CN1648353A - Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure - Google Patents
Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure Download PDFInfo
- Publication number
- CN1648353A CN1648353A CN 200410039307 CN200410039307A CN1648353A CN 1648353 A CN1648353 A CN 1648353A CN 200410039307 CN200410039307 CN 200410039307 CN 200410039307 A CN200410039307 A CN 200410039307A CN 1648353 A CN1648353 A CN 1648353A
- Authority
- CN
- China
- Prior art keywords
- cage
- pile
- reinforcing cage
- concrete
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The present invention provides pile forming process and machine system with environment protecting efficient long screw driller and central pump pressurizing concrete to reinforcing bar cage. Special MF vibrating cage depositing and drawing apparatus has less disturbance on concrete, fast ground assembling and disassembling. Especially, in some case with reinforcing bar cage incapable of being deposited in requirement level, the reinforcing bar cage may be drawn out timely with fast connecting mechanism and vibrating mechanism and reset after the concrete is initially solidified, and this results in relatively low cost. In addition, the present invention adopts also opened soil withdrawer for convenient muck treating and civilized construction.
Description
Technical field
The present invention relates to a kind of long auger deposited reinforced concrete pile construction technology, particularly a kind of long auger center pump pressure concrete, the pile-formation process of implanted reinforced bar cage before the pile body concrete does not coagulate.
Background technology
In the construction of long auger in situ concrete pile, often adopt a kind of desired depth that is bored into, putting forward brill is pressed onto concrete by the drilling rod center formation pile body in the stake hole that has been drilled to simultaneously with concrete pump method.This method is usually used in the construction works of CFG pile composite foundation.Implanted reinforced bar cage in the plain concrete pile body that forms can improve shearing resistance, bending resistance, the resistance to tension of stake, enlarges its range of application.Patented technology " Superfluid state concrete " (patent No. CN1074426a) provides a kind of concrete of being convenient to pumping and inserting reinforcing cage.But insert in the reinforcing cage construction in vibration, run into long, the relatively poor reinforcing cage of rigidity, usually run into heavy problem less than desired depth, not only quality assurance also can not cause waste; Cage assembly is inserted in vibration now commonly used to be with vibrating hammer or to vibrate and electronicly be connected with the reinforcing cage top.In the process of reinforcing cage vibration-sunk in the concrete of stake hole.The whole generation of reinforcing cage vibrated, and makes the continuous vibratory compaction of concrete, and the vibrating motor vibration frequency of general small vibrating hammer is but at 1100min
-1More than.Vibrating motor not only produces the vertical direction vibration, also can produce the horizontal direction vibration, and it is closely knit to help concrete vibration.In heavy cage process, exactly do not wish the too early closely knit reinforcement of concrete.Vibrating hammer or vibrating motor are pressed in the reinforcing cage top and make the reinforcing cage pressurized in addition, and it is crooked that its unstability is produced.The above all produces very adverse influence to heavy cage.Make heavy cage construction not reach the effect of anticipation; When lifting by crane reinforcing cage, also can produce additional bending moment with common vibrating hammer, easily make reinforcing cage produce plastic strain reinforcing cage; In addition when CFG pile composite foundation etc. is constructed with full screw earth auger, concrete shutter-type drill bit is adopted in the drilling rod bottom, for conveniently closing the operation of valve, the normal fixedly casing that adopts, because fixedly casing does not have the casting function, therefore the boring mud, the muddy water that get out pile with the place, does not only form and carry out production strictly in line with rules and regulations, and because earth has been buried the difficulty that stake position mark has increased in place hole.
