CN1759959A - Allocation mode for zoning foundry - Google Patents
Allocation mode for zoning foundry Download PDFInfo
- Publication number
- CN1759959A CN1759959A CN 200510200693 CN200510200693A CN1759959A CN 1759959 A CN1759959 A CN 1759959A CN 200510200693 CN200510200693 CN 200510200693 CN 200510200693 A CN200510200693 A CN 200510200693A CN 1759959 A CN1759959 A CN 1759959A
- Authority
- CN
- China
- Prior art keywords
- aluminium
- foundry
- casting
- holding furnace
- district
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Manufacture And Refinement Of Metals (AREA)
Abstract
A regional configuration method for a casting workshop features that a casting workshop is divided into the region A, where the ground balance, aluminium holding furnace, ladle tilting mechanism and overhead travelling crane are arranged, and the region B, where the casting machine communicated with said aluminium holding furnace and fork truck are arranged.
Description
Technical field:
The present invention relates to a kind of foundry's configuration mode of Aluminium Electrolysis.
Background technology:
Along with the continuous progress of modern pre-baked cell technologies, the current strength of aluminium cell constantly increases, to obtain increasing single series production capacity.In recent years, be accompanied by the production-scale continuous increase of aluminium manufacturer, also increasing to the requirement of its foundry's founding ability that matches.Frequent 24t or the 40t aluminium holding furnace that uses of past foundry, supporting production capacity is 9t/h or the such configuration mode of 16t/h casting machine.
For the design disposal ability is the foundry of 250kt/a, its traditional collocation form is: plant area is 144m * 81m, wherein contains aluminium ingot working area 48 * 81m, overhead traveling crane tread absolute altitude 11.6m, the workshop is that configuration is striden by three companies, whenever strides 2 general-purpose overhead cranes (to call overhead traveling crane in the following text) are installed.This traditional collocation form has following weak point:
1. in the traditional processing technology of foundry, whenever striding in the factory building that aluminium holding furnace is installed, generally all will be equipped with 2 overhead traveling cranes, the two is standby each other.With this collocation form, three companies stride factory building 6 overhead traveling cranes need be installed altogether, and in fact, casting unit district (to call casting region in the following text) does not use overhead traveling crane substantially, and (to call the founding district in the following text) two-mand ladle and just need be used overhead traveling crane when irritating the aluminium operation only in the aluminium holding furnace district.Configuration has increased the input cost of equipment greatly like this, causes the utilization rate of overhead traveling crane lowly to reach waste of manpower resource simultaneously.
2. in the foundry, overhead traveling crane is general only to carry out work in the founding district, but considers the running space and the operating repairs of overhead traveling crane ordinary production, will overhead crane orbit be installed reaching in the factory building of 144m; In order to guarantee that overhead traveling crane can freely drive in the workshop, overhead traveling crane driver's cabin bottom absolute altitude must be higher than the about 500mm of aluminium holding furnace highest point absolute altitude.The actual the highest setting height(from bottom) of using of aluminium holding furnace is about 7.3m, considers the safe distance of cab heights and installation, and the final absolute altitude of overhead traveling crane tread is more than the 11.6m.More than 2 the building cost of factory building is increased greatly, strengthened capital expenditure.
3. in traditional foundry's configuration, the production capacity of casting machine will be far longer than actual production needs.If electrolytic series will increase production capacity, as long as in foundry, increase the quantity of aluminium holding furnace.But, increase an aluminium holding furnace, then to increase the construction area of 42m * 30m at least, to consider also simultaneously and the problem of docking of old factory building that difficulty of construction is bigger.
Summary of the invention:
The objective of the invention is to: a kind of more rational allocation mode for zoning foundry is provided, had both guaranteed the economy of engineering construction and the reasonability of production run cost, help the production and the reorganization and expansion of aluminium manufacturer again.
The present invention is achieved in that foundry is divided into two relatively independent zones, and one is that founding district (1), one are casting region (2); At the place of entering of founding district (1) weighing apparatus (3) on the ground is set, aluminium holding furnace (4) is set, on aluminium holding furnace (4) next door the tipple (8) of two-maing ladle is set, and disposes overhead traveling crane (5) near a side; Casting machine (7) and fork truck (9) are arranged in casting region (2); Aluminium holding furnace (4) is connected by going out aluminium chute (6) with casting machine (7).
5 aluminium holding furnaces (4) are arranged, 3 tipples of two-maing ladle (8), 2 overhead traveling cranes (5) in founding district (1); 3 casting machines (7) and 3 fork trucks (9) are arranged in casting region (2).
