CN105507149A - Arrangement method for cable-hanging of single parallel steel strand wires - Google Patents

Arrangement method for cable-hanging of single parallel steel strand wires Download PDF

Info

Publication number
CN105507149A
CN105507149A CN201510830571.2A CN201510830571A CN105507149A CN 105507149 A CN105507149 A CN 105507149A CN 201510830571 A CN201510830571 A CN 201510830571A CN 105507149 A CN105507149 A CN 105507149A
Authority
CN
China
Prior art keywords
steel strand
draw
cable
pulling
anchoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510830571.2A
Other languages
Chinese (zh)
Inventor
陈宜强
钟智强
朱徐平
林松
汪伟
周亮
刘微微
孙健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Jinxing Prestressing Engineering Technology Co Ltd
Original Assignee
Anhui Jinxing Prestressing Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Jinxing Prestressing Engineering Technology Co Ltd filed Critical Anhui Jinxing Prestressing Engineering Technology Co Ltd
Priority to CN201510830571.2A priority Critical patent/CN105507149A/en
Publication of CN105507149A publication Critical patent/CN105507149A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention provides an arrangement method for cable-hanging of single parallel steel strand wires. By adopting an enclosed signal steel strand cable-hanging circulating device and utilizing a network intelligent tension system, cable-penetrating speed and tension quality are greatly enhanced. The method comprises following steps: pulling the steel strand wire to the cable-hanging circulating device to a platform outside a tower and linking the steel strand wire with a cable-pulling device at an anchoring end and pulling the steel strand wire into an anchorage device at a tower end, installing clamp pieces and tensioning and pre-tightening; linking the other end of the steel strand wire with the cable-pulling device at the anchoring end of a beam end, pulling the steel strand wire to a beam-end anchorage device; installing clamp pieces and tensioning and pre-tightening; sequentially hanging cables of the whole steel strand wire; pulling the steel strand wire out to certain length outside the anchorage device at the tensioning and anchoring end of by a pulling rope and anchoring; continuing to pulling and fixing the pulling rope at the anchoring end till length of the steel strand wire penetrating out of the outside part of the tensioning and anchoring end of the anchorage device reaches the working length; anchoring the other end of the steel strand wire, dismantling the pulling rope and pulling the other steel strand wire; and pre-tightening and tensioning two steel strand wires.

