CN1920174A CN 200610017956 CN200610017956A CN1920174A CN 1920174 A CN1920174 A CN 1920174A CN 200610017956 CN200610017956 CN 200610017956 CN 200610017956 A CN200610017956 A CN 200610017956A CN 1920174 A CN1920174 A CN 1920174A
Authority
CN
China
Prior art keywords
pocket
concrete
aggregate chips
fine sand
rubble
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610017956
Other languages
Chinese (zh)
Other versions
CN100482890C (en
Inventor
王昱海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2006100179568A priority Critical patent/CN100482890C/en
Publication of CN1920174A publication Critical patent/CN1920174A/en
Application granted granted Critical
Publication of CN100482890C publication Critical patent/CN100482890C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention relates to a non-maintenance pitch road and relative construction, wherein said construction comprises: it constructs three layers or two layers, while the bottom is pore concrete, while said layer can be avoided; the upper layer is the high-density solid pitch concrete, which uses mine powder to replace some pitch via bag theory and particle package theory; the mass percentages (kg/m3) after replacement are broken stone at 1276-2146, chip at 518-680, fine sand at 120-280, pitch at 80-155 and fined mine powder at 0-60; the diameter ration of particles are broken stone: chip >=3.15; chip: fine sand >=3.15; find sand: grinded mine powder >=3.15; and the theory density is 1580-2880/3; and the production comprises: mixing and heating said raw materials, rolling and shaping. Since the invention uses bag theory, optimizes the mass ratio and particle diameter ratio, to improve the strength of pitch concrete and reduce the pollution.

Description

Maintenance free asphalt pavement surface and job practices
Technical field: the present invention relates to maintenance free asphalt pavement surface and the job practices used in a kind of various engineering construction.
Background technology: along with China's rapid economy development, the quickening of capital works rhythm, pavement asphalt concrete is widely used, and is in crucial position in our life equally, no matter be trip or lodging, we are using it every day.But, bituminous concrete processing and production, except that special requirement, the technology of employing and proportioning all are common ways, the defective of existence is that intensity is not high, bad easily, has influenced the road surface use, wastes a large amount of manpower and materials.
Summary of the invention: the present invention has overcome above defective, and a kind of energy conservation is provided, maintenance free asphalt pavement surface that overlength is durable and job practices.Described job practices is divided three layers or two-layer the construction, and bottom is a poor concrete, and the middle level is the graded broken stone layer, and the upper strata is the high compact bituminous concrete; Its upper strata high compact bituminous concrete is the theoretical and theoretical breeze replacing section pitch of using of particle parcel according to pocket, and the mixing ratio by weight after the displacement is (kg/m3) rubble 1276-2146, aggregate chips 518-680, fine sand 120-280, pitch 80-155, ground blast furnace slag 0-60; Particle diameter is than being rubble: aggregate chips 〉=3.15, and aggregate chips: fine sand 〉=3.15, fine sand: ground blast furnace slag 〉=3.15, solid density are 1580-2880/m3; Its production method is the above-mentioned material heating to be mixed stir roller-compaction.Because the present invention has adopted " pocket " theory, the construction of three floor height performances, and concrete strength is significantly improved, save a large amount of raw material, reduced pollution, and workability of the present invention is excellent, good endurance, maintenance-free, cost is low, thereby has good social benefit and economic benefit.
The specific embodiment: job practices of the present invention is divided three layers or two-layer the construction, and bottom is a poor concrete, and the middle level is the graded broken stone layer, and the upper strata is the high compact bituminous concrete; Its upper strata high compact bituminous concrete is the theoretical and theoretical breeze replacing section pitch of using of particle parcel according to pocket, and the mixing ratio by weight after the displacement is that the also available coarse sand of (kg/m3) rubble 1276-2146, aggregate chips replaces 518-680, the also available flyash of fine sand to replace 120-280, pitch 80-155, ground blast furnace slag 0-60; Particle diameter is than being rubble: aggregate chips 〉=3.15, and aggregate chips: fine sand 〉=3.15, fine sand: ground blast furnace slag 〉=3.15, cumulative volume are the 1050-1080 liter, solid density is 1580-2880/m3; Its production method is above-mentioned material to be mixed stir roller-compaction.
Described bottom poor concrete, mixing ratio by weight are that the also available coarse sand of (kg/m3) rubble 1276-2146, aggregate chips replaces 518-680, the also available flyash of fine sand to replace 120-280,32.5 class g cement 50-295; Particle diameter is than being rubble: aggregate chips 〉=3.15, aggregate chips: fine sand 〉=3.15; Its production method is above-mentioned material to be mixed stir roller-compaction.
Described middle level graded broken stone layer, mixing ratio by weight are that the also available coarse sand of (kg/m3) rubble 1276-2146, aggregate chips replaces 518-680, the also available flyash of fine sand to replace 120-280; Particle diameter is than being rubble: aggregate chips 〉=3.15, aggregate chips: fine sand 〉=3.15; Its production method is above-mentioned material to be mixed stir, roller-compaction, and this layer also can.
Adopt " pocket " theoretical and particle parcel theory in the present invention." pocket " theoretical its principle is that pocket itself does not have compressive strength, and dry grain does not have compressive strength yet; When we pack into pocket and make grain closely knit of grain, the loading pocket shows good anti-pressure ability, and grain is closely knit more, the compressive strength of loading pocket is higher; In concrete, the gelling thing is the effect of effect-immediate shipment grain pocket that hoop is reined in thing to what gathered materials, is grain in the pocket and gather materials; In " pocket " theory, concrete strength is relevant with two factors, i.e. the packing density that the hoop of gelling deposits yields is reined in power and gathered materials.Theoretical its principle of particle parcel is gathered materials for i.e. thin one-level and is used for the thick one-level of parcel and gathers materials, make can gluing between gathering materials together.That is to say that aggregate chips is filled into by rubble to be piled up in the space that forms; Breeze is filled into aggregate chips and piles up in the space that forms; Gathering materials has minimum porosity, has maximum packing density, produces maximum intensity, maximum durability.
In order to guarantee the high strength requirement of high dense asphalt concrete, my door is theoretical according to " pocket " theory and particle parcel, can produce minimum porosity in gathering materials, and guarantees suitable particle diameter ratio and the part by weight of material, thereby formed high strength, high durable high dense asphalt concrete.
High dense asphalt concrete is meant 7 days following high strength asphalt concretes of the above 10MPa of intensity 1MPa.Bituminous concrete according to above match ratio preparation designs density in theory and can reach 2580-2880/m3, and construction density can reach 2500-2800/m3, and the homogenieity permeability resistance durability of bituminous concrete and rutting resistance all obviously improve.

