CN1935622B CN2005100297790A CN200510029779A CN1935622B CN 1935622 B CN1935622 B CN 1935622B CN 2005100297790 A CN2005100297790 A CN 2005100297790A CN 200510029779 A CN200510029779 A CN 200510029779A CN 1935622 B CN1935622 B CN 1935622B
Authority
CN
China
Prior art keywords
wall
attaching crane
crane frame
attaching
slideway shelf
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2005100297790A
Other languages
Chinese (zh)
Other versions
CN1935622A (en
Inventor
吴欣之
潘令誉
严时汾
陈晓明
薛备芬
陈正大
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN2005100297790A priority Critical patent/CN1935622B/en
Publication of CN1935622A publication Critical patent/CN1935622A/en
Application granted granted Critical
Publication of CN1935622B publication Critical patent/CN1935622B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a wall attachment crane, especially a self-elevating wall attachment crane, comprising attachment self-elevating mechanism and hoisting equipment, where extension of hydraulic oil cylinder of the attachment self-elevating mechanism makes wall attachment crane frame and runner frame slide on the outer wall of a kernel cylinder in turn, so as to support attachment in turn of wall attachment crane frame anchor bolt and runner frame anchor bolt on the outer wall of the kernel cylinder, thus meeting the requirements of self-elevating on the outer wall of the kernel cylinder. And it has functions of self-elevating attached to the outer wall of the kernel cylinder according to the given requirements and performing hoisting operation; and it largely improves economy; it adopts a combined structure, simplifies assembly and disassembly and the wall attachment crane frame can be equipped with the hoisting equipment and other matching construction equipment.