Content of the present invention
The purpose of this invention is to provide a kind of environmental protection, construction technology and corollary equipment efficiently.Adopt that a kind of special-purpose medium and low frequency vibration is heavy pulls out cage assembly and reduce concrete disturbance in heavy cage process.The dismounting annex is quick and convenient on ground.When particularly running into indivedual reinforcing cages and causing sinking not satisfy workmanship and require, can adopt quick-connect machanism, in time reinforcing cage be extracted a hole, apply pile again with vibrating device less than predetermined absolute altitude because of multiple factor.Can avoid replacing piling, strengthen expensive remedial measure such as foundation structure.The present invention also adopts bottom-open type to go out earthenware, can make things convenient for having bad luck of dregs, makes on-the-spot civilized construction.
The technical scheme of construction technology of the present invention is: heavy pull out reinforcing cage and adopt a kind of special-purpose medium and low frequency vibrating device, can a steel pipe be inserted the reinforcing cage inner chamber in the ground level direction, steel pipe and special-purpose medium and low frequency vibrating device are rigidly connected fast, and reinforcing cage and vibrating device flexibly connect.After treating that drill center pump pressure concrete forms pile body, sling vibrating device, steel pipe and reinforcing cage, the reinforcing cage lower end is inserted in the concrete pile body, rely on gravity and vibrating device to drive steel pipe the reinforcing cage bottom is vibrated and impacts, make reinforcing cage sink to desired depth; Insert reinforcing cage and meet a small amount of reinforcing cage when sinking to not reaching the situation of desired depth, untie flexibly connecting of vibrating device and reinforcing cage rapidly, steel pipe is extracted ground, itself and vibrating device are taken apart placed ground.To press from both sides the cage device is connected with vibrating device.Folder cage device is clamped reinforcing cage upper end stud, starts vibrating device, utilizes the pile pulling principle that reinforcing cage pulling from the concrete pile body is come out.After treating the pile body initial set, repeat above pile-formation process, finish the present walling pile construction in former stake position.
When using more high-power vibrating device, steel pipe, pull out the cage device and make one, be rigidly connected fast with the special vibrating device; Reinforcing cage and vibrator flexibly connect, and folder cage device and reinforcing cage upper end are in relaxed state.Repeat above-mentioned heavy cage technology, finish the present walling pile operation.Meet a small amount of reinforcing cage and sink, folder cage device and reinforcing bar upper end stud are rigidly connected, start vibrating device, steel pipe and reinforcing cage are extracted from the pile body concrete simultaneously less than the situation of desired depth, treat concrete initial set after, carry out same pile operation again.
The lifting direction of medium and low frequency special vibrating device shock absorber can be parallel to direction of vibration and change perpendicular to direction of vibration.Folder cage device, steel pipe is connected fast with vibrating device is mechanical or fluid pressure type.At horizontal level, the covering of steel pipe and reinforcing cage carried out in steel pipe and vibrating device released state or connection status, used bottom-open type to go out earthenware when bore operation.
Description of drawings
Fig. 1 is a process schematic flow diagram of the present invention.
Fig. 2 goes out the earthenware schematic diagram for downward swing door
Fig. 3 is the heavy cage operation schematic diagram of vibration
Fig. 4 is a quick-connect machanism embodiment schematic diagram
Fig. 5 is lifting reinforcing cage operation schematic diagram
Fig. 6 is following hanging fortune cage dolly schematic diagram
Fig. 7 is folder cage device embodiment schematic diagram
Specific implementation
Concrete construction technique of the present invention is described below
1, working drawing measuring stake position, boring in place (seeing Fig. 1 a and Fig. 1 b)
2, the on-the-spot reinforcing cage of making;
3, pile-forming machine perching, the verticality on adjustment drilling rod and ground; Drill bit stake position starts rig and goes into to bore, and gets into the degree of depth in predetermined hole.(seeing Fig. 1 c)
4, when pore-forming creeps into, carry out the stirring of compound according to match ratio, the compound that stirs is delivered to the drilling machine construction scope of operation and is prepared pouring;
5, the cage steel pipe that will shake on ground penetrates reinforcing cage, is connected fast with the reinforcing cage vibratory equipment.