Description

A kind of method for arranging of single parallel steel stranded wire hanging cable
Technical field
The present invention relates to technical field of building construction, be specifically related to a kind of method for arranging of single parallel steel stranded wire hanging cable.
Background technology
Parallel steel stranded wire drag-line generally takes single hanging cable, the form of construction work of single tendon stretch, and after this terminates, the later stage need carry out single tune rope to lock body, and traditional tune Suo Fangfa manually adjusts rope for using sensor and jack, and error range is large, inefficiency.
Summary of the invention
For traditional hanging cable construction method progress slowly, the problem of stretch-draw precision controlling difference, the invention provides a kind of method for arranging of novel parallel steel stranded wire hanging cable, by adopting closed single steel strand hanging cable circulating device, utilize network-enabled intelligent tensioning system, greatly increase the speed of reeving, stretch-draw quality.
For solving the problems of the technologies described above, the present invention adopts following technical scheme:
A method for arranging for single parallel steel stranded wire hanging cable, comprises hanging cable circulating device, and this hanging cable circulating device comprises draw drum, hoist engine, draw-gear, guy rope device, comprises the steps:
1) draw drum is put in beam anchorage end;
2) be connected with one end traction grooved of draw-gear the steel strand one end on draw drum, the other end traction grooved of draw-gear is connected by wire rope with described hoist engine, forms closed system of reeving;
3) steel strand are drawn to tower outer platform by hanging cable circulating device and connect with the guy rope device of anchored end, are drawn to by steel strand in tower end ground tackle, install intermediate plate, stretch-draw pretension;
4) other end of steel strand connects with the guy rope device of beam anchorage end, is drawn to by steel strand in beam-ends ground tackle, installs intermediate plate, stretch-draw pretension;
5) above-mentioned steps 2 is repeated) ~ 4) hanging cable is carried out to whole bundle steel strand;
6) hanging cable circulating device continues the drag cable of traction mooring anchor fixed end, until the length that steel strand pass ground tackle Outboard Sections in stretch-draw anchor end reaches active length;
7) anchoring is carried out to the steel strand other end, pull down drag cable, use hanging cable circulating device to draw another root steel strand;
8) pretension stretch-draw is carried out to two steel strand.
Further, described steel strand are arranged with guide cylinder, form every root steel strand independently pilot hole one to one.
Further, described clip surface carries out oozing heat treatment, and it oozes hot thickness is 0.45 ~ 0.65mm.
Preferably, the anchoring of described steel strand adopts pushing tow anchoring.
Preferably, described steel strand adopt epoxy coating strand or stranded galvanized steel.
From above technical scheme, the present invention has following beneficial effect:
One, utilize hanging cable circulating device control load to carry out stretch-draw, this system realizes prestressed stretch-draw full process automatization by computer software control, stops interference from human factor, can effectively guarantee tensioning construction quality;
Two, in conjunction with the improvement of anchor structure and stretching construction equipment, adopt closed single steel strand hanging cable circulating device, greatly increase reeve, the efficiency of construction of stretch-draw, the construction technology of improvement, compared with existing construction technology, decreases a large amount of labour intensity and construction cost.
Accompanying drawing explanation
Fig. 1 is method flow diagram of the present invention.
Detailed description of the invention
Below in conjunction with accompanying drawing, a kind of preferred embodiment of the present invention is described in detail.
Described hanging cable circulating device comprises draw drum, hoist engine, draw-gear, guy rope device, wherein hoist engine is arranged on beam, guy rope device is arranged on tower end, guy rope device is connected by wire rope with between hoist engine, this wire rope is turned to by two groups of directive wheels, and during use, the steel strand one end on draw drum is connected with one end traction grooved of draw-gear, the other end traction grooved of draw-gear is connected by wire rope with described hoist engine, forms closed system of reeving.Described guy rope device is used for stretch-draw pretension steel strand.
The anchoring system of described parallel steel stranded wire suspension cable adopts sealing drum to carry out the combination of alternative support tube and extending, reduce material cost and labour intensity is installed, and guide cylinder is arranged with on steel strand, form every root steel strand independently pilot hole one to one, realize steel strand single tendon stretch, single tune rope, singlely change rope, avoid the phenomenon connecting and occur in steel strand process interlocking in ground tackle, accelerate installation progress.
Described steel strand adopt epoxy coating strand or stranded galvanized steel, can be used as a kind of novel cable body materials application with excellent antiseptic property in bridges in highway engineering fields such as cable stayed bridge, low-pylon cable-stayed bridge, external prestressing, arch bridge tie-rods.And because the epoxy coating of this kind of steel strand surface attachment has certain thickness, the more general steel strand of diameter are slightly large, in order to enable intermediate plate fully be engaged anchoring with these steel strand, need tooth form and the tooth distance of new design intermediate plate.In the present invention, the surface of intermediate plate has carried out oozing heat treatment, it oozes hot thickness is 0.45 ~ 0.65mm, the inner teeth occlusion presstressed reinforcing steel of intermediate plate uniform force radially, avoid snap-in force concentrations, prevent the fracture of presstressed reinforcing steel, when being engaged presstressed reinforcing steel, sawtooth tooth can not be lost efficacy and damage, during intermediate plate follow-up distortion, entirety has certain toughness, makes clamping snap-in force be dispersed in prestressed periphery.
Due in steel strand stay cable installation process, the maximum stretching force of general single cable body is 45% to 60% of the disrumpent feelings force value of the steel strand limit, so easily there is low-stress state, retraction only by steel strand can not make intermediate plate be engaged steel strand and anchoring completely from anchor, therefore, pushing tow anchoring need be changed to the intermediate plate of parallel steel stranded wire into from anchor, make intermediate plate fully be engaged steel strand, form effective anchorage effect, decrease prestressed loss.
Shown in composition graphs 1, the method for arranging of parallel steel stranded wire hanging cable of the present invention, specifically comprises the steps:
1) draw drum is put in beam anchorage end;
2) be connected with one end traction grooved of draw-gear the steel strand one end on draw drum, the other end traction grooved of draw-gear is connected by wire rope with described hoist engine, forms closed system of reeving;
3) steel strand are drawn to tower outer platform by hanging cable circulating device and connect with the guy rope device of anchored end, are drawn to by steel strand in tower end ground tackle, install intermediate plate, stretch-draw pretension;
4) other end of steel strand connects with the guy rope device of beam anchorage end, is drawn to by steel strand in beam-ends ground tackle, installs intermediate plate, stretch-draw pretension;
5) above-mentioned steps 2 is repeated) ~ 4) hanging cable is carried out to whole bundle steel strand;
6) hanging cable circulating device continues the drag cable of traction mooring anchor fixed end, until the length that steel strand pass ground tackle Outboard Sections in stretch-draw anchor end reaches active length;
7) anchoring is carried out to the steel strand other end, pull down drag cable, use hanging cable circulating device to draw another root steel strand;
8) pretension stretch-draw is carried out to two steel strand.
By traditional the utilize method of jack and sensor adjustment Suo Li and advanced PLC control technology are combined, two jack can be controlled simultaneously and carry out synchronous tension, error range can be reduced, by the indicating value of pulling force in real-time collecting device, the load of applying can be checked and approved in time, and the elongation of jack, thus specification stretching process, reduce loss of prestress, improve pre-stress construction quality.
The above embodiment is only be described the preferred embodiment of the present invention; not scope of the present invention is limited; under not departing from the present invention and designing the prerequisite of spirit; the various distortion that those of ordinary skill in the art make technical scheme of the present invention and improvement, all should fall in protection domain that claims of the present invention determine.

