CN102505682A - Building waste powder cement pile and foundation treatment method thereof - Google Patents

Building waste powder cement pile and foundation treatment method thereof Download PDF

Info

Publication number
CN102505682A
CN102505682A CN201110335985XA CN201110335985A CN102505682A CN 102505682 A CN102505682 A CN 102505682A CN 201110335985X A CN201110335985X A CN 201110335985XA CN 201110335985 A CN201110335985 A CN 201110335985A CN 102505682 A CN102505682 A CN 102505682A
Authority
CN
China
Prior art keywords
building waste
stake
slag
building
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201110335985XA
Other languages
Chinese (zh)
Inventor
吴俊喜
王亦德
吴鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG HONGTAI CONSTRUCTION GROUP CO Ltd
Original Assignee
SHANDONG HONGTAI CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG HONGTAI CONSTRUCTION GROUP CO Ltd filed Critical SHANDONG HONGTAI CONSTRUCTION GROUP CO Ltd
Priority to CN201110335985XA priority Critical patent/CN102505682A/en
Publication of CN102505682A publication Critical patent/CN102505682A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/91Use of waste materials as fillers for mortars or concrete

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The invention discloses a building waste powder cement pile and a foundation treatment method thereof. The building waste powder cement pile is made of cement and building waste powder. The preparation method comprises process steps of crushing, screening, mixing, drilling, filling, ramming, pile forming and the like. The building waste powder cement pile and the foundation treatment method have the advantages that the problem that most building wastes cannot be fully utilized is solved, the building waste powder and particles are used for building foundations, the building wastes are fully utilized, a new approach is developed for fully utilizing the building wastes, the building waste powder cement pile can be widely for building engineering such as railways, roads, houses and the like, the bearing capacity of the building foundations which are treated by adopting the method can full satisfy the requirements of building design, the treatment cost is low, the cost is saved, the effective utilization ratio of the wastes is improved and the economic benefit is realized.