6, creep into projected depth after, slightly carry drilling rod so that the concrete material washes valve open, on one side mixture-pumping carry brill on one side; (seeing Fig. 1 d)
7, the influx height of compound should be a little more than design stake top mark height.The unnecessary part later stage chisels out, and guarantees that the intensity on stake top meets design requirement.Before Kelly Stubb goes out the aperture, close concrete pump earlier, note guaranteeing material stock amount in the drilling rod, satisfy the stake heights of roofs.(seeing Fig. 1 e)
8, Kelly Stubb goes out the aperture, after the affirmation pile meets the requirements, inserts reinforcing cage before the pile body concrete does not coagulate, and starts vibrating device, and reinforcing cage is sunk to desired depth; (seeing Fig. 1 f)
9, after reinforcing cage puts in place, extract steel pipe, place ground.(seeing Fig. 1 g)
10, in the construction, should sample and do the concrete test block;
11, run into indivedual reinforcing cages because of multiple factor causes sinking when requiring absolute altitude, will press from both sides the cage device fast and be connected with vibrating device, folder cage device in time with on the reinforcing cage is connected, and with the method for pile pulling reinforcing cage is extracted a hole.After treating concrete initial set, again at former stake position construction pile.(seeing Fig. 1 h and Fig. 1 i)
Boring adopts downward swing door to go out the earthenware (see figure 2), goes out earthenware and generally is fixed on machine column 8 bottom.The effect that goes out earthenware downward swing door 7 is an artificial shutoff operation of being convenient to press concrete drill bit valve.When carrying out bore operation, to go out earthenware downward swing door 7 and close, the dregs that drilling rod is arranged up rises to tilting chute 5 along going out earthenware cylindrical shell 6, and dregs is discharged to the ground far away of leaving an aperture, be convenient to the loading and unloading of loader, also available spoil car directly connects soil away from operation field.Make the operation place avoid the dregs state that pile up like a mountain, accomplish civilized construction.Also can take to reserve the method for 0.5-0.6m far from ground and replace downward swing door to go out earthenware with going out the earthenware bottom.
With reference to the heavy cage schematic diagram 3 of vibration, vibrating hammer 1 and steel pipe 2 are rigidly connected by quick-connect machanism.The exciting force of vibrating hammer 1 passes to the bottom of reinforcing cage by steel pipe 2, and reinforcing cage 3 is produced unidirectional straight down impact force, can not cause the direction vibration of reinforcing cage 3; Reinforcing cage 3 is flexible bodies, and static pressure and single vibration impact force produce pulling force rather than pressure to main muscle, help the transmission of power and the sinking of reinforcing cage; Vibrating device adopts 500-900 min
-1Medium and low frequency has weakened steel pipe to concrete vibratory compaction effect, and the preferable value of vibration frequency is 750 min
-1, a little less than concrete disturbance, range of disturbance is little; The steel pipe lower openings, pore is opened in the middle and upper part, makes concrete enter the steel pipe inner chamber, unlikelyly makes concrete overflow a hole to cause waste or cause the concrete quality problem.
Fig. 4 is that a kind of rigidity of quick-connect machanism connects the embodiment signal.Be made up of adapter sleeve 4-1, connector 4-2 and connecting pin 4-3, method of attachment is that connector 4-2 is inserted adapter sleeve 4-1, inserts with connecting pin 4-3 to lock in the pin-and-hole again.