During work, the primary aluminum that potroom is extracted out is transported to the interior ground weighing apparatus (3) in founding district (1) by the trailer of two-maing ladle, weighing apparatus (3) is delivered near the aluminium holding furnace (4) after going up weighing on the ground, fill the overhead traveling crane (5) that two-maing ladle of aluminium liquid be positioned in the founding district (1) and winch in the tipple of two-maing ladle (8), pour into then in the aluminium holding furnace (4).Aluminium liquid through in keeping stove (4) and leaving standstill, refining, skim after, be dispensed to the casting machine (7) that is arranged in casting region (2) by going out aluminium chute (6).Aluminium liquid is gone up the casting bailing at casting machine (7), is transported in the warehouse for finished product by fork truck (9) to store.
The present invention compares with the conventional arrangement technology, has the following advantages:
Because have only the production of aluminium holding furnace to need overhead traveling crane, founding district (1) and casting region (2) is independent, 2 overhead traveling cranes, standby each other getting final product only are installed in founding district (2).Under the condition of equal annual capacity, can save 4 overhead traveling cranes like this, improve usage ratio of equipment greatly.;
In zone configuration, aluminium holding furnace is installed in a side of founding district (1) factory building, and driver's cabin is arranged in the stage casing of overhead traveling crane, like this if runway girder be higher than aluminium holding furnace just can ordinary production.High standard is up to about 8.3m in production run for aluminium holding furnace, though more original aluminium holding furnace exceeds nearly 1m, actual overhead traveling crane tread height has only 9.6m; Simultaneously, because casting region (2) does not use overhead traveling crane, factory building height is as long as satisfy casting unit setting height(from bottom) and produce needs, the factory building bracket bottom absolute altitude of casting region (2) has only 7m, thereby solved second problem of conventional arrangement: promptly reduced the height of factory building, saved the capital expenditure expense.
Zone configuration more helps the reorganization and expansion of factory building.Because founding district factory building is independent of the casting region factory building, just can satisfy the reorganization and expansion needs as long as increase the length of founding district factory building like this, be easier to construction; Simultaneously as can be seen, just can increase the about 50000t of production capacity, satisfy the reorganization and expansion needs as long as increase the about 27m * 36m of plant area.
Description of drawings:
Fig. 1: schematic diagram of the present invention, foundry's zone configuration plane;
Fig. 2: schematic diagram of the present invention, foundry's zone configuration elevation.
The specific embodiment:
Embodiments of the invention: the Foundry Design disposal ability is 250kt/a.The workshop is divided into two relatively independent Production Regional, and one is casting region 2 for 1, one in founding district; Wherein the factory building in founding district 1 is to stride, and area is 84m * 33m, and the tread absolute altitude of overhead traveling crane 5 is 9.6m; The factory building of casting region 2 is three to stride, and area is about 78m * 72m, and factory building bracket bottom absolute altitude is 7m.Two 22/3.2t double hook overhead traveling cranes 5 are installed in the founding district 1, dispose 5 60t tilt bed aluminium holding furnaces 4; 3,3 tipples 8 of two-maing ladle of ground weighing apparatus of 1 30t; 3 casting machine 7 and 3 fork trucks 9 that production capacity is 22t/h of configuration in the casting region 2 go out between the casting machine 7 that aluminium chute 6 is connected the aluminium holding furnace 4 in founding district 1 and casting region 2.
Claims (3)
1. allocation mode for zoning foundry, it is characterized in that: foundry is divided into two relatively independent zones, and one is that founding district (1), one are casting region (2); At the place of entering of founding district (1) weighing apparatus (3) on the ground is set, aluminium holding furnace (4) is set, on aluminium holding furnace (4) next door the tipple (8) of two-maing ladle is set, and disposes overhead traveling crane (5) near a side; Casting machine (7) and fork truck (9) are arranged in casting region (2); Aluminium holding furnace (4) is connected by going out aluminium chute (6) with casting machine (7).
2. allocation mode for zoning foundry according to claim 1 is characterized in that: 5 aluminium holding furnaces (4) are arranged, 3 tipples of two-maing ladle (8), 2 overhead traveling cranes (5) in founding district (1).