Description

A kind of building waste ground-slag concrete stake and method for processing foundation thereof
Technical field
The present invention relates to a kind of building lot, specifically a kind of building waste ground-slag concrete stake and method for processing foundation thereof belong to the building lot field.
Background technology
Along with the raising and the industrialized development of national economy, existing building all has a lot of buildings need remove reconstruction because of reaching the problem of rationally utilizing aspects such as soil data at function, the time limit every year, and the building waste of generation will get more and more.The quantity of China's building waste has accounted for about 40% of municipal refuse at present, and the pollution that building waste produces is equivalent to the twice of motor vehicle emission tail gas.The harm that building waste brings has obtained the abundant attention of all circles.Yet the building waste that building produced is because of the difference of various types of composition and content, thereby need distinguish utilization according to its performance.Urban architecture is at present removed rubbish and generally mostly is brick mix structure, brickbat and the mortar of the rubbish that is produced nearly 80% for building a wall and forming, nearly 10% concrete block.
At present, it mainly is to use concrete wherein to make regeneration aggregate that building waste utilizes again, produce the concrete brick and be used for the not high positions of compressive strength such as roadbed, foundation pad and non-structural part, thereby consumption is little, and the scope of application is narrow.The regeneration aggregate of producing is to process after crushing and screening cleans with the concrete in the building waste basically; But a large amount of concrete pieces and mortar do not obtain utilizing yet; Mainly be because the intensity of brick body is low; The regeneration concrete aggregate of making is difficult to meet the requirements of design strength, so very most building waste can not be utilized.
Low-intensity rammed concrete pile foundation treatment technology is widely used in the construction works such as railway, highway and house, uses that structure foundation bearing capacity after this technical finesse is high, distortion is little, and it is low to handle cost, thereby is widely used.Low-strength cement soil stake is in Ground Treatment, because the acting in conjunction of stake and soil, its pile body is stressed little, so low to the compressive strength of the cement-soil of pile body requirement.The compressive strength of cement-soil is generally at 1-5MPa, and consumption is big, and in order to reduce the distortion on road, all full hall arranges that the stake diameter is in 500 millimeter like speedway, railway etc., and consumption is big, requirement of strength is low.
Summary of the invention
In order to address the above problem, the present invention has designed a kind of building waste ground-slag concrete stake and method for processing foundation thereof, and this method is through pulverizing, sieve building rubbish; Process rubbish ground-slag concrete stake then, carry out long auger at last and ram and to fill into stake, adopt the structure foundation bearing capacity after this method identical with the effect of the former raw material of use; Be out of shape for a short time, and it is low to handle cost, provides cost savings; Improve the effective rate of utilization of refuse, realized economic benefit.
Technical scheme of the present invention is:
A kind of building waste ground-slag concrete stake comprises cement and building waste ground-slag, and described building waste ground-slag is a particle diameter less than 2 millimeters building waste ground-slag particle; The mass ratio of described cement and building waste ground-slag is 1 ︰ 6~8, and said building waste ground-slag concrete stake compressive strength is 1-5MPa.
A kind of method for processing foundation of building waste ground-slag concrete stake may further comprise the steps:
(1) with the building rubbish of removing comprise brick, watt, the piece material of stone, concrete pulverizes, sieves; Obtain particle diameter at 5~40 millimeters building waste coarse aggregate and particle diameter building waste fines, and remaining particle diameter is less than 2 millimeters building waste ground-slag particle at 2~5 millimeters; Particle diameter is used to prepare the plain concrete stake of building refuse regeneration aggregate at 5~40 millimeters building waste coarse aggregate and particle diameter at 2~5 millimeters building waste fines;
(2) particle diameter that above-mentioned steps (1) is obtained is less than 2 millimeters building waste ground-slag particle and the cement mixed according to mass ratio 1 ︰ 6~8;
(3) boring is rammed and is filled into stake, comprising:
3.1 boring:, hole through a kind of mode in immersed tube, impact, luoyang spade, the auger according to the requirement of architectural design;
Be drilled to the hole 3.2 carry: carry brill after the degree of depth that reaches the architectural design requirement of holing, carry the drilling speed degree and want evenly slowly, speed controlling obtains a hole at 1.2-1.5m/min;