With reference to Fig. 5, this figure has described the stressing conditions of reinforcement cage hoisting state, and reinforcing cage 3, steel pipe 2, vibrating hammer 1 are in level during lifting, and the general vibrating hammer suspension centre of using always is at the top of vibrating hammer.This just makes the gravity of vibrating hammer itself that reinforcing cage is formed additional bending moment, and is very unfavorable to the lifting reinforcing cage, can cause the flexural deformation of reinforcing cage.The lifting vibration isolator of this programme special vibrating hammer can be around the rotation of 1-3 twisted point when lifting, and the Heave Here overlaps with the center of gravity of vibrator 1-2, the additional bending moment vanishing.Got rid of the gravity influence that bending produces to reinforcing cage owing to vibrating hammer self like this, steel pipe is placed on the reinforcing cage lumen centers simultaneously, has also increased integral rigidity.Reinforcing cage is lifted by crane smoothly, do not produce the flexural bending distortion, the technology that helps rear inserting cage is carried out, and guarantees the quality of pile.The hinge joint of vibration isolator and vibrating hammer is convenient to and being connected and dismounting of steel pipe.
Hanging fortune cage dolly (see figure 6) is made up of two wheels 10 and car body 9 down, and the slender member 17 of slinging in the centre of dolly two-wheeled can move horizontally.The effect of dolly has three like this: can have bad luck the reinforcing cage of making at the scene with dolly; Can penetrate the reinforcing cage inner chamber in the ground level direction with the dolly steel pipe that cage uses that will shake.Available dolly is sling and is put on the steel pipe of reinforcing cage, and the steel pipe upper end is rigidly connected fast with vibrating device, and method is simple and efficient.
Fig. 7 is a folder cage device embodiment schematic diagram.Folder cage device and vibrating device can be rigidly connected by quick-connect machanism.Folder cage device is made up of adapter sleeve 11, connection steel pipe 12, connection disc 13, ring flat-plate 15 and U type clamping body 14.In the time of need pulling up defective reinforcing cage, reinforcing cage master muscle 16 is passed U type clamping body 14, fastening U type clamping body bolt 14-1 makes the reinforcing cage upper end and presss from both sides the cage device and just be connected.Start vibrating hammer, pull out the cage operation.
The present invention has expanded the range of application of center pressure cast-in-place concrete pile.Not only can be applied to the composite foundation stabilization engineering of CFG stake, can also be used for construction workss such as the engineering piles of building foundation and slope protection pile, thereby bring immeasurable economic benefit and social benefit.
Claims (7)
1, a kind of long auger center pump pressure concrete implanted reinforced bar cage pile-formation process method, the pile-formation process of implanted reinforced bar cage before the pile body concrete does not coagulate, comprise boring in place, be drilled into hole depth, the limit is carried and is bored limit pump pressure concrete, the pump pressure concrete is to the stake top, insert reinforcing cage, pile, it is characterized in that: before the pile body concrete does not coagulate, insert reinforcing cage and adopt a kind of medium and low frequency vibrating device, a steel pipe is inserted the reinforcing cage inner chamber, steel pipe and special-purpose medium and low frequency vibrating device are rigidly connected fast, simultaneously reinforcing cage and vibrating device are flexibly connected with wire rope, treat that drill center pump pressure concrete forms pile body after, the vibrating device of slinging, steel pipe and reinforcing cage, the reinforcing cage lower end is inserted in the concrete pile body, rely on gravity and vibrating device to drive steel pipe the reinforcing cage bottom is vibrated and impacts, make reinforcing cage sink to desired depth, then steel pipe is extracted the ground pile.
2, pile-formation process method according to claim 1, it is characterized in that: insert reinforcing cage when reinforcing cage sinks to not reaching desired depth, untie flexibly connecting of vibrating device and reinforcing cage rapidly, steel pipe is extracted ground, itself and vibrating device are taken apart placed ground; To press from both sides the cage device and be connected with vibrating device, folder cage device is clamped reinforcing cage upper end stud, starts vibrating device, utilizes the pile pulling principle that reinforcing cage pulling from the concrete pile body is come out, treat the pile body initial set after, repeat above pile-formation process in former stake position, finish the present walling pile construction.