3. allocation mode for zoning foundry according to claim 1 is characterized in that: 3 casting machines (7) and 3 fork trucks (9) are arranged in casting region (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB200510200693XA CN1326647C (en) | 2005-11-11 | 2005-11-11 | Allocation mode for zoning foundry |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB200510200693XA CN1326647C (en) | 2005-11-11 | 2005-11-11 | Allocation mode for zoning foundry |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1759959A true CN1759959A (en) | 2006-04-19 |
CN1326647C CN1326647C (en) | 2007-07-18 |
Family
ID=36706247
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB200510200693XA Active CN1326647C (en) | 2005-11-11 | 2005-11-11 | Allocation mode for zoning foundry |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1326647C (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102348521A (en) * | 2009-03-10 | 2012-02-08 | 新东工业株式会社 | Pouring facility, and pouring method |
CN106399717A (en) * | 2016-11-21 | 2017-02-15 | 安德里茨(中国)有限公司 | Aluminium holding furnace group for matched aluminium continuous casting and rolling production line |
CN109202054A (en) * | 2018-10-10 | 2019-01-15 | 广东华劲金属型材有限公司 | A kind of die casting molten aluminum intelligence transportation system |
CN110860685A (en) * | 2019-10-30 | 2020-03-06 | 上海宝冶集团有限公司 | Construction method of steelmaking continuous casting plant |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101433958B (en) * | 2007-11-14 | 2011-01-26 | 贵阳铝镁设计研究院 | Mode for configuring combination of caption foundry and railway transportation |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2047140A (en) * | 1979-04-12 | 1980-11-26 | Stone Wallwork Int Ltd | Conveying system in die-casting plant |
US4747444A (en) * | 1985-05-02 | 1988-05-31 | Amsted Industries Incorporated | Automated casting plant and method of casting |
US6073678A (en) * | 1996-10-28 | 2000-06-13 | Tenedora Nemak S.A. De C.V. | Method and apparatus for production of aluminum alloy castings |
DE20320923U1 (en) * | 2003-12-19 | 2005-06-09 | Hydro Aluminium Alucast Gmbh | Production of light metal castings, especially engine blocks, comprises forming mold cores, mounting them in molds, casting, cooling castings in mold and removing castings at rate determined by core production rate |
CN1251828C (en) * | 2004-11-01 | 2006-04-19 | 重庆隆鑫工业(集团)有限公司 | Junk head circulating foundry product line |
-
2005
- 2005-11-11 CN CNB200510200693XA patent/CN1326647C/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102348521A (en) * | 2009-03-10 | 2012-02-08 | 新东工业株式会社 | Pouring facility, and pouring method |
CN106399717A (en) * | 2016-11-21 | 2017-02-15 | 安德里茨(中国)有限公司 | Aluminium holding furnace group for matched aluminium continuous casting and rolling production line |
CN106399717B (en) * | 2016-11-21 | 2018-11-20 | 安德里茨(中国)有限公司 | Aluminum holding furnace group for mating aluminium continuous casting and rolling production line |
CN109202054A (en) * | 2018-10-10 | 2019-01-15 | 广东华劲金属型材有限公司 | A kind of die casting molten aluminum intelligence transportation system |
CN110860685A (en) * | 2019-10-30 | 2020-03-06 | 上海宝冶集团有限公司 | Construction method of steelmaking continuous casting plant |
Also Published As
Publication number | Publication date |
---|---|
CN1326647C (en) | 2007-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201217605Y (en) | Lever-type sling | |
CN1326647C (en) | Allocation mode for zoning foundry | |
CN201264870Y (en) | Bridge type aluminum discharge cart | |
CN107512661A (en) | A kind of replacing of vehicle wheel method | |
CN208883351U (en) | A kind of lifting equipment | |
CN113106192A (en) | Steel-smelting converter and integral pushing method of tilting device | |
CN209465688U (en) | A kind of metallurgy self-propelled mucking machine | |
CN202558494U (en) | Multifunctional lifting transport unit for aluminum electrolysis production | |
CN207645652U (en) | A kind of explosion-proof crane that security performance is high | |
CN207188779U (en) | A kind of LF refining steel ladle covering/uncovering device | |
CN2641001Y (en) | Bogie of bridge crane | |
CN2531993Y (en) | Semitrailed type frame separatable conveying vehicle | |
CN210254217U (en) | High-temperature aluminum-iron metal liquid feeding line | |
CN202088279U (en) | Straight web box girders shared hydraulic internal mold | |
CN204779663U (en) | Promote ladle formula RH vacuum tank sideslip platform truck | |
CN212350354U (en) | Ladle transporting device | |
CN1040530A (en) | Steelmaking equipment with a smelting furnace and a following process device | |
CN211758432U (en) | Rear-turning type dumping transfer trolley of molten iron ground conveying system | |
CN108584715A (en) | Auxiliary hook casting does not translate the twin beams ladle carne of scarfing cinder Forward | |
CN211758431U (en) | Energy-saving efficient liftable dumping type ladle conveying trolley | |
CN209210234U (en) | One kind is for the moveable hanging apparatus of metallurgical large-tonnage overhead traveling crane | |
CN110498345A (en) | A kind of equipment and its application method based on light-type novel intelligent overhead traveling crane | |
CN205732952U (en) | A kind of steel ladle hydraulic pressure tipping arrangement | |
CN215561943U (en) | Be used for bridge anticollision barrier template ann to dismantle and put | |
CN203904372U (en) | Arc-shaped liner plate of integral novel blast furnace material pipe insertion piece |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee |
Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST. |
|
CP03 | Change of name, title or address |
Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2 Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd. Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou Patentee before: Guiyang Aluminium and Magnesium Design Inst. |