Description

Be used to have the self-lifting wall-attaching crane of the construction of super highrise building of core tube
Technical field
The present invention relates to a kind of wall-attaching crane, particularly a kind of self-lifting wall-attaching crane that is used to have the construction of super highrise building of core tube.
Background technology
Wall-attaching crane is a kind of seeking connections with at building or other structural special purpose crane tools, rational in infrastructure, economical and practical because of it, so application surface is wider, but because of its manoevreability poor, use less at the realm of building construction, and, can not be applied to have the construction of the high-rise building of core tube because of it does not have in building structure soaring voluntarily function.
Summary of the invention
The objective of the invention is to overcome the deficiency that wall-attaching crane can not rise voluntarily in building structure, it is had in building structure by the soaring voluntarily function of the requirement of setting, thereby can seek connections with in the core drum outer wall, be applied to have the exterior hoisting operation of core tube of the high-rise building of core tube.The present invention is designed for the self-lifting wall-attaching crane of the construction of super highrise building with core tube, comprise by seeking connections with crab-bolt, slideway shelf, the wall-attaching crane frame, compositions such as hydraulic ram seek connections with self-hoisting unit of TQ 60/80 and weight-lifting equipment, it is characterized in that: anchor hole is arranged on slideway shelf, can be connected and fixed by slideway shelf crab-bolt and core tube, anchor hole is also arranged on the wall-attaching crane frame, can be connected and fixed by wall-attaching crane frame crab-bolt and core tube, hydraulic ram is fixed in the wall-attaching crane frame, the external part of hydraulic ram can be connected and fixed with connecting pin and hydraulic ram counter-force seat, hydraulic ram counter-force seat is fixed on the slideway shelf, there is slideway the both sides of slideway shelf, there is slide block the both sides of wall-attaching crane frame, the slide block of wall-attaching crane frame embeds in the slideway of slideway shelf both sides, the wall-attaching crane frame is in the slideway shelf front, can slide up and down in the slideway shelf front along slideway by the flexible of hydraulic ram, on the wall-attaching crane frame, weight-lifting equipment is installed.The wall-attaching crane frame is connected and fixed with connecting pin and slideway shelf.The sequence of erection of self-lifting wall-attaching crane is: 1. press the anchor hole position dimension of self-lifting wall-attaching crane and the soaring track of setting at the core drum outer wall, preset slideway shelf crab-bolt and wall-attaching crane frame crab-bolt; 2. slideway shelf is fixedly connected on the core drum outer wall by the slideway shelf crab-bolt; 3. the wall-attaching crane frame is installed in the front of slideway shelf, and the slide block of wall-attaching crane frame is embedded in the slideway of slideway shelf; 4. hydraulic ram stretches out and withstands oil cylinder counter-force seat, and the external part of hydraulic ram is connected and fixed with connecting pin and hydraulic ram counter-force seat; 5. the wall-attaching crane frame is connected and fixed with connecting pin and slideway shelf; 6. the wall-attaching crane frame is fixedly connected on the core drum outer wall by wall-attaching crane frame crab-bolt; 7. on the wall-attaching crane frame, weight-lifting equipment is installed.The soaring voluntarily program of self-lifting wall-attaching crane is: 1. remove the wall-attaching crane frame crab-bolt that wall-attaching crane frame and core tube are connected and fixed; 2. remove the connecting pin that is connected and fixed wall-attaching crane frame and slideway shelf; 3. by the elongation of hydraulic ram, make the wall-attaching crane frame along moving on to assigned address on the slideway shelf; 4. wall-attaching crane frame crab-bolt is installed, the wall-attaching crane frame is fixedly connected on the core drum outer wall; 5. remove the slideway shelf crab-bolt that slideway shelf and core tube are connected and fixed; 6. by the contraction of hydraulic lifting oil cylinder, make slideway shelf make progress slippage to assigned address along the wall-attaching crane frame; 7. the connecting pin that is connected and fixed wall-attaching crane frame and slideway shelf is installed; 8. the slideway shelf crab-bolt is installed, slideway shelf is fixedly connected on the core drum outer wall.
Advantage of the present invention is: 1. overcome wall-attaching crane and fixedly sought connections with in building structure, the deficiency that can not rise voluntarily, make it have the function that in building structure, upwards rises voluntarily, make its field of application expand the lifting construction field of high-rise building to core tube by the setting requirement; 2. self-lifting wall-attaching crane is sought connections with in building structure, transmits deadweight and operation load and anti-tilting complex torque etc. by building structure, compares with general tower crane tool, has saved supporting and balance components such as body of the tower, equilibrium arm, foundary weight, and economy improves greatly; 3. the present invention adopts the unitized construction of seeking connections with self-hoisting unit of TQ 60/80 and weight-lifting equipment, not only reduced the lifting requirement of Assembly ﹠Disassembly accessory equipment of the present invention, reduced the difficulty of Assembly ﹠Disassembly work, and the weight-lifting equipment of installing on the wall-attaching crane frame can be selected the movable arm type wall-attaching crane for use according to engineering specifications and requirement of engineering, the also optional horizontal arm type wall-attaching crane of using, other preparation of construction that mate with the wall-attaching crane frame also can be installed, be combined into the self-lifting wall-attaching construction machinery and equipment of other purposes.