Claims (5)

1, a kind of maintenance free asphalt pavement surface and job practices is characterized in that three layers of branches or two-layer the construction, and bottom is a poor concrete, and the middle level is a dirt graded broken stone layer, this layer also can, the upper strata is the high compact bituminous concrete; Its upper strata high compact bituminous concrete is the theoretical and theoretical breeze replacing section pitch of using of particle parcel according to pocket, and the mixing ratio by weight after the displacement is (kg/m3) rubble 1276-2146, aggregate chips 518-680, fine sand 120-280, pitch 80-155, ground blast furnace slag 0-60; Particle diameter is than being rubble: aggregate chips 〉=3.15, and aggregate chips: fine sand 〉=3.15, fine sand: ground blast furnace slag 〉=3.15, solid density are 1580-2880/m3; Its production method is the above-mentioned material heating to be mixed stir roller-compaction.
2, maintenance free asphalt pavement surface according to claim 1 and job practices is characterized in that the bottom poor concrete, and mixing ratio by weight is (kg/m3) rubble 1276-2146, aggregate chips 518-680, fine sand 120-280,32.5 class g cement 50-295; Particle diameter is than being rubble: aggregate chips 〉=3.15, aggregate chips: fine sand 〉=3.15; Its production method is that above-mentioned material mixes and stirs roller-compaction.
3, maintenance free asphalt pavement surface according to claim 1 and job practices is characterized in that middle level graded broken stone layer, and mixing ratio by weight is (kg/m3) rubble 1276-2146, aggregate chips 518-680, fine sand 120-280; Particle diameter is than being rubble: aggregate chips 〉=3.15, aggregate chips: fine sand 〉=3.15; Its production method is above-mentioned material to be mixed stir, roller-compaction, and this layer also can.
4, maintenance free asphalt pavement surface according to claim 1 and job practices is characterized in that adopting " pocket " theory, and its principle is that pocket itself does not have compressive strength, and dry grain does not have compressive strength yet; When we pack into pocket and make grain closely knit of grain, the loading pocket shows good anti-pressure ability, and grain is closely knit more, the compressive strength of loading pocket is higher; In concrete, the gelling thing is the effect of effect-immediate shipment grain pocket that hoop is reined in thing to what gathered materials, is grain in the pocket and gather materials; In " pocket " theory, concrete strength is relevant with two factors, i.e. the packing density that the hoop of gelling deposits yields is reined in power and gathered materials.Its principle is gathered materials for i.e. thin one-level and is used for being filled into thick one-level and gathers materials and pile up in the space that forms, and makes a space that gathers materials reach minimum, and it is maximum that packing density reaches.That is to say that sand is filled into by rubble to be piled up in the space that forms; Cement is in the space of filling sand heap-shaped one-tenth; Ground blast furnace slag is filled into cement and piles up in the formation space; Water is filled into ground blast furnace slag and piles up in the space that forms; If ground blast furnace slag is enough thin, be enough to filling concrete and form the space, and the space that ground blast furnace slag forms has only water to fill, gathering materials has minimum porosity emin=0, has maximum packing density.
5, maintenance free asphalt pavement surface according to claim 1 and job practices is characterized in that adopting the particle parcel theoretical, that is to say: pitch parcel sandstone material, and bonding sandstone material, and make the sandstone material become piece, in bituminous concrete, play the effect of gelling thing.
CNB2006100179568A 2006-06-07 2006-06-07 Maintenance free asphalt pavement surface and construction method thereof Expired - Fee Related CN100482890C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100179568A CN100482890C (en) 2006-06-07 2006-06-07 Maintenance free asphalt pavement surface and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100179568A CN100482890C (en) 2006-06-07 2006-06-07 Maintenance free asphalt pavement surface and construction method thereof

