CN1799697A - Combined gold deposits tailings reclamation device - Google Patents

Combined gold deposits tailings reclamation device Download PDF

Info

Publication number
CN1799697A
CN1799697A CN 200410103975 CN200410103975A CN1799697A CN 1799697 A CN1799697 A CN 1799697A CN 200410103975 CN200410103975 CN 200410103975 CN 200410103975 A CN200410103975 A CN 200410103975A CN 1799697 A CN1799697 A CN 1799697A
Authority
CN
China
Prior art keywords
slide carriage
ore pulp
layer
equipment
distributor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200410103975
Other languages
Chinese (zh)
Other versions
CN1799697B (en
Inventor
商伯成
苏宪堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200410103975 priority Critical patent/CN1799697B/en
Publication of CN1799697A publication Critical patent/CN1799697A/en
Application granted granted Critical
Publication of CN1799697B publication Critical patent/CN1799697B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

The invention relates to an integrated banket tailings recovery device, which comprises: a submersible deep production device which comprises a bucket, a sand pump inside the bucket, a squirt gun and an ore pulp outlet pipe; an ore pulp divider; an ore pulp distributor and an ore pulp pick-flushing device. Wherein, said ore pulp divider can be divided into multi-path dividing pipes which each dividing pipe is connected to the chassis of each layer of distributor; said ore pulp pick-flushing device comprise: a slide carriage integration formed by multi-layer of slide carriages and it is connected to the square frame; the square frame is fixed on the steel ring which contacts the bearing inside the slot of rotary support; the back of each slide carriage is connected to the distributing pipe and the water spraying pipe, while the blowhole on the spraying pipe is opposite to the stock chest on the slide carriage. The invention can recover the gold body which is hard covered by other devices, with big treatment amount, high recovery rate, simple operation, non-pollution and wider application.

