CN200964585Y - All-bushing perfusion stake bitten cement earth stake - Google Patents

All-bushing perfusion stake bitten cement earth stake Download PDF

Info

Publication number
CN200964585Y
CN200964585Y CN 200620019434 CN200620019434U CN200964585Y CN 200964585 Y CN200964585 Y CN 200964585Y CN 200620019434 CN200620019434 CN 200620019434 CN 200620019434 U CN200620019434 U CN 200620019434U CN 200964585 Y CN200964585 Y CN 200964585Y
Authority
CN
China
Prior art keywords
pile
stake
cement
cement earth
bushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200620019434
Other languages
Chinese (zh)
Inventor
刘富华
卢信雅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Original Assignee
Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Jiecheng Foundation Engineering & Machine Co Ltd filed Critical Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Priority to CN 200620019434 priority Critical patent/CN200964585Y/en
Application granted granted Critical
Publication of CN200964585Y publication Critical patent/CN200964585Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a complete sleeve pouring pile occluding a soil cement pile, belonging to a construction pile, in particular to a combined typed pile body. The device is characterized in that the combined typed pile is formed as integration by occlusion of a side wall of the complete sleeve pouring pile and a side wall of the soil cement pile. The utility model has the advantages of a simple structure, a high integral rigidity, a good anti leakage effect and a low production cost.

Description

Bushing complete compresol pile occlusion rammed-cement-soil pile
Technical field
The utility model belongs to the pile body of building, particularly the combined type pile body.
Background technology
The normal retaining fortifield village protection structure that adopts of soft clay area has common boring supporting campshed, cement mixing method, the stake of SMW worker's method, diaphragm wall, fully-sleeved filled pile (concrete) interlock stake etc.The shear strength of common boring supporting campshed is low, and the safety and the poor-performing that intercepts water are bigger to the environmental protection influence; It is bigger that cement mixing method exists the construction plant to take, and integral rigidity is low, in order to remedy the deficiency on intensity and the rigidity, can only strengthen the volume of pile body; The construction technology of SMW worker's method stake is complicated, and wall quality, integral rigidity are desirable not enough, and only as temporary structure; Construction of continuous concrete wall technology is complicated, and mud is big to the environmental protection influence, exists reinforcement ratio higher, so cost is higher; Fully-sleeved filled pile (concrete) interlock stake is than environmental protection, the integral rigidity ideal, and anti-seepage effect is better, but during in the excavation of foundation pit degree of depth≤10 meter, cost is higher relatively.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of Bushing complete compresol pile occlusion rammed-cement-soil pile, and it is simple in structure, the integral rigidity height, and antiseep is effective, and cost is lower.
Solving the scheme that technical problem of the present utility model adopts is: form whole compound pile with the sidewall of fully-sleeved filled pile and the mutual interlock of sidewall of cement earth pile.
The compound pile that this is novel is owing to taked fully-sleeved filled pile and the structure of the mutual interlock overlap joint of cement earth pile, the bending resistance structure king pile of body of wall is a fully-sleeved filled pile, the auxilliary stake that cement earth pile transmits as lateral stress, the arranged spaced mode of two kinds of pile bodies can reduce the reinforcement ratio of supporting and protection structure, both guarantee certain intensity, reduced cost again; The outer freight volume of the roach of two kinds of pile bodies is all less, need not mud off, and is therefore very little to the environmental protection influence; Because the interlock stake is construction continuously, do not have constuction joint between stake, so the antiseep effect is better.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Each label is represented successively among the figure: cement earth pile 1, fully-sleeved filled pile 2, occlusal surface 3.
The specific embodiment
Referring to Fig. 1, this interlock stake is the sidewall that is embedded (cutting) cement earth piles 1 by fully-sleeved filled pile 2, overlaps mutually and the combination pile body that forms, becomes the occlusal surface 3 of integral body in the concrete setting of the position of its overlap joint, make the existing integral intensity of pile body, good antiseep is arranged again.In construction, two kinds of stakes have simultaneously possessed the few characteristics of roach outward transport, thereby very little to the environmental protection influence.Can be during construction according to concrete building requirements, diameter to two kinds of stakes is joined choosing flexibly in the scope of 600mm~1200mm, also can be from the angle and the view of function of economy, reinforcement ratio in the fully-sleeved filled pile 2 is made only selection, but the single cement earth pile of fully-sleeved filled pile interlock simultaneously, but also many continuous cement earth piles of interlock.

