CN1944913A - Mounting and constructing method for polyvinyl-chloride floor - Google Patents
Mounting and constructing method for polyvinyl-chloride floor Download PDFInfo
- Publication number
- CN1944913A CN1944913A CN 200610122169 CN200610122169A CN1944913A CN 1944913 A CN1944913 A CN 1944913A CN 200610122169 CN200610122169 CN 200610122169 CN 200610122169 A CN200610122169 A CN 200610122169A CN 1944913 A CN1944913 A CN 1944913A
- Authority
- CN
- China
- Prior art keywords
- pvc
- polyvinyl chloride
- floor
- paving
- glue
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The polyvinyl chloride floor board mounting construction process includes the following steps: 1. polishing the floor, cleaning and leveling with putty; 2. compounding glue and brushing the glue to the floor; 3. laying floor board after the glue is dried naturally for 10-30 min while leaving gaps of 1-3 mm between floor boards; and 4. hot welding after 24 hr with polyvinyl chloride welding rod to connecting the floor boards integrally and cutting off the excessive parts. The polyvinyl chloride floor board is adhered firmly to the floor.
Description
Technical field
The present invention relates to the construction method of installation on floor, particularly the construction method of installation on polyvinyl chloride (PVC) floor.
Background technology
Easy aliquation when brushing PVC glue is handled on existing present polyvinyl chloride (PVC) floor, and adhesive effect is bad, and application life is short.
Summary of the invention
The object of the present invention is to provide the construction method of installation on the good polyvinyl chloride of a kind of adhesive effect (PVC) floor.
Purpose of the present invention can realize like this, designs a kind of polyvinyl chloride (PVC) floor construction method of installation, may further comprise the steps:
A, floor treatment; Polish one time to the ground that will construct is whole with grinding apparatus earlier, grind off the foreign material and the ground thing that floating of protrusion, cleaning afterwards is clean, if there is recess to repair levelling with putty;
B, brushing glue: configure PVC glue, stir, brush on construction ground, brushing is evenly once brushed 5~10 square metres;
C, paving polyvinyl chloride (PVC) floor; Wait to scribble the floor air dry 10~30 minutes of glue, begin paving polyvinyl chloride (PVC) floor afterwards, with two right-angle side alignment fiducials lines of thick china, paving should be quick rapidly during paving; Should leave 1~3mm slit between plate and the plate, gap width is consistent between each plate; Beat and roll panel with instrument, it is pasted firmly; Limit paving frontier inspection is looked into, and guarantees to paste firmly;
D, welding: carry out thermal weld after at least 24 hours in polyvinyl chloride (PVC) floor installation, carry out the thermoplastic welding at the welding groove place with polyvinyl chloride (PVC) welding rod, welding gun, plate and plate are fused, and solder-bump thing or fifth wheel are used scraper and are cut flat.
Use polyvinyl chloride of the invention process (PVC) floor and ground bonding firmly.
The specific embodiment
The invention will be further described below in conjunction with embodiment.
A kind of polyvinyl chloride (PVC) floor construction method of installation may further comprise the steps:
A, floor treatment; Polish one time to the ground that will construct is whole with grinding apparatus earlier, grind off the foreign material and the ground thing that floating of protrusion, cleaning afterwards is clean, if there is recess to repair levelling with putty;
B, brushing glue: configure practical PVC glue, stir, brush on construction ground, brushing is evenly once brushed 5~10 square metres;
C, paving polyvinyl chloride (PVC) floor; Wait to scribble the floor air dry 10~30 minutes of glue, begin paving polyvinyl chloride (PVC) floor afterwards, with two right-angle side alignment fiducials lines of thick china, paving should be quick rapidly during paving; Should leave 1~3mm slit between plate and the plate, gap width is consistent between each plate; Beat and roll panel with instrument, it is pasted firmly; Limit paving frontier inspection is looked into, and guarantees to paste firmly;
D, welding: carry out thermal weld after at least 24 hours in polyvinyl chloride (PVC) floor installation, carry out the thermoplastic welding at the welding groove place with polyvinyl chloride (PVC) welding rod, welding gun, plate and plate are fused, and solder-bump thing or fifth wheel are used scraper and are cut flat.
Antistatic or polyvinyl chloride (PVC) the ground construction content of leading static comprise that base treatment, grounding system are installed, paving, cleaning, construction, test and the quality inspection etc. on glue preparation, PVC film overlay panel floor.The job site temperature is answered between 10~35 ℃; Relative humidity must not be greater than 75%; Ventilation should be good.