Claims (5)

1. a method for arranging for single parallel steel stranded wire hanging cable, comprises hanging cable circulating device, and this hanging cable circulating device comprises draw drum, hoist engine, draw-gear, guy rope device, it is characterized in that, comprises the steps:
1) draw drum is put in beam anchorage end;
2) be connected with one end traction grooved of draw-gear the steel strand one end on draw drum, the other end traction grooved of draw-gear is connected by wire rope with described hoist engine, forms closed system of reeving;
3) steel strand are drawn to tower outer platform by hanging cable circulating device and connect with the guy rope device of anchored end, are drawn to by steel strand in tower end ground tackle, install intermediate plate, stretch-draw pretension;
4) other end of steel strand connects with the guy rope device of beam anchorage end, is drawn to by steel strand in beam-ends ground tackle, installs intermediate plate, stretch-draw pretension;
5) above-mentioned steps 2 is repeated) ~ 4) hanging cable is carried out to whole bundle steel strand;
6) hanging cable circulating device continues the drag cable of traction mooring anchor fixed end, until the length that steel strand pass ground tackle Outboard Sections in stretch-draw anchor end reaches active length;
7) anchoring is carried out to the steel strand other end, pull down drag cable, use hanging cable circulating device to draw another root steel strand;
8) pretension stretch-draw is carried out to two steel strand.
2. method for arranging according to claim 1, is characterized in that, described steel strand are arranged with guide cylinder, forms every root steel strand independently pilot hole one to one.
3. method for arranging according to claim 1, is characterized in that, described clip surface carries out oozing heat treatment, and it oozes hot thickness is 0.45 ~ 0.65mm.
4. method for arranging according to claim 1, is characterized in that, the anchoring of described steel strand adopts pushing tow anchoring.
5. method for arranging according to claim 1, is characterized in that, described steel strand adopt epoxy coating strand or stranded galvanized steel.
CN201510830571.2A 2015-11-25 2015-11-25 Arrangement method for cable-hanging of single parallel steel strand wires Pending CN105507149A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510830571.2A CN105507149A (en) 2015-11-25 2015-11-25 Arrangement method for cable-hanging of single parallel steel strand wires

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510830571.2A CN105507149A (en) 2015-11-25 2015-11-25 Arrangement method for cable-hanging of single parallel steel strand wires

Publications (1)

Publication Number Publication Date
CN105507149A true CN105507149A (en) 2016-04-20

Family

ID=55715428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510830571.2A Pending CN105507149A (en) 2015-11-25 2015-11-25 Arrangement method for cable-hanging of single parallel steel strand wires

Country Status (1)