Claims (2)

1, a kind of Bushing complete compresol pile occlusion rammed-cement-soil pile is characterized in that: the sidewall of fully-sleeved filled pile and the sidewall of cement earth pile are bited into whole compound pile mutually.
2, by the described Bushing complete compresol pile occlusion rammed-cement-soil pile of claim 1, it is characterized in that: the suitable diameter of fully-sleeved filled pile and cement earth pile is 600mm~1200mm.
CN 200620019434 2006-04-12 2006-04-12 All-bushing perfusion stake bitten cement earth stake Expired - Fee Related CN200964585Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620019434 CN200964585Y (en) 2006-04-12 2006-04-12 All-bushing perfusion stake bitten cement earth stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620019434 CN200964585Y (en) 2006-04-12 2006-04-12 All-bushing perfusion stake bitten cement earth stake

Publications (1)

Publication Number Publication Date
CN200964585Y true CN200964585Y (en) 2007-10-24

Family

ID=38868597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620019434 Expired - Fee Related CN200964585Y (en) 2006-04-12 2006-04-12 All-bushing perfusion stake bitten cement earth stake

Country Status (1)

Country Link
CN (1) CN200964585Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418348A (en) * 2011-08-23 2012-04-18 谢清光 Construction technology of using occlusive pile to form underground continuous wall
CN102900077A (en) * 2012-11-08 2013-01-30 上海强劲地基工程股份有限公司 Construction method of six-shaft cement mixing piles
CN103556634A (en) * 2013-09-29 2014-02-05 国鼎(南通)管桩有限公司 High-strength prestress combined support pile
CN103556633A (en) * 2013-09-29 2014-02-05 国鼎(南通)管桩有限公司 High-strength special-shaped prestress combined support pile
CN104563095A (en) * 2014-12-18 2015-04-29 上海建工二建集团有限公司 Novel enclosure system of soft-hard occlusion piles and construction method
CN104863120A (en) * 2015-05-13 2015-08-26 中国建筑第八工程局有限公司 Occlusive pile construction method and prefabricated occlusive piles used for method
CN109113086A (en) * 2018-10-24 2019-01-01 湖北工业大学 A kind of steel reinforced concrete combined cofferdam construction method in deep water exposed bedrock riverbed area

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418348A (en) * 2011-08-23 2012-04-18 谢清光 Construction technology of using occlusive pile to form underground continuous wall
CN102900077A (en) * 2012-11-08 2013-01-30 上海强劲地基工程股份有限公司 Construction method of six-shaft cement mixing piles
CN102900077B (en) * 2012-11-08 2015-01-21 上海强劲地基工程股份有限公司 Construction method of six-shaft cement mixing piles
CN103556634A (en) * 2013-09-29 2014-02-05 国鼎(南通)管桩有限公司 High-strength prestress combined support pile
CN103556633A (en) * 2013-09-29 2014-02-05 国鼎(南通)管桩有限公司 High-strength special-shaped prestress combined support pile
CN104563095A (en) * 2014-12-18 2015-04-29 上海建工二建集团有限公司 Novel enclosure system of soft-hard occlusion piles and construction method
CN104863120A (en) * 2015-05-13 2015-08-26 中国建筑第八工程局有限公司 Occlusive pile construction method and prefabricated occlusive piles used for method
CN109113086A (en) * 2018-10-24 2019-01-01 湖北工业大学 A kind of steel reinforced concrete combined cofferdam construction method in deep water exposed bedrock riverbed area

Similar Documents

Publication Publication Date Title
CN200964585Y (en) All-bushing perfusion stake bitten cement earth stake
CN101775803A (en) Mushroom-shaped mixed composite pile capable of effectively controlling settlement and construction method
CN203334270U (en) Mountable buried type prefabricated hollow underground diaphragm wall
CN210151660U (en) Embedded concrete antiskid tenon grout stone retaining wall
CN210117712U (en) Stirring grooving insertion type prefabricated combined box foundation structure
CN103898918A (en) Combined supporting structure and construction method
CN203530959U (en) High-strength underground diaphragm wall
CN203174586U (en) Concrete pipe pile for reinforcing railway soft soil foundation
CN209723230U (en) The connecting node of steel plate combined shear wall and not equal higher baselines
CN203904972U (en) Anti-soil leaking combined support pile
CN202881963U (en) Inverted filter device for water drainage of retaining wall
CN201321612Y (en) Prestressing pipe pile for buildings
CN200946270Y (en) Sinking pipe bottom-expanding pile
CN200955146Y (en) Multi-stage sink-pipe bored concrete pile
CN2828143Y (en) Pile shoe special for tubular pile
CN103835290A (en) Pile foundation structure suitable for marine soft soil and design method thereof
CN204125960U (en) Concrete bearing platform
CN202090334U (en) Capped two-way-perforated PTC tubular pile composite foundation
CN201087410Y (en) Pedestal pile suitable for high-rise building foundation construction
CN201087400Y (en) High bearing ability immersed tube filling pedestal pile
CN200949227Y (en) Pipe sank prefabricated pedestal pile
CN203905016U (en) Shallow foundation pit three-pile combined supporting structure
CN200967959Y (en) High-rise building club-footed pile
CN201074329Y (en) Sinking pipe pedestal pile
CN201121317Y (en) Anti-impact pedestal pile for building foundation construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Zhongkuang Resources Exploration Co., Ltd

Assignor: Kunming Jiecheng Foundation Engineering & Machine Co., Ltd.

Contract fulfillment period: 2007.11.28 to 2015.11.30

Contract record no.: 2009110000064

Denomination of utility model: All-bushing perfusion stake bitten cement earth stake

Granted publication date: 20071024

License type: Exclusive license

Record date: 20090505

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2007.11.28 TO 2015.11.30; CHANGE OF CONTRACT

Name of requester: ZHONGKUANG RESOURCES EXPLORATION CO., LTD.

Effective date: 20090505

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20071024

Termination date: 20150412