment and pushing process for large-section I-shaped steel beam
CN1458347A (en) Single stay tensing construction method and apparatus for parallel twisted steel stay system
CN1831291A (en) Continuous strenth compound tube for oil production of oil field and its production technology
CN200985492Y (en) Construction positioning device for suspending bridge main cable
CN1802459A (en) Replaceable components for a flyer bow
CN216737335U (en) Auxiliary lifting equipment for mounting steel box girder tower
CN215711348U (en) Fiber rope lifting device for bridge crane
KR101327759B1 (en) Pulling up apparatus for installing cable of suspension bridge and installing condition thereof
CN115467234B (en) Follow-up steel wire rope pre-clamping mechanism of wire winding machine and clamping method
CN111762702B (en) Tower crane steel wire rope pre-tightening locking device
CN219824927U (en) Stay cable soft and hard combined traction conversion device
CN203440795U (en) Integral U-shaped anchor rope pre-buried hole channel
CN203716518U (en) Prestress carbon fiber cloth laying device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Effective date of abandoning: 20060927

C25 Abandonment of patent right or utility model to avoid double patenting