Fill out 3.3 ram in the hole: compacting before the filler of stake hole, the rammer on stake top are filled out aspect ratio design stake heights of roofs and are exceeded the 200-300 millimeter, stake end face level; The rubbish ground-slag concrete stake material that above-mentioned steps (2) is obtained is filled in the hole, mechanical then segmentation compacting pile hole, and coefficient of consolidation is greater than 0.95; Stake hole centre deviation is no more than 1/4 of stake footpath design load, and the vertical degree of the peg hole deviation is less than 1.5%, and the stake bore dia is greater than design stake footpath, and the stake hole depth is dark greater than projected depth, obtains the rubbish ground-slag concrete stake of compressive strength at 1-5MPa.
The brick-and-concrete buildings rubbish green strength of removing is generally more than 7.5 MPa; Through broken and screening back according to different particle diameters, particle diameter is used as the concrete of regenerating at 5~40 millimeters building waste coarse aggregate and particle diameter at 2~5 millimeters building waste fines coarse aggregate and fines; Obtain particle diameter after the screening less than 2 millimeters building waste ground-slag particle; Add cement and make compacting concrete stake material; Be used for requirement after treatment low building of bearing capacity also can satisfy designing requirement, calcium oxide combines to react with silicon property material in the cement, and the pile strength of cement can be provided; The excellent cement of pile quality is practiced thrift cement simultaneously with the cooperation of soil.
The invention has the advantages that: solved the problem that most of building waste can not be fully utilized; Building waste ground-slag particle is applied to building lot, building waste is fully used, developed a new way that makes full use of building waste; Can be widely used in the construction works such as railway, highway and house; Structure foundation bearing capacity after employing the inventive method can reach the requirement of architectural design fully, and it is low to handle cost, provides cost savings; Improve the effective rate of utilization of refuse, realized economic benefit.
The specific embodiment
Below the preferred embodiments of the present invention are described, should be appreciated that preferred embodiment described herein only is used for explanation and explains the present invention, and be not used in qualification the present invention.
Embodiment 1
A kind of building waste ground-slag concrete stake comprises cement and building waste ground-slag, and described building waste ground-slag is the building waste ground-slag particle less than 2 millimeters; The mass ratio of described cement and building waste ground-slag is 1 ︰ 8, and said building waste ground-slag concrete stake compressive strength is 2MPa.
A kind of method for processing foundation of building waste ground-slag concrete stake may further comprise the steps:
(1) with the building rubbish of removing comprise brick, watt, the piece material of stone, concrete pulverizes, sieves; Obtain particle diameter at 5~40 millimeters building waste coarse aggregate and particle diameter building waste fines, and remaining particle diameter is less than 2 millimeters building waste ground-slag particle at 2~5 millimeters; Particle diameter is used to prepare the plain concrete stake of building refuse regeneration aggregate at 5~40 millimeters building waste coarse aggregate and particle diameter at 2~5 millimeters building waste fines;
(2) with above-mentioned steps (1) particle diameter less than 2 millimeters building waste ground-slag particle and cement mixed according to mass ratio 1 ︰ 8;
(3) boring is rammed and is filled into stake:
3.1 boring:, hole through a kind of mode in immersed tube, impact, luoyang spade, the auger according to the requirement of architectural design;
Be drilled to the hole 3.2 carry: carry brill after the degree of depth that reaches the architectural design requirement of holing, carry the drilling speed degree and want evenly slowly, speed controlling obtains a hole at 1.2m/min;
Fill out 3.3 ram in the hole: compacting before the filler of stake hole, the rammer on stake top are filled out aspect ratio design stake heights of roofs and are exceeded 200 millimeters, stake end face level; The rubbish ground-slag concrete stake material that above-mentioned steps (2) is obtained is filled in the hole, mechanical then segmentation compacting pile hole, and coefficient of consolidation is greater than 0.95; Stake hole centre deviation is no more than 1/4 of stake footpath design load, and the vertical degree of the peg hole deviation is 1%, and the stake bore dia is greater than design stake footpath, and the stake hole depth is dark greater than projected depth, obtains the rubbish ground-slag concrete stake of compressive strength at 2MPa.
Interpretation of result:
It is little to adopt structure foundation bearing capacity after this method can reach building intensity, the distortion identical with former raw material; And it is low to handle cost; Substituted former raw material, provided cost savings, every cube of concrete cost is than using former raw material to practice thrift 22%; And improved the effective rate of utilization of refuse, realized economic benefit.
Embodiment 2
A kind of building waste ground-slag concrete stake comprises cement and building waste ground-slag, and described building waste ground-slag is the building waste ground-slag particle less than 2 millimeters; The mass ratio of described cement and building waste ground-slag is 1 ︰ 7, and said building waste ground-slag concrete stake compressive strength is 3MPa.
A kind of method for processing foundation of building waste ground-slag concrete stake may further comprise the steps:
(1) with the building rubbish of removing comprise brick, watt, the piece material of stone, concrete pulverizes, sieves; Obtain particle diameter at 5~40 millimeters building waste coarse aggregate and particle diameter building waste fines, and remaining particle diameter is less than 2 millimeters building waste ground-slag particle at 2~5 millimeters; Particle diameter is used to prepare the plain concrete stake of building refuse regeneration aggregate at 5~40 millimeters building waste coarse aggregate and particle diameter at 2~5 millimeters building waste fines;
(2) with above-mentioned steps (1) particle diameter less than 2 millimeters building waste ground-slag particle and cement mixed according to mass ratio 1 ︰ 7;
(3) boring is rammed and is filled into stake:
3.1 boring:, hole through a kind of mode in immersed tube, impact, luoyang spade, the auger according to the requirement of architectural design;
Be drilled to the hole 3.2 carry: carry brill after the degree of depth that reaches the architectural design requirement of holing, carry the drilling speed degree and want evenly slowly, speed controlling obtains a hole at 1.4m/min;
Fill out 3.3 ram in the hole: compacting before the filler of stake hole, the rammer on stake top are filled out aspect ratio design stake heights of roofs and are exceeded 250 millimeters, stake end face level; The rubbish ground-slag concrete stake material that above-mentioned steps (2) is obtained is filled in the hole, mechanical then segmentation compacting pile hole, and coefficient of consolidation is greater than 0.95; Stake hole centre deviation is no more than 1/4 of stake footpath design load, and the vertical degree of the peg hole deviation is 1%, and the stake bore dia is greater than design stake footpath, and the stake hole depth is dark greater than projected depth, obtains the rubbish ground-slag concrete stake of compressive strength at 3MPa.
Interpretation of result:
It is little to adopt structure foundation bearing capacity after this method can reach building intensity, the distortion identical with former raw material; And it is low to handle cost; Substituted former raw material, provided cost savings, every cube of concrete cost is than using former raw material to practice thrift 19%; And improved the effective rate of utilization of refuse, realized economic benefit.
Embodiment 3
A kind of building waste ground-slag concrete stake comprises cement and building waste ground-slag, and described building waste ground-slag is the building waste ground-slag particle less than 2 millimeters; The mass ratio of described cement and building waste ground-slag is 1 ︰ 6, and said building waste ground-slag concrete stake compressive strength is 5MPa.
A kind of method for processing foundation of building waste ground-slag concrete stake may further comprise the steps:
(1) with the building rubbish of removing comprise brick, watt, the piece material of stone, concrete pulverizes, sieves; Obtain particle diameter at 5~40 millimeters building waste coarse aggregate and particle diameter building waste fines, and remaining particle diameter is less than 2 millimeters building waste ground-slag particle at 2~5 millimeters; Particle diameter is used to prepare the plain concrete stake of building refuse regeneration aggregate at 5~40 millimeters building waste coarse aggregate and particle diameter at 2~5 millimeters building waste fines;
(2) with above-mentioned steps (1) particle diameter less than 2 millimeters building waste ground-slag particle and cement mixed according to mass ratio 1 ︰ 6;
(3) boring is rammed and is filled into stake:
3.1 boring:, hole through a kind of mode in immersed tube, impact, luoyang spade, the auger according to the requirement of architectural design;
Be drilled to the hole 3.2 carry: carry brill after the degree of depth that reaches the architectural design requirement of holing, carry the drilling speed degree and want evenly slowly, speed controlling obtains a hole at 1.5m/min;
Fill out 3.3 ram in the hole: compacting before the filler of stake hole, the rammer on stake top are filled out aspect ratio design stake heights of roofs and are exceeded 300 millimeters, stake end face level; The rubbish ground-slag concrete stake material that above-mentioned steps (2) is obtained is filled in the hole, mechanical then segmentation compacting pile hole, and coefficient of consolidation is greater than 0.95; Stake hole centre deviation is no more than 1/4 of stake footpath design load, and the vertical degree of the peg hole deviation is 1%, and the stake bore dia is greater than design stake footpath, and the stake hole depth is dark greater than projected depth, obtains the rubbish ground-slag concrete stake of compressive strength at 5MPa.
Interpretation of result:
It is little to adopt structure foundation bearing capacity after this method can reach building intensity, the distortion identical with former raw material; And it is low to handle cost; Substituted former raw material, provided cost savings, every cube of concrete cost is than using former raw material to practice thrift 18%; And improved the effective rate of utilization of refuse, realized economic benefit.
What should explain at last is: the above is merely the preferred embodiments of the present invention; Be not limited to the present invention; Although the present invention has been carried out detailed explanation with reference to previous embodiment; For a person skilled in the art, it still can be made amendment to the technical scheme that aforementioned each embodiment put down in writing, and perhaps part technical characterictic wherein is equal to replacement.All within spirit of the present invention and principle, any modification of being done, be equal to replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (3)

1. building waste ground-slag concrete stake is characterized in that: be prepared from cement and building waste ground-slag, described building waste ground-slag is a particle diameter less than 2 millimeters building waste ground-slag particle; The mass ratio of described cement and building waste ground-slag is 1 ︰ 6~8; Said building waste ground-slag concrete stake compressive strength is 1-5MPa.
2. building waste ground-slag concrete stake according to claim 1 is characterized in that: the mass ratio of said cement and building waste ground-slag is 1 ︰ 7.
3. the method for processing foundation of a building waste ground-slag concrete stake as claimed in claim 1 is characterized in that, may further comprise the steps:
(1) with the building rubbish of removing comprise brick, watt, the piece material of stone, concrete pulverizes, sieves; Obtain particle diameter at 5~40 millimeters building waste coarse aggregate and particle diameter building waste fines at 2~5 millimeters; And remaining particle diameter is less than 2 millimeters building waste ground-slag particle, and particle diameter is used to prepare the plain concrete stake of building refuse regeneration aggregate at 5~40 millimeters building waste coarse aggregate and particle diameter at 2~5 millimeters building waste fines;
(2) particle diameter that above-mentioned steps (1) is obtained is less than 2 millimeters building waste ground-slag particle and the cement mixed according to mass ratio 1 ︰ 6~8;
(3) boring is rammed and is filled into stake
3.1 boring:, hole through a kind of mode in immersed tube, impact, luoyang spade, the auger according to the requirement of architectural design;
Be drilled to the hole 3.2 carry: carry brill after the degree of depth that reaches the architectural design requirement of holing, carry the drilling speed degree and want evenly slowly, speed controlling obtains a hole at 1.2-1.5m/min;
Fill out 3.3 ram in the hole: compacting before the filler of stake hole, the rammer on stake top are filled out aspect ratio design stake heights of roofs and are exceeded the 200-300 millimeter, stake end face level; The rubbish ground-slag concrete stake material that above-mentioned steps (2) is obtained is filled in the hole, mechanical then segmentation compacting pile hole, and coefficient of consolidation is greater than 0.95; Stake hole centre deviation is no more than 1/4 of stake footpath design load, and the vertical degree of the peg hole deviation is less than 1.5%, and the stake bore dia is greater than design stake footpath, and the stake hole depth is dark greater than projected depth, obtains the rubbish ground-slag concrete stake of compressive strength at 1-5MPa.
CN201110335985XA 2011-10-31 2011-10-31 Building waste powder cement pile and foundation treatment method thereof Pending CN102505682A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110335985XA CN102505682A (en) 2011-10-31 2011-10-31 Building waste powder cement pile and foundation treatment method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110335985XA CN102505682A (en) 2011-10-31 2011-10-31 Building waste powder cement pile and foundation treatment method thereof

Publications (1)

Publication Number Publication Date
CN102505682A true CN102505682A (en) 2012-06-20

Family

ID=46217809

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110335985XA Pending CN102505682A (en) 2011-10-31 2011-10-31 Building waste powder cement pile and foundation treatment method thereof

Country Status (1)

Country Link
CN (1) CN102505682A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104711976A (en) * 2015-01-27 2015-06-17 南昌大学 Construction waste recycled aggregate composite carrier pile and preparation method thereof
CN104711974A (en) * 2015-01-27 2015-06-17 南昌大学 Steel tube recycled concrete composite bearing base pile and manufacturing method thereof
CN105110712A (en) * 2015-08-26 2015-12-02 安徽芜湖飞琪水泥制品有限公司 High-rigidity cement pile and preparation method thereof
CN105110736A (en) * 2015-08-26 2015-12-02 安徽芜湖飞琪水泥制品有限公司 Construction waste slag powder cement pile and preparation method thereof
CN105236846A (en) * 2015-08-26 2016-01-13 安徽芜湖飞琪水泥制品有限公司 Compression-resistant cement pile and preparation method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1098758A (en) * 1993-08-11 1995-02-15 沧州市建筑安装工程公司机械施工分公司 The compacted pile work method of enlarging building refuse is rammed in the weight punching
EP0900883A1 (en) * 1997-09-04 1999-03-10 JOSEF MÖBIUS BAUGESELLSCHAFT (GmbH & Co.) Method and covering for making a column in the ground, which can carry loads from buildings or traffic
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1098758A (en) * 1993-08-11 1995-02-15 沧州市建筑安装工程公司机械施工分公司 The compacted pile work method of enlarging building refuse is rammed in the weight punching
EP0900883A1 (en) * 1997-09-04 1999-03-10 JOSEF MÖBIUS BAUGESELLSCHAFT (GmbH & Co.) Method and covering for making a column in the ground, which can carry loads from buildings or traffic
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王罗春等: "建筑垃圾作建筑渣土桩填料加固软土地基的机理与工艺", 《上海电力学院学报》 *
王罗春等: "旧建筑物拆除垃圾资源化研究现状", 《环境卫生工程》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104711976A (en) * 2015-01-27 2015-06-17 南昌大学 Construction waste recycled aggregate composite carrier pile and preparation method thereof
CN104711974A (en) * 2015-01-27 2015-06-17 南昌大学 Steel tube recycled concrete composite bearing base pile and manufacturing method thereof
CN105110712A (en) * 2015-08-26 2015-12-02 安徽芜湖飞琪水泥制品有限公司 High-rigidity cement pile and preparation method thereof
CN105110736A (en) * 2015-08-26 2015-12-02 安徽芜湖飞琪水泥制品有限公司 Construction waste slag powder cement pile and preparation method thereof
CN105236846A (en) * 2015-08-26 2016-01-13 安徽芜湖飞琪水泥制品有限公司 Compression-resistant cement pile and preparation method thereof

Similar Documents

Publication Publication Date Title
CN101139193B (en) Regenerative concrete composite material and method for making same
CN108842557B (en) Temporary road pavement structure and road building method
CN104891888B (en) A kind of imitative stone material environment-friendly concrete pavior brick and its manufacture method
CN104711974B (en) A kind of steel tube regeneration concrete complex carrier stake and preparation method thereof
CN106045399B (en) A kind of water-permeable brick and preparation method thereof
CN104711976B (en) A kind of construction refuse regenerated aggregate complex carrier stake and preparation method thereof
CN101265685A (en) Method for regenerating waste solid for use in road foundation
CN101956357A (en) Double-layer baking-free permeable brick and manufacturing method thereof
CN1963022A (en) Use method of industrial caustic dross in treatment of road bed and foundation
CN101265060A (en) Soil solidifying material and applying method thereof on heavy load soft ground foundation
CN102505682A (en) Building waste powder cement pile and foundation treatment method thereof
CN108505409B (en) Solidified muddy soil and construction waste regenerated aggregate composite inorganic material and forming method thereof
CN102444116A (en) Construction waste regenerated aggregate concrete pile and soil foundation treatment method thereof
CN203346730U (en) Ballast track embankment bedding structure for municipal railways
CN113754364A (en) Artificial aggregate based on muck sand washing tail mud and preparation method thereof
CN101250044A (en) Road subbase course material and method for preparing same
CN204753293U (en) Main line cement concrete pavement " bai jiahei " regeneration structure is economized by state
CN104909699A (en) Environment-friendly crack-resistant pavement base composition and preparation method thereof
CN112794682A (en) Premixed fluid solidified soil doped with high-silicon type iron tailings and preparation method thereof
CN104529322A (en) Iron tailings roller compacted concrete for pavement
CN112521101A (en) Modified medium weathering argillaceous siltstone filler and preparation method thereof
CN115215591B (en) Roadbed mixture and preparation method thereof
CN106906709A (en) A kind of construction method of the modified cement earth pile of quick lime
CN102731029A (en) Regenerated and utilizable subgrade engineering material and preparation method thereof
CN103952957B (en) Can the roadbase structure of solving problem of vehicle bump at bridge head

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120620