Description

A kind of combined gold deposits tailings reclamation device
Technical field
The present invention relates to a kind of high throughput, high-recovery gold deposits tailings reclamation device, particularly a kind of combined gold deposits tailings inclusion enclave retracting device.
Background technology
All there are some defectives in existing gold deposits tailings recovery method and device, though the treating capacity that for example has is big, its rate of recovery is low, the rate of recovery height that has, and treating capacity is relatively low.Particularly, still do not have effective retracting device so far, therefore be necessary to provide a kind of both rate of recovery height, the gold deposits tailings inclusion enclave retracting device that treating capacity is big again for the recovery of inclusion enclave.
Summary of the invention
The purpose of this invention is to provide a kind of combined gold deposits tailings reclamation device, this unit capacity is big, rate of recovery height, and facility compact, easy to operate, cost is low, and is pollution-free.
For achieving the above object, the present invention takes following design: this combined gold deposits tailings reclamation device, and it comprises: the submersible deep layer is towards device for picking, it comprises well-bucket, be placed with sand pump in the well-bucket, preposition hydraulic giant, rearmounted hydraulic giant, underlying hydraulic giant, ore pulp efferent duct; Also comprise ore pulp current divider, pulp distributer; And at least one ore pulp carefully selects, flushing device, described ore pulp current divider is the multichannel distribution pipeline with the shunting that is divided into two step by step, every layer of chassis of each isocon and distributor connects one to one, described ore pulp carefully selects, flushing device comprises: the slide carriage of being made up of the multilayer slide carriage makes up, the slide carriage combination is connected with the square frame skeleton, square frame skeleton and steel ring are fixed, bearing in steel ring and the rotary bracket groove contacts, described every layer of back side of heating up in a steamer plate is water receiving distributing pipe and sparge pipe again, hole for water spraying on the sparge pipe is facing to the storage ore deposit cell on the slide carriage, and every layer of chassis of described pulp distributer dustpan mouth and first ore pulp carefully select, corresponding slide carriage dustpan muzzle connects in the equipment.
Described each slide carriage combination is made up of 8 layers of slide carriage, the size of every slide carriage is long 1200mm, wide 1000mm, every layer of slide carriage has 128 profiles, every layer of slide carriage back spraying water pipe is 4, described current divider is 8 the tunnel, described distributor has 8 layers of chassis, four ore pulps carefully select, bath equipment is formed one group, promptly having added three ore pulps behind original equipment carefully selects, bath equipment, they are connected in series in order, adopt the upper end dustpan mouth of the slide carriage of next equipment to insert the gap position of the slide carriage dustpan mouth of an equipment, and the height of a last equipment is higher than the height of next equipment, be repeatedly water state, laterally scribble glue at a last equipment slide carriage connecting portion.
Description of drawings
Fig. 1 is the structural representation of ore pulp current divider and pulp distributer
Fig. 2 carefully selects for ore pulp, flushing device structural representation (carefully selecting state)
Fig. 3 carefully selects for ore pulp, flushing device structural representation (dextrorotation turn 90 degrees after, be the flushing state)
Fig. 4 a is the front view of Fig. 2 middle slide carriage and sparge pipe annexation
Fig. 4 b is the rearview of Fig. 4 a
Fig. 5 a is slide carriage structural representation (dotted portion represents that another ore pulp carefully selects, slide carriage and its annexation on the flushing device)
Fig. 5 b is the vertical view of Fig. 5 a
Fig. 6 is the schematic diagram that rotary bracket cooperates with steel ring
Fig. 7 is that the submersible deep layer is towards device for picking
The specific embodiment
Among Fig. 1, the left side is the ore pulp current divider, wherein, 1 is the confession ore deposit house steward who is connected with the ore pulp efferent duct, 2 is ore pulp isocon (for three-way pipe), and the ore pulp that comes from house steward is divided into two the tunnel, and wherein each road is further divided into two-way by three-way pipe again, be about to the next ore pulp of house steward and be split into 4 the tunnel, by that analogy, 4 these ore pulps of expression have been divided into 8 tunnel isocon, among the figure, 3 is shell, and shell is used for fixing isocon.Adopt this structure can make ore pulp evenly, stably the shunting.
Right side among Fig. 1 is the pulp distributer structure, is divided into 8 tunnel ore pulp through current divider and delivers to respectively in the pulp distributer, and wherein every railways and mineies slurry isocon is corresponding with every layer of chassis in the distributor, and the chassis has 8 layers.Every layer of this distributor comprises chassis 9, jet baffle plate 6, flow distribution plate 7.8 is support.Described jet baffle plate is to be supported on the frame that is positioned at the both sides, chassis, facing to the flow of slurry outgoing direction, leave neutral between baffle plate and the chassis, the effect of jet baffle plate is to prevent ore pulp direct projection slide carriage, it is turned back pass through from plate washer below, and fluid flow to that ore pulp carefully selects, before the flushing device, through flow distribution plate 7, the position of flow distribution plate is regulated as required for flexibly connecting in this flow distribution plate and chassis, come the standard flow of slurry to.
Described ore pulp current divider is adorned a connecting piece 5 with the below that can adopt isocon that is connected between the pulp distributer, penetrates screw in the hole of this brace, and the chassis of this screw and distributor joins.Pulp distributer carefully selects with ore pulp, being connected of flushing device be: with ore pulp carefully select, each layer slide carriage upper end dustpan muzzle in the flushing device below distributor dustpan mouth, approximately be inserted in 10 centimeters, the height of two equipment is that preceding high back is low,