Description of drawings
Below in conjunction with drawings and Examples the present invention is elaborated
Accompanying drawing 1 (a) is a structural representation of the present invention, and Fig. 1 (b) is the birds-eye view of Fig. 1 (a), and Fig. 1 (c) is the side schematic view of the installation weight-lifting equipment of Fig. 1 of the present invention (a),
Accompanying drawing 2 (a) is the wall-attaching crane frame of the present invention scheme drawing of soaring initial bit voluntarily, Fig. 2 (b) is the side schematic view that weight-lifting equipment is installed of Fig. 2 (a), scheme drawing after Fig. 2 (c) rises for wall-attaching crane frame of the present invention is soaring voluntarily, Fig. 2 (d) is the side schematic view that weight-lifting equipment is installed of Fig. 2 (c), accompanying drawing 3 (a) is the soaring voluntarily initial bit scheme drawing of slideway shelf of the present invention, Fig. 3 (b) is the side schematic view that weight-lifting equipment is installed of Fig. 3 (a), scheme drawing after Fig. 3 (c) climbs for slideway shelf of the present invention is soaring voluntarily, Fig. 3 (d) is the side schematic view that weight-lifting equipment is installed of Fig. 3 (c).
The specific embodiment
Self-lifting wall-attaching crane in the accompanying drawing 1,2,3 is according to parameters such as the construction operating radius of needs and the biggest lifting capacities, buying or self design weight-lifting equipment 9, according to parameters such as the deadweight of this weight-lifting equipment 9 and peak loads, manufacture and design wall-attaching crane frame 2 and wall-attaching crane frame crab-bolt 4, parameters such as deadweight according to this weight-lifting equipment 9 and wall-attaching crane frame 2, manufacture and design slideway shelf 1 and slideway shelf crab-bolt 3, according to the parameters such as deadweight of this weight-lifting equipment 9 and wall-attaching crane frame 2, buying and installation hydraulic ram 5.
On slideway shelf 1, anchor hole is arranged, can be connected and fixed by slideway shelf crab-bolt 3 and core tube, anchor hole is also arranged on the wall-attaching crane frame 2, can be connected and fixed by wall-attaching crane frame crab-bolt 4 and core tube, hydraulic ram 5 is fixed in the wall-attaching crane frame 2, the external part of hydraulic ram 5 can be connected and fixed with connecting pin 6 and hydraulic ram counter-force seat 7, hydraulic ram counter-force seat 7 is fixed on the slideway shelf 1, there is slideway the both sides of slideway shelf 1, there is slide block the both sides of wall-attaching crane frame 2, the slide block of wall-attaching crane frame 2 embeds in the slideway of slideway shelf 1 both sides, wall-attaching crane frame 2 is in slideway shelf 1 front, can slide up and down in slideway shelf 1 front along slideway by the flexible of hydraulic ram 5, weight-lifting equipment 9 is installed on wall-attaching crane frame 2.Wall-attaching crane frame 2 usefulness connecting pins 8 are connected and fixed with slideway shelf 1, and the self-lifting wall-attaching crane that the manufacturing assembling is finished is standby after bug check is qualified.
The use Assembly ﹠Disassembly of self-lifting wall-attaching crane adopts the method for partial installation and dismounting, concrete sequence of erection is: 1. press the anchor hole position dimension of self-lifting wall-attaching crane and the soaring track of setting at the core drum outer wall, preset slideway shelf crab-bolt 3 and wall-attaching crane frame crab-bolt 4; 2. slideway shelf 1 is fixedly connected on the core drum outer wall by slideway shelf crab-bolt 3; 3. wall-attaching crane frame 2 is installed in the front of slideway shelf 1, and the slide block of wall-attaching crane frame 2 is embedded in the slideway of slideway shelf 1; 4. hydraulic ram 5 stretches out and withstands oil cylinder counter-force seat 6, and the external part of hydraulic ram 5 is connected and fixed with connecting pin 6 and hydraulic ram counter-force seat 7; 5. wall-attaching crane frame 2 usefulness connecting pins 8 are connected and fixed with slideway shelf 1; 6. wall-attaching crane frame 2 is fixedly connected on the core drum outer wall by wall-attaching crane frame crab-bolt 4; 7. weight-lifting equipment 9 is installed on wall-attaching crane frame 2.
The soaring voluntarily program of self-lifting wall-attaching crane is: 1. remove the wall-attaching crane frame crab-bolt 4 that wall-attaching crane frame 2 and core tube are connected and fixed; 2. remove the connecting pin 8 that is connected and fixed wall-attaching crane frame 2 and slideway shelf 1; 3. by the elongation of hydraulic ram 5, make wall-attaching crane frame 2 along moving on to assigned address on the slideway shelf 1; 4. wall-attaching crane frame crab-bolt 4 is installed, wall-attaching crane frame 2 is fixedly connected on the core drum outer wall; 5. remove the slideway shelf crab-bolt 3 that slideway shelf 1 and core tube are connected and fixed; 6. by the contraction of hydraulic lifting oil cylinder 5, make slideway shelf 1 make progress slippage to assigned address along wall-attaching crane frame 2; 7. the connecting pin 7 that is connected and fixed wall-attaching crane frame 2 and slideway shelf 1 is installed; 8. slideway shelf crab-bolt 3 is installed, slideway shelf 1 is fixedly connected on the core drum outer wall.Be that this finishes a soaring program, by this program repetitive operation, self-lifting wall-attaching crane is soaring voluntarily behind the height of demand, just can begin hoisting operation.
Hoisting operation can be pressed the opposite sequence of self-lifting wall-attaching crane installation method after finishing under the cooperation of accessory equipment, substep is dismantled self-lifting wall-attaching crane, finishes construction overall process.

Claims (4)

1. be used to have the self-lifting wall-attaching crane of the construction of super highrise building of core tube, comprise by seeking connections with crab-bolt, slideway shelf, the wall-attaching crane frame, hydraulic ram is formed seeks connections with self-hoisting unit of TQ 60/80 and weight-lifting equipment, it is characterized in that: anchor hole is arranged on slideway shelf, can be connected and fixed by slideway shelf crab-bolt and core tube, anchor hole is also arranged on the wall-attaching crane frame, can be connected and fixed by wall-attaching crane frame crab-bolt and core tube, hydraulic ram is fixed in the wall-attaching crane frame, the external part of hydraulic ram can be connected and fixed with connecting pin and hydraulic ram counter-force seat, hydraulic ram counter-force seat is fixed on the slideway shelf, there is slideway the both sides of slideway shelf, there is slide block the both sides of wall-attaching crane frame, the slide block of wall-attaching crane frame embeds in the slideway of slideway shelf both sides, the wall-attaching crane frame is in the slideway shelf front, can slide up and down in the slideway shelf front along slideway by the flexible of hydraulic ram, on the wall-attaching crane frame, weight-lifting equipment is installed.
2. by the described self-lifting wall-attaching crane that is used to have the construction of super highrise building of core tube of claim 1, it is characterized in that: the wall-attaching crane frame is connected and fixed with connecting pin and slideway shelf.
3. by the described self-lifting wall-attaching crane that is used to have the construction of super highrise building of core tube of claim 1, it is characterized in that: the sequence of erection of self-lifting wall-attaching crane is: 1. press the anchor hole position dimension of self-lifting wall-attaching crane and the soaring track of setting at the core drum outer wall, preset slideway shelf crab-bolt and wall-attaching crane frame crab-bolt; 2. slideway shelf is fixedly connected on the core drum outer wall by the slideway shelf crab-bolt; 3. the wall-attaching crane frame is installed in the front of slideway shelf, and the slide block of wall-attaching crane frame is embedded in the slideway of slideway shelf; 4. hydraulic ram stretches out and withstands oil cylinder counter-force seat, and the external part of hydraulic ram is connected and fixed with connecting pin and hydraulic ram counter-force seat; 5. the wall-attaching crane frame is connected and fixed with connecting pin and slideway shelf; 6. the wall-attaching crane frame is fixedly connected on the core drum outer wall by wall-attaching crane frame crab-bolt; 7. on the wall-attaching crane frame, weight-lifting equipment is installed.
4. by the described self-lifting wall-attaching crane that is used to have the construction of super highrise building of core tube of claim 1, it is characterized in that: the soaring voluntarily program of self-lifting wall-attaching crane is: 1. remove the wall-attaching crane frame crab-bolt that wall-attaching crane frame and core tube are connected and fixed; 2. remove the connecting pin that is connected and fixed wall-attaching crane frame and slideway shelf; 3. by the elongation of hydraulic ram, make the wall-attaching crane frame along moving on to assigned address on the slideway shelf; 4. wall-attaching crane frame crab-bolt is installed, the wall-attaching crane frame is fixedly connected on the core drum outer wall; 5. remove the slideway shelf crab-bolt that slideway shelf and core tube are connected and fixed; 6. by the contraction of hydraulic lifting oil cylinder, make slideway shelf make progress slippage to assigned address along the wall-attaching crane frame; 7. the connecting pin that is connected and fixed wall-attaching crane frame and slideway shelf is installed; 8. the slideway shelf crab-bolt is installed, slideway shelf is fixedly connected on the core drum outer wall.
CN2005100297790A 2005-09-20 2005-09-20 Self-lifting wall-attaching crane for superhigh-rise building construction with core drum Expired - Fee Related CN1935622B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2005100297790A CN1935622B (en) 2005-09-20 2005-09-20 Self-lifting wall-attaching crane for superhigh-rise building construction with core drum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2005100297790A CN1935622B (en) 2005-09-20 2005-09-20 Self-lifting wall-attaching crane for superhigh-rise building construction with core drum

Publications (2)

Publication Number Publication Date
CN1935622A CN1935622A (en) 2007-03-28
CN1935622B true CN1935622B (en) 2010-10-27

Family

ID=37953399

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2005100297790A Expired - Fee Related CN1935622B (en) 2005-09-20 2005-09-20 Self-lifting wall-attaching crane for superhigh-rise building construction with core drum

Country Status (1)

Country Link
CN (1) CN1935622B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105366566A (en) * 2014-08-28 2016-03-02 三一汽车起重机械有限公司 Crane
CN105439005B (en) * 2014-08-28 2017-06-06 三一汽车起重机械有限公司 Crane
CN105293315B (en) * 2015-11-12 2017-03-08 山东恒堃机械有限公司 A kind of hanging device of assembled architecture prefabricated components

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1051023A (en) * 1989-10-16 1991-05-01 刘铭 Self-hoisting unit of tq 60/80 type tower crane
CN2133563Y (en) * 1992-05-27 1993-05-19 建设部长沙建筑机械研究所 External climbing tower crane
CN2184684Y (en) * 1994-01-17 1994-12-07 中国建筑第三工程局第二建筑安装工程公司 Self lifting high speed derrick lift
CN2189145Y (en) * 1994-04-29 1995-02-08 淄博市淄川再生资源公司 Climbing wall type crane

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1051023A (en) * 1989-10-16 1991-05-01 刘铭 Self-hoisting unit of tq 60/80 type tower crane
CN2133563Y (en) * 1992-05-27 1993-05-19 建设部长沙建筑机械研究所 External climbing tower crane
CN2184684Y (en) * 1994-01-17 1994-12-07 中国建筑第三工程局第二建筑安装工程公司 Self lifting high speed derrick lift
CN2189145Y (en) * 1994-04-29 1995-02-08 淄博市淄川再生资源公司 Climbing wall type crane

Also Published As

Publication number Publication date
CN1935622A (en) 2007-03-28

Similar Documents

Publication Publication Date Title
CN105544984A (en) Large-span steel structure jig frame integrity slip construction process
CN1935622B (en) Self-lifting wall-attaching crane for superhigh-rise building construction with core drum
CN201116267Y (en) Externally hung supporting device for internally climbing tower crane
CN208668817U (en) A kind of light-duty armored concrete formula precast stair
CN202575771U (en) Double-cylinder central hydraulic jacking device
CN109879179A (en) A kind of assembling type steel structure tower crane platform
CN111039197B (en) Construction method for reverse-order joint addition of jacking of internal-climbing tower crane
CN209770223U (en) Multi-stage lifting upright post of window cleaning machine
CN101580214A (en) Hydraulic lifting method for large-scale equipment
CN106150081B (en) A kind of no scaffold cast-in-place concrete system and without scaffold concrete cast-in-situ method
CN112609954B (en) Novel automatic climbing system in elevator shaft and construction method thereof
CN201738563U (en) Hydraulic climbing scaffold for building construction
CN211773642U (en) Pile pressing device convenient to move for construction engineering
CN111498735A (en) Auxiliary moving supporting device for prefabricated part for constructional engineering
CN211548833U (en) Combined type roof hanging cross beam
CN2775210Y (en) Adjustable control hydraulic support device for building structure construction
KR100427751B1 (en) An installation beam of tower-crane for an outer wall
CN209493853U (en) A kind of support frame structure of high-speed railway attaching scaffold
CN205668902U (en) There is attachment self tower crane of foundation underpinning device
CN201460183U (en) Integral type hydraulic lifting scaffold
CN218758620U (en) Assembled building construction platform
CN110242034A (en) A kind of Mobile operating platform and its installation method for the installation of high-altitude pipe-line equipment
CN2237085Y (en) Integrate lifting shuttlering of three shaft hinged telescopic lift pit shaft
CN217326460U (en) Creeping formwork system for concrete high pier pouring construction
CN204980794U (en) Elevator landing door jamb spare

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

Free format text: FORMER NAME: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 200072, Shanghai, 200 old Shanghai Road

Patentee after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 200072, Shanghai, 200 old Shanghai Road

Patentee before: Shanghai Mechanized Construction Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101027

Termination date: 20200920

CF01 Termination of patent right due to non-payment of annual fee