The processing on ground.The construction plant should meet following requirement: when (1) basic unit ground was cement floor or terazzo surface, hardened artiwear ground, ground should be cleaned, and residues such as ground paint, adhesive should be cleaned out.(2) ground should be smooth; With 2 meters ruler inspections, the gap should be less than 1~2mm.If there is uneven or crackled place must mend flat.(3) basic unit ground is that wood flooring, ceramic tile, plastics etc. should be removed and are former floor, and should thoroughly remove ground residual binding, and the job site should be equipped with the artificial illumination device.(4) ground layer should be dry.If ground floor should be done moistureproof water treatment earlier.Ground layer is answered the hard layer of sand that do not rise, and the substrate surface strength of cement mortar is greater than 3000PSI.Need do self-leveling cement or resin is a base plane from the levelling levelling if the floor is uneven.(5) determine the earth terminal position; Area is at 1000m
2In, earth terminal should be no less than 2, the every increase of area 1000m
2, should set up earth terminal 1-2.
Lay the job practices on common (PVC) floor on construction ground.A, floor treatment; With large-sized grinder integral body dry grinding one time is carried out on ground earlier,, ground off the foreign material and the ground thing that floating of protrusion again with the whole polishing of small-sized hand mill one time, clean with the dust catcher cleaning afterwards, if there is recess to repair levelling with putty.
B, the practical glue of configurating PVC stir, and brush on the ground, and brushing is evenly once brushed 5-10 square metre.
C, paving common PVC floor.Wait to scribble floor air dry 10-30 minute of glue, should begin paving PVC floor immediately, should be during paving with two right-angle side alignment fiducials lines of thick china, paving should be quick rapidly.Should leave the 1-3mm slit between plate and the plate, gap width should keep basically identical, evenly beats the plate face with rubber hammer, and heavy 30-50 kilogram cylinder advances to roll.Limit paving frontier inspection is looked into, and guarantees to paste firmly.Ground edge uses non-standard thick china paving polishing, and non-standard thick china is formed with the cutter cutting by the standard thick china.
D, should carry out thermal weld after at least 24 hours in the installation of PVC floor.Carry out the thermoplastic welding at the welding groove place with PVC welding rod, welding gun; Plate and plate are fused.Welding fifth wheel application scraper cuts flat, but must not scratch the thick china surface.
Lay antistatic or lead the job practices on static polyvinyl chloride (PVC) floor on construction ground.A, floor treatment; With large-sized grinder integral body dry grinding one time is carried out on ground earlier,, ground off the foreign material and the ground thing that floating of protrusion again with the whole polishing of small-sized hand mill one time, clean with the dust catcher cleaning afterwards, if there is recess to repair levelling with putty.
A1, should look the room geometry and rationally determine to delimit reference line, should lay the copper-foil conducting electricity grid by the earth mat arrangement diagram, the crosspoint in length and breadth of Copper Foil should be in the center of thick china, and the laying of copper chaff should be straight, must not curl, and also must not be interrupted.The copper chaff that is connected with earth terminal should leave enough connection length, generally at 5 centimetres to 30 centimetres.
B, configurating PVC are led the practical glue of static; Stir, on the copper-foil conducting electricity of paving, brush evenly, once brush 5-10 square metre.
Static or antistatic (PVC) floor are led in C, paving; Wait to scribble floor air dry 10-30 minute of glue, should begin paving PVC floor immediately, should be during paving with two right-angle side alignment fiducials lines of thick china, paving should be quick rapidly.Should leave the 1-3mm slit between plate and the plate, gap width should keep basically identical, evenly beats the plate face with rubber hammer, and heavy 30-50 kilogram cylinder advances to roll.Limit paving frontier inspection is looked into, and guarantees to paste firmly.Ground edge uses non-standard thick china paving polishing, and non-standard thick china is formed with the cutter cutting by the standard thick china.
When C1, pawnshop are attached to the earth terminal place; Should be earlier the copper chaff that connects earth terminal be drawn, firmly link with the method and the earth terminal of soldering or crimping.Continue the paving panel again.
After D1, the paving of whole room finish; Should snap access slot with groover along the thick china seam crossing.The line of rabbet joint should be straight, even, groove width 2~3 ± 0.2mm is advisable.
D, should carry out thermal weld after at least 24 hours in the installation of PVC floor.Carry out the thermoplastic welding at the welding groove place with PVC welding rod, welding gun; Plate and plate are fused.Welding fifth wheel application scraper cuts flat, but must not scratch the thick china surface.
E, the operation of paving panel are clean with floor cleaning after finishing, and should the protection of brushing antistatic wax.
The grounding system construction should comprise: the copper-foil conducting electricity earth mat; Contents such as ground connection Copper Foil, connecting terminal, down conductor, ground connector.Copper Foil is connected to each other together by Copper Foil net figure, the conduction earth mat should be 10-20mm greater than 0.025mm, width with the thickness of Copper Foil, digs one long 1 meter wide 1 meter dark heatable adobe sleeping platform, and thickness is put into the hole at the 15-25mm copper rod as ground connector, laying salt in the hole buries soil at last and fills and leads up and get final product then.The mesh of Copper Foil net is generally 1 meter * 1 meter~2 meters * 2 meters, and two Copper Foils are fixed in the Copper Foil junction.