Realize repeatedly water.
Among Fig. 2, Fig. 3,10 is the feed pipe articulation, the water that comes from joint enters flushing water isocon 11, and the water in the isocon 11 is divided into 8 water routes 25 again, and every water route is every layer a water distribution pipe, the water distribution pipe of each layer is further divided into four row's sparge pipes 13, the end of each row's sparge pipe is for sealing, and each Frame closure is on stay pipe 17, and 14 is the sparge pipe crossbeam among the figure, 16 are heavy mineral storage cell (being the groove of slide carriage) among the figure, and 18 are collection ore deposit base plate and discharging opening among the figure.24 is the frame of slide carriage among the figure.This ore pulp carefully selects, contain the slide carriage combination of being made up of 8 layers of slide carriage in the flushing device, this combination is connected with iron square frame skeleton 23, it is fixing that the outside, angle of square frame skeleton is welded with steel ring 21, also contain rotary bracket in this equipment, rotary bracket has groove, and steel ring crouches in groove, and contacts with bearing on being installed in rotary bracket 15,27 is bearing, and 20 for being contained in the axle (see figure 6) on the carriage.This structure makes the slide carriage group to make clockwise or to be rotated counterclockwise (90 degree) corresponding to rotary bracket.26 is the iron castor that is used for sliding on the light rail among the figure.
Among Fig. 4 a, Fig. 4 b, water distribution pipe and sparge pipe 13 are established in every layer of slide carriage back side, can be to another piece ore dressing front of saddle water spray, and 17 is stay pipe, adopts 4 sparge pipes in the present embodiment, and 22 is hole for water spraying, and hole for water spraying is over against slide carriage storage ore deposit cell 16 water sprays.24 is the slide carriage frame, and 12 is slide carriage upper end dustpan mouth, dustpan mouth end, slide carriage lower end band one breach 19 (upper end dustpan mouth refers to that ore pulp enters the position of slide carriage, go out position claim lower end dustpan mouth).
See among Fig. 5 a, Fig. 5 b, 24 is frame, slide carriage is arranged in the frame, and slide carriage comprises: with the two-layer base plate that galvanized iron sheet 28 and aluminium-plastic panel 29 make, be waterproof cloth 30 above the aluminium-plastic panel, it above the waterproof cloth lamp house cloth 31, be coated with triangle aluminium support frame 32 in the cloth, form soft clad can and be fixed on the base plate, on the lamp house cloth that outside triangle skeleton, coats profile 33 (claiming the thread gluing bar again) is housed, for example Chang Yong velcro , Qie Velvet face or male and fomale(M﹠F) all can.When flow of slurry is crossed slide carriage, (see Fig. 5 a direction of arrow), move forward up and down, realize little eddy current hindered settling, so that in the storage ore deposit cell 16 that the ore pulp middling particle is stayed along the sawtooth corrugated surface.
By in this composite set, need owing to produce, ore pulp carefully selects, flushing device can be four serial connections (i.e. four joint combinations).Except that distributor carefully selects with ore pulp, being connected between the first segment of flushing device, need also that ore pulp carefully selects, the connection successively between the flushing device, method is: breach 19 positions of adopting the upper end dustpan mouth 12 of the slide carriage of next equipment to insert a last equipment slide carriage dustpan mouth, and, the height of equipment is that last relative superiority or inferiority is low, accomplishes repeatedly water.Simultaneously, the transverse edge gluing in the slide carriage junction of a last equipment is in case leak.
Among Fig. 7,40 is mine tailing, 44 well-buckets, sand pump 37 is housed in the well-bucket, the hydraulic giant of outside water spray is arranged in the bucket, and they are the preposition hydraulic giants 35 that are positioned at the place ahead, are positioned at the rearmounted hydraulic giant 36 at rear, and the underlying hydraulic giant 38 that is positioned at the below, 39 is the sand pump suction inlet, and 41 is power line, and 34 is the ore pulp efferent duct, 43 for providing the pump discharge at water source, and 31 for dashing the hoisting mechanism of adopting the power-equipment that the equipment lifting uses with this.
The specific embodiment
Embodiment:
Ore pulp carefully selects, flushing device to adopt four (claiming four joints again) in the present embodiment, with four joints match an ore pulp current divider and pulp distributer arranged, this combination is called one group, can form a production line by four groups, for adding high throughput, can be many production lines.Produce in the used slide carriage combination, every slide carriage length and width is respectively long 1200mm, wide 1000mm, and every slide carriage is stained with 128 profiles.Selected ore pulp granular size is between the 200-300 order, and the concentration of ore pulp is 20-30 weight %, and used sand pump lift is a 20-25 rice.During operation, every layer of slide carriage flow hourly is 0.078 ton in every group, operates after 2 hours, and rotatable 90 degree cleaned 10 minutes.
The present invention is used for inclusion enclave and reclaims, and can obtain 90% the rate of recovery and reclaim the inclusion enclave that obtains and deliver to tower grinder preface.
Advantage of the present invention is: because the present invention adopts deep layer to dash and adopts, ore pulp be divided into two shunting mode step by step multichannel evenly, stable shunting and distributing, selected for use slide carriage combination, the refinement of multilayer to divide option, and ore dressing is finished with washing in a device, by rotation, can change mode of operation.Recyclable other equipment of the present invention are difficult to reclaim to such an extent that contain golden inclusion enclave, and treating capacity is big, the rate of recovery is high, and facility compact is easy to operate, pollution-free, are widely used in the refinement sorting of the gravity treatment of rock gold, heavy metallic mineral, and select factory to transform always.