Country Link
CN (1) CN105507149A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106348034A (en) * 2016-08-30 2017-01-25 中国能源建设集团安徽电力建设第工程有限公司 Suspension cable steel structure large power plant coal transporting trestle stay cable construction method
CN108385525A (en) * 2018-01-29 2018-08-10 中交二航局第四工程有限公司 The method that revolution steel strand wires are unidirectionally drawn in the same direction
CN108385524A (en) * 2018-01-29 2018-08-10 中交第二航务工程局有限公司 The method of revolution steel strand wires bivector traction in the same direction
CN111155822A (en) * 2018-11-20 2020-05-15 中国船舶重工集团海装风电股份有限公司 Steel strand installation method for wind driven generator support tower frame prestressed structure
CN114775430A (en) * 2022-04-13 2022-07-22 江阴法尔胜住电新材料有限公司 Steel strand tie rod cable system with layered wire-dividing supporting structure and installation method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0790812A (en) * 1991-03-12 1995-04-04 Freyssinet Internatl (Stup) Technique and apparatus for making various wire constituting diagonal wire in same length
CN1458347A (en) * 2002-05-15 2003-11-26 柳州市建筑机械总厂 Single stay tensing construction method and apparatus for parallel twisted steel stay system
CN102852092A (en) * 2012-10-10 2013-01-02 中铁上海工程局有限公司 Hanging cable guiding device and method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0790812A (en) * 1991-03-12 1995-04-04 Freyssinet Internatl (Stup) Technique and apparatus for making various wire constituting diagonal wire in same length
CN1458347A (en) * 2002-05-15 2003-11-26 柳州市建筑机械总厂 Single stay tensing construction method and apparatus for parallel twisted steel stay system
CN102852092A (en) * 2012-10-10 2013-01-02 中铁上海工程局有限公司 Hanging cable guiding device and method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
卿三惠: "《土木工程施工工艺:桥梁工程(第2版)》", 31 October 2013, 中国铁道出版社 *
左先宇: ""平行钢绞线斜拉索施工技术"", 《中华建设》 *
陈儒发: ""礐石大桥平行钢绞线斜拉索施工"", 《公路》 *
陈林: ""平行钢绞线斜拉索施工技术"", 《公路交通技术》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106348034A (en) * 2016-08-30 2017-01-25 中国能源建设集团安徽电力建设第工程有限公司 Suspension cable steel structure large power plant coal transporting trestle stay cable construction method
CN106348034B (en) * 2016-08-30 2018-08-17 中国能源建设集团安徽电力建设第一工程有限公司 Suspension cable steel construction large-scale power station coal transporting trestle stayed Cable Construction method
CN108385525A (en) * 2018-01-29 2018-08-10 中交二航局第四工程有限公司 The method that revolution steel strand wires are unidirectionally drawn in the same direction
CN108385524A (en) * 2018-01-29 2018-08-10 中交第二航务工程局有限公司 The method of revolution steel strand wires bivector traction in the same direction
CN108385524B (en) * 2018-01-29 2020-07-14 中交第二航务工程局有限公司 Bidirectional traction method for equidirectional rotary steel strands
CN111155822A (en) * 2018-11-20 2020-05-15 中国船舶重工集团海装风电股份有限公司 Steel strand installation method for wind driven generator support tower frame prestressed structure
CN114775430A (en) * 2022-04-13 2022-07-22 江阴法尔胜住电新材料有限公司 Steel strand tie rod cable system with layered wire-dividing supporting structure and installation method

Similar Documents

Publication Publication Date Title
CN105507149A (en) Arrangement method for cable-hanging of single parallel steel strand wires
CN102444086B (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN104278637B (en) A kind of main rope of suspension bridge strand is without the cableway erection method in cat road
MX2018002590A (en) System and method for installing a tensioning tendon in a wind turbine tower.
CN103790113B (en) A kind of steel strand stay cable reeving device and method of reeving thereof
CN104631329A (en) Method for adjusting overall line shape of continuous catwalk of suspension bridge
CN103147400A (en) One-time tensioning construction method of super-long prestressed tendon for cast-in-place box girder bridge web
CN103410125B (en) Integral U-shaped anchor rope embedded duct and mounting method thereof
CN102535336A (en) Composite prestressed bar finished guy cable and manufacturing method thereof
CN101967796A (en) Method for arranging parallel steel wire stay cable
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN108149932B (en) Beam penetrating device and beam penetrating method for prestress steel strand
CN106401196A (en) Steel strand tensioning device for pre-stressed anchorage device
CN209760863U (en) External prestress steel strand connector and matched tensioning device
CN106087759B (en) A kind of threading method of prestressed strand threader and prestressed strand
CN202543802U (en) Composite-prestressed-tendon finished inhaul cable
CN202543803U (en) Finished cable consisting of steel strands
CN111924720A (en) Wind cable anchoring system of cable crane tower and construction method
CN203923907U (en) The pre-integer unit cable strand of main rope of suspension bridge
CN208934432U (en) It is a kind of circle concrete tube chamber structure without support prestressed reinforcement equipment
CN106988310A (en) A kind of glass fiber-reinforced polymer material, the anchor cable being made up of glass fiber-reinforced polymer material and construction technology
CN111155822A (en) Steel strand installation method for wind driven generator support tower frame prestressed structure
CN207987752U (en) A kind of deck unit erection gantry anchor automatically adjusting anchoring angle
KR101327759B1 (en) Pulling up apparatus for installing cable of suspension bridge and installing condition thereof
CN211547407U (en) Steel strand stay cable reeving device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160420