3, pile-formation process method according to claim 1 is characterized in that: steel pipe is subsidiary to be pulled out the cage device and makes one, is rigidly connected fast with vibrating device; Reinforcing cage and vibrator flexibly connect, folder cage device and reinforcing cage upper end are in relaxed state, when a small amount of reinforcing cage sinks situation less than desired depth, folder cage device and reinforcing bar upper end stud are rigidly connected, start vibrating device, steel pipe and reinforcing cage are extracted from the pile body concrete simultaneously, treat concrete initial set after, carry out the pile operation of same stake position again.
4, according to claim 2 or 3 described pile-formation process methods, it is characterized in that: the lifting direction of medium and low frequency vibrating device shock absorber can be parallel to direction of vibration and change perpendicular to direction of vibration, and folder cage device, steel pipe is connected fast with vibrating device is mechanical or fluid pressure type.
5, according to claim 1,2 or 3 described pile-formation process methods, it is characterized in that: the vibration frequency of medium and low frequency vibrator is 500-900 min
-1
6, pile-formation process according to claim 4 is characterized in that: used bottom-open type to go out earthenware when bore operation.
7, pile-formation process according to claim 4 is characterized in that: the steel pipe lower openings, pore is opened in the middle and upper part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100393079A CN100412272C (en) | 2004-01-19 | 2004-01-19 | Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100393079A CN100412272C (en) | 2004-01-19 | 2004-01-19 | Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1648353A true CN1648353A (en) | 2005-08-03 |
CN100412272C CN100412272C (en) | 2008-08-20 |
Family
ID=34868581
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2004100393079A Expired - Fee Related CN100412272C (en) | 2004-01-19 | 2004-01-19 | Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100412272C (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535445A (en) * | 2012-02-07 | 2012-07-04 | 陕西桩鑫建设工程有限公司 | Molding device and molding method for long spiral extruding rock-entering cast-in-place pile |
CN102619218A (en) * | 2012-04-19 | 2012-08-01 | 中铁第四勘察设计院集团有限公司 | Back-insert steel reinforcement cage cement-flyash-gravel pile and pile-forming method thereof |
CN103266599A (en) * | 2013-05-13 | 2013-08-28 | 汇通路桥建设集团有限公司 | Construction method of rotating drilling dry-drilled piles of sand soil interlayer foundation |
CN104790391A (en) * | 2015-03-18 | 2015-07-22 | 北京中岩大地工程技术有限公司 | Protective cylinder device for long spiral drilling machine |
CN107130592A (en) * | 2017-04-10 | 2017-09-05 | 贾茂来 | A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction |
CN107806087A (en) * | 2017-09-22 | 2018-03-16 | 河南心连心化肥有限公司 | A kind of joint bar method after overlength CFG stakes |
CN108755686A (en) * | 2018-04-28 | 2018-11-06 | 嘉兴涌锦服饰有限公司 | The pile-driving system of piling machine |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1035154A (en) * | 1988-12-06 | 1989-08-30 | 北京市机械施工公司 | Penetrating process for clay layer below groundwater level with long spiral drill |
CN1111230C (en) * | 1994-12-26 | 2003-06-11 | 石寅生 | Making method for non-annular borehole cast-in-place pile |
JP3615082B2 (en) * | 1999-04-15 | 2005-01-26 | 戸田建設株式会社 | On-site concrete pile construction method |
DE10054459A1 (en) * | 2000-11-03 | 2002-05-08 | Schorr Claus Peter | Continuous drilling screw to construct piles has spiral surface reduced or widened dependent upon thread lead |
CN1137313C (en) * | 2000-12-27 | 2004-02-04 | 柯刚 | Pile constructing process including drilling hole with long screw and pressure depositing concrete and steel bar cage vibrating feeder |
-
2004