Claims (4)

1, a kind of combined gold deposits tailings reclamation device, it is characterized in that it comprises: the submersible deep layer is towards device for picking, and it comprises well-bucket, is placed with sand pump in the well-bucket, preposition hydraulic giant, rearmounted hydraulic giant, underlying hydraulic giant, ore pulp efferent duct; Also comprise ore pulp current divider, pulp distributer; And ore pulp carefully selects, flushing device, described ore pulp current divider is the multichannel distribution pipeline with the shunting that is divided into two step by step, every layer of chassis of each isocon and distributor connects one to one, described ore pulp carefully selects, flushing device comprises: the slide carriage of being made up of the multilayer slide carriage makes up, the slide carriage combination is connected with the square frame skeleton, square frame skeleton and steel ring are fixed, bearing in steel ring and the rotary bracket groove contacts, described every layer of back side of heating up in a steamer plate is water receiving distributing pipe and sparge pipe again, hole for water spraying on the sparge pipe is facing to the storage ore deposit cell on the slide carriage, and every layer of chassis dustpan of described pulp distributer and ore pulp carefully select, corresponding slide carriage dustpan muzzle connects in the equipment.
2, combined gold deposits tailings reclamation device according to claim 1, it is characterized in that: described each slide carriage comprises: on frame, base plate, the described base plate waterproof cloth is arranged, it above the waterproof cloth lamp house cloth, be coated with triangle aluminium support frame in the cloth, formed soft clad can and be fixed on the base plate, on the inclined-plane of lamp house cloth, profile has been housed.
3, combined gold deposits tailings reclamation device according to claim 1 and 2, it is characterized in that: described each slide carriage combination is made up of 8 layers of slide carriage, the size of every slide carriage is long 1200mm, wide 1000mm, every layer of slide carriage has 128 profiles, every layer of slide carriage back spraying water pipe is 4, described current divider is 8 the tunnel, described distributor has 8 layers of chassis, the described ore pulp that joins with pulp distributer carefully selects, also have three thin choosings behind the bath equipment, bath equipment, they are connected in series in order, adopt the upper end dustpan mouth of the slide carriage of next equipment to insert the gap position of the slide carriage dustpan mouth of an equipment, the height of a last equipment is higher than the height of next equipment, is repeatedly water state.Laterally scribble glue at a last equipment slide carriage connecting portion.
4, combined gold deposits tailings reclamation device according to claim 1 and 2, it is characterized in that: described each road isocon is fixed on each floor chassis of the distributor corresponding with it with screw, distributor also is provided with ore pulp jet plate washer, the neutral gear that passes through for ore pulp is left in the below of plate washer, and the place ahead of jet plate washer is provided with the ore pulp flow distribution plate.
CN 200410103975 2004-12-31 2004-12-31 Combined gold deposits tailings reclamation device Expired - Fee Related CN1799697B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200410103975 CN1799697B (en) 2004-12-31 2004-12-31 Combined gold deposits tailings reclamation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200410103975 CN1799697B (en) 2004-12-31 2004-12-31 Combined gold deposits tailings reclamation device

Publications (2)

Publication Number Publication Date
CN1799697A true CN1799697A (en) 2006-07-12
CN1799697B CN1799697B (en) 2010-05-05

Family

ID=36810046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200410103975 Expired - Fee Related CN1799697B (en) 2004-12-31 2004-12-31 Combined gold deposits tailings reclamation device

Country Status (1)

Country Link
CN (1) CN1799697B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104888933A (en) * 2014-03-04 2015-09-09 侯树强 Heavy metal reselection enrichment pipe and beneficiation method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH530822A (en) * 1971-02-15 1972-11-30 Pallana Gmbh Process for the safe separation of different plastic waste by type of plastic and its recovery after reuse, and device for carrying out the process
US4511461A (en) * 1983-07-06 1985-04-16 Jan Kruyer Process for recovering minerals and metals by oleophilic adhesion
CN2248594Y (en) * 1996-02-13 1997-03-05 招远市玲珑黄金机械研究所 Equipment for recovery of gold-bearing lailing
CN1212198C (en) * 2002-11-19 2005-07-27 孙进元 Combined preparation system of screening, water-washed and skip oscillating

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104888933A (en) * 2014-03-04 2015-09-09 侯树强 Heavy metal reselection enrichment pipe and beneficiation method thereof

Also Published As

Publication number Publication date
CN1799697B (en) 2010-05-05

Similar Documents

Publication Publication Date Title
CN104895569B (en) A kind of hydraulic collecting mechanism
CN204870935U (en) Pier haulage vehicle tyre -cleaning device
CN103785125B (en) Water band is collected and is laid fire fighting truck
CN201143394Y (en) Novel bidirectional flow tipping plate clarifying basin
CN1799697B (en) Combined gold deposits tailings reclamation device
CN106996209A (en) A kind of multi-storied garage and its stop pick-up method
CN106824868A (en) The cleaning device of weldment
CN103785126B (en) There is the fire fighting truck of automatic deploying and retracting band function
CN2754730Y (en) Fine gold re-choosing device
CN210766938U (en) High-protection underwater dredging and sewage discharging robot
CN107332502A (en) A kind of photovoltaic battery panel purging system
CN116691742A (en) Multifunctional railway transport vehicle and application method thereof
CN216994245U (en) Vehicle washing system
CN206543345U (en) Water fetching device
JP2016019974A (en) Washing apparatus
CN214638558U (en) Crawler belt cleaning machine
CN201411622Y (en) Road surface recovery cleaning device paved by soft-sand road surface emergent building car
CN209892197U (en) Spraying dust device that coal mine engineering tunnelling machine used
CN212197022U (en) Garbage truck convenient to wash
CN210657178U (en) Coating system for container
CN102614976A (en) Automatic ore water-washing recovery equipment
CH706921A1 (en) Apparatus for cleaning surfaces of arbitrarily structured floors.
CN207828018U (en) A kind of integral type phosphorized waste water processing unit
CN206715563U (en) A kind of surface mine dumping plough dedusting movable type water case apparatus
CN111760401A (en) Movable dust removal device for surface mine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100505

Termination date: 20171231

CF01 Termination of patent right due to non-payment of annual fee