After antistatic or polyvinyl chloride (PVC) floor of leading static installed, the test resistance performance requirement was led electrostatic PVC sheet resistance 10
4Ω-10
6Between the Ω, the anti-static PVC sheet resistance is 10
6Ω-10
9Between the Ω.
PVC plate and PVC welding rod preferably adopt color and luster even, external diameter unanimity, flexible good material.The PVC panel preferably is stored in the warehouse of aeration-drying, away from acid, alkali and other corrosive substance.Should with light packsly gently unload during carrying, forbid to clash into sudden force.Forbid to place outdoor exposing to the sun and rain.
Claims (6)
1, a kind of polyvinyl chloride (PVC) flooring construction method of installation is characterized in that may further comprise the steps:
A, floor treatment; Polish one time to the ground that will construct is whole with grinding apparatus earlier, grind off the foreign material and the ground thing that floating of protrusion, cleaning afterwards is clean, if there is recess to repair levelling with putty;
B, brushing glue: configure polyvinyl chloride (PVC) glue, stir, brush on construction ground, brushing is evenly once brushed 5~10 square metres;
C, paving polyvinyl chloride (PVC) floor: wait to scribble the floor air dry 10~30 minutes of glue, begin paving polyvinyl chloride (PVC) floor afterwards, with two right-angle side alignment fiducials lines of thick china, paving should be quick rapidly during paving; Should leave 1~3mm slit between plate and the plate, gap width is consistent between each plate; Beat and roll panel with instrument, it is pasted firmly; Limit paving frontier inspection is looked into, and guarantees to paste firmly;
D, welding: carry out thermal weld after at least 24 hours in polyvinyl chloride (PVC) floor installation, carry out the thermoplastic welding at the welding groove place with polyvinyl chloride (PVC) welding rod, welding gun, plate and plate are fused, and solder-bump thing or fifth wheel are used scraper and are cut flat.
2, polyvinyl chloride (PVC) flooring construction method of installation according to claim 1 is characterized in that:
Comprise in the described steps A: should lay the copper-foil conducting electricity grid by the earth mat arrangement diagram, the crosspoint in length and breadth of Copper Foil should be in the center of thick china, and the laying of copper chaff should be straight, and is uninterrupted; The copper chaff that is connected with earth terminal should leave connection length;
Disposing polyvinyl chloride (PVC) glue among the described step B is that polyvinyl chloride (PVC) is led the practical glue of static;
The polyvinyl chloride of paving (PVC) floor is for leading static or antistatic polyvinyl chloride (PVC) floor among the described step C; When the pawnshop is attached to the earth terminal place, should be earlier the copper chaff that connects earth terminal be drawn, firmly link with the method and the earth terminal of soldering or crimping; Continue the paving panel again;
Before the working face paving finishes the back thermal weld among the described step D, snap access slot with groover along the thick china seam crossing; Groove width 2~3mm.
Also comprise step e: after the smooth operation of panel thermal weld is finished that cleaning surfaces is clean, and the protection of brushing antistatic wax.
3, polyvinyl chloride (PVC) flooring construction method of installation according to claim 1 is characterized in that: evenly beat the plate face with rubber hammer in the described C step, weigh 30~50 kilograms of cylinders and advance to roll.
4, polyvinyl chloride (PVC) flooring construction method of installation according to claim 1 is characterized in that: in the described C step: ground edge uses non-standard thick china paving polishing, and non-standard thick china is formed with the cutter cutting by the standard thick china.
5, polyvinyl chloride (PVC) flooring construction method of installation according to claim 2, it is characterized in that: described construction area is at 1000m
2In, the earth terminal of earth mat is provided with 2 at least, the every increase of area 1000m
2, earth terminal is corresponding sets up 1~2.