- 2004-01-19 CN CNB2004100393079A patent/CN100412272C/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535445A (en) * | 2012-02-07 | 2012-07-04 | 陕西桩鑫建设工程有限公司 | Molding device and molding method for long spiral extruding rock-entering cast-in-place pile |
CN102535445B (en) * | 2012-02-07 | 2013-09-04 | 陕西桩鑫建设工程有限公司 | Molding device and molding method for long spiral extruding rock-entering cast-in-place pile |
CN102619218A (en) * | 2012-04-19 | 2012-08-01 | 中铁第四勘察设计院集团有限公司 | Back-insert steel reinforcement cage cement-flyash-gravel pile and pile-forming method thereof |
CN102619218B (en) * | 2012-04-19 | 2015-09-30 | 中铁第四勘察设计院集团有限公司 | Rear slotting reinforcing cage CFG and piling method thereof |
CN103266599A (en) * | 2013-05-13 | 2013-08-28 | 汇通路桥建设集团有限公司 | Construction method of rotating drilling dry-drilled piles of sand soil interlayer foundation |
CN104790391A (en) * | 2015-03-18 | 2015-07-22 | 北京中岩大地工程技术有限公司 | Protective cylinder device for long spiral drilling machine |
CN107130592A (en) * | 2017-04-10 | 2017-09-05 | 贾茂来 | A kind of long screw auger and impact drill two-shipper is combined pore-creating filling pile construction |
CN107806087A (en) * | 2017-09-22 | 2018-03-16 | 河南心连心化肥有限公司 | A kind of joint bar method after overlength CFG stakes |
CN108755686A (en) * | 2018-04-28 | 2018-11-06 | 嘉兴涌锦服饰有限公司 | The pile-driving system of piling machine |
Also Published As
Publication number | Publication date |
---|---|
CN100412272C (en) | 2008-08-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4832535A (en) | Process for compaction-reinforcement-grouting or for decompaction-drainage and for construction of linear works and plane works in the soils | |
CN105862861B (en) | A plant pile construction method | |
CN100350105C (en) | Vibrating piling-hammer sink-pull steel protective-cylinder piling method and special steel protective cylinder | |
KR100762991B1 (en) | Precast piling method injected with high-strength mortar | |
CN101696578A (en) | Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway | |
CN104047542B (en) | Embedding rock taper pile impacts drilling pipe hammer system and embedding rock taper pile impacts construction method | |
CN101629421A (en) | Method for pulling out deep pile foundation by utilizing full slewing drilling machine | |
JP2009036010A (en) | Method of building subsidence prevention pile and subsidence prevention pile | |
CN101575852A (en) | Construction method of wall-retaining bottom-expanding sinking-pipe cast-in-situ piles | |
CN112746615A (en) | Brine stratum mucky soil cast-in-place pile construction is with protecting a section of thick bamboo device | |
DE102008056262B4 (en) | Apparatus and method for extracting cuttings and drilling mud | |
CN100412272C (en) | Concrete transplanting steel bar cage pile forming technical method of long screw hole drilling and center pump pressure | |
CN106013088A (en) | High-bearing-capacity drilling pile planting method | |
CN104711975A (en) | Construction technology for long spiral cast-in-situ bored pile | |
CN105862862B (en) | A kind of large diameter pile buries hammer Refloatation method | |
CN1206421C (en) | A drill hole grout pile drag reduction extraction process | |
AU2013351554B2 (en) | Method for manufacturing a pile | |
GB2067233A (en) | A method of constructing a collector well | |
CN102031780A (en) | Water flushing construction method of static tubular pile of sand pile tip | |
CN212335996U (en) | Resistance to compression resistance to plucking variable diameter steel reinforcement cage club-footed pile | |
CN2244572Y (en) | Hydraulic rocking full-sleeve machine for pouring pile | |
JP2000170149A (en) | Forming method for underground pile and equipment therefor | |
CN1773024A (en) | Concrete bored pile piling technology with implanted reinforced bar cage | |
CN108547301A (en) | A kind of long auger guncreting pile construction method having negative dead band | |
CN111155513B (en) | Full-slewing drilling machine and hydraulic vibration hammer cooperative well drilling method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080820 Termination date: 20130119 |