Publications (2)

Publication Number Publication Date
CN1920174A true CN1920174A (en) 2007-02-28
CN100482890C CN100482890C (en) 2009-04-29

Family

ID=37778004

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100179568A Expired - Fee Related CN100482890C (en) 2006-06-07 2006-06-07 Maintenance free asphalt pavement surface and construction method thereof

Country Status (1)

Country Link
CN (1) CN100482890C (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105524475A (en) * 2014-09-30 2016-04-27 北京路新大成景观建筑工程有限公司 Flexible asphalt, preparation method therefor, road pavement material and road
CN105648865A (en) * 2016-02-02 2016-06-08 上海建工集团股份有限公司 Paving method for tropical zone road surface
CN107226641A (en) * 2017-06-30 2017-10-03 淮阴工学院 Alkaline residue regenerative micro powder is bituminous concrete of filler and preparation method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105524475A (en) * 2014-09-30 2016-04-27 北京路新大成景观建筑工程有限公司 Flexible asphalt, preparation method therefor, road pavement material and road
CN105648865A (en) * 2016-02-02 2016-06-08 上海建工集团股份有限公司 Paving method for tropical zone road surface
CN107226641A (en) * 2017-06-30 2017-10-03 淮阴工学院 Alkaline residue regenerative micro powder is bituminous concrete of filler and preparation method thereof

Also Published As

Publication number Publication date
CN100482890C (en) 2009-04-29

Similar Documents

Publication Publication Date Title
CN104891888B (en) A kind of imitative stone material environment-friendly concrete pavior brick and its manufacture method
CN101619557B (en) Pavement base course material prepared from brick mixed building rubbish regenerated aggregate and preparation method thereof
CN109231894A (en) A kind of road asphalt mixture and preparation method thereof
CN105924038B (en) Thermal resistance degrading tail gas type asphalt pavement structure
CN107226648A (en) A kind of diamond dust mine tailing composite sand base ecological permeable bricks and preparation method thereof
CN106587835A (en) Cold-mixed cement-emulsified asphalt concrete and pavement method thereof
CN106116395A (en) A kind of inorganic colloid methoder as road subbase course filler and compound method thereof
CN203346730U (en) Ballast track embankment bedding structure for municipal railways
CN108532401A (en) A kind of coral sand concrete road surface structure and its construction method
CN100482890C (en) Maintenance free asphalt pavement surface and construction method thereof
CN100364918C (en) Inorganic regenerated concrete mixture and its preparing method
CN105926400A (en) Green low-carbon environment-friendly asphalt pavement structure
CN107365145A (en) Water-permeable brick and its application
CN102444116A (en) Construction waste regenerated aggregate concrete pile and soil foundation treatment method thereof
CN101244910A (en) Broken stone water permeability pavement mixture with epoxy resin as adhesive agent
CN102505682A (en) Building waste powder cement pile and foundation treatment method thereof
KR102073375B1 (en) Composition for soil pavement including woodchip and construction method of soil pavement using the same
CN108101450A (en) A kind of cement stabilized base course material and its design method
CN201826241U (en) Low-carbon, energy-saving and environment-friendly road pavement
CN201495466U (en) Roadbed constructed by utilizing recycled aggregate from brick and concrete construction waste
CN106517944A (en) Solidified granular soil produced by utilizing waste and old materials from building project
CN104692771B (en) It is combined prepared road pavements of mud and preparation method thereof with building waste
CN201169737Y (en) Water seepage runway
CN106746911A (en) A kind of environmental protection water-permeable brick and preparation method thereof
CN114560669A (en) Curing agent-stabilized coal gangue mixture for road base and preparation method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090429

Termination date: 20140607

EXPY Termination of patent right or utility model