6, polyvinyl chloride (PVC) flooring construction method of installation according to claim 2 is characterized in that: described conduction earth mat should be greater than 0.025mm with copper thickness, and width is 10~20mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200610122169 CN1944913A (en) | 2006-09-08 | 2006-09-08 | Mounting and constructing method for polyvinyl-chloride floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200610122169 CN1944913A (en) | 2006-09-08 | 2006-09-08 | Mounting and constructing method for polyvinyl-chloride floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN1944913A true CN1944913A (en) | 2007-04-11 |
Family
ID=38044493
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200610122169 Pending CN1944913A (en) | 2006-09-08 | 2006-09-08 | Mounting and constructing method for polyvinyl-chloride floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1944913A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535814A (en) * | 2012-02-28 | 2012-07-04 | 天津盛霖化工有限公司 | Fluorescent floor, preparation method and using method thereof |
CN102535816A (en) * | 2012-02-29 | 2012-07-04 | 圣象(江苏)木业研究有限公司 | Method for paving floor boards |
CN103866981A (en) * | 2014-04-08 | 2014-06-18 | 黑龙江天有为电子有限责任公司 | Anti-static method used in electronic product manufacturing shop |
CN104453171A (en) * | 2015-01-03 | 2015-03-25 | 李�浩 | Simple vinyl tile paving method |
CN108071213A (en) * | 2017-11-06 | 2018-05-25 | 安徽枫帆轨道装备有限公司 | A kind of construction technology on anti-static PVC floor |
CN108166719A (en) * | 2017-12-26 | 2018-06-15 | 南通远洋船舶配套有限公司 | PVC floor directly lays processing mounting process of the upper wall as skirting from ground |
CN109441059A (en) * | 2018-10-30 | 2019-03-08 | 安徽智恒信科技有限公司 | A kind of plastic floor laying structure and its construction method |
CN109989315A (en) * | 2019-04-11 | 2019-07-09 | 河北绿城园林绿化工程有限公司 | A kind of method for paving on plastics road surface |
-
2006
- 2006-09-08 CN CN 200610122169 patent/CN1944913A/en active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535814A (en) * | 2012-02-28 | 2012-07-04 | 天津盛霖化工有限公司 | Fluorescent floor, preparation method and using method thereof |
CN102535816A (en) * | 2012-02-29 | 2012-07-04 | 圣象(江苏)木业研究有限公司 | Method for paving floor boards |
CN103866981A (en) * | 2014-04-08 | 2014-06-18 | 黑龙江天有为电子有限责任公司 | Anti-static method used in electronic product manufacturing shop |
CN104453171A (en) * | 2015-01-03 | 2015-03-25 | 李�浩 | Simple vinyl tile paving method |
CN108071213A (en) * | 2017-11-06 | 2018-05-25 | 安徽枫帆轨道装备有限公司 | A kind of construction technology on anti-static PVC floor |
CN108166719A (en) * | 2017-12-26 | 2018-06-15 | 南通远洋船舶配套有限公司 | PVC floor directly lays processing mounting process of the upper wall as skirting from ground |
CN109441059A (en) * | 2018-10-30 | 2019-03-08 | 安徽智恒信科技有限公司 | A kind of plastic floor laying structure and its construction method |
CN109989315A (en) * | 2019-04-11 | 2019-07-09 | 河北绿城园林绿化工程有限公司 | A kind of method for paving on plastics road surface |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1944913A (en) | Mounting and constructing method for polyvinyl-chloride floor | |
CN107246158A (en) | The construction technology of carbon fiber cloth strengthening technology | |
JP2012021315A (en) | Composite waterproof sheet, floor slab waterproof structure and construction method for floor slab waterproof structure | |
NZ544369A (en) | Multi-layer covering having a flexible fabric layer for use in floors, ceilings and roofs | |
CN101935196A (en) | Putty for building external wall | |
CN101105076A (en) | On site antistatic terrazzo ground construction method | |
US8945332B2 (en) | Exterior composite finish flooring | |
CN103835478A (en) | Copper plate grounding grid antistatic terrazzo floor construction process | |
CN1458357A (en) | Anti-cracking inner thermal insulation wall and construction process | |
CN109441113A (en) | Roof waterproof engineering construction method | |
CN111395410B (en) | Construction method for pre-paving asphalt-based waterproof coiled material through welding and bonding combined construction | |
CN209568594U (en) | A kind of assembling type steel structure floor ceiling | |
US8327602B2 (en) | Method and system for remediating and covering wood floors | |
CN207419541U (en) | A kind of composite light lumber convenient for splicing | |
CN105544924A (en) | Electrostatic precipitation air purification external heat emission element floor heating composite floor | |
KR20200013283A (en) | Waterproofing sheet, double layer waterproof for bridge and method for construction using the same | |
CN206591722U (en) | A kind of moistureproof cement light partition wall board of crack resistence for connecting wall | |
RU77626U1 (en) | SET OF ELEMENTS AND PLATE FOR DOUBLE FLOORING | |
CN100585112C (en) | Installation method for building decorative board | |
CN211949245U (en) | Roof stone flashing structure | |
CN210067247U (en) | Rigid-flexible composite waterproof structure | |
CN207974445U (en) | Ground paving system | |
CN217537712U (en) | Finish coat structure convenient to dismouting | |
JP2005146775A (en) | Semiconductive sheet and sheet waterproof structure | |
CN213675527U (en) | Ground module composite device on assembled ground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |