CN1521376A - Hollow slab beam and filling construction method therefor - Google Patents

Hollow slab beam and filling construction method therefor Download PDF

Info

Publication number
CN1521376A
CN1521376A CNA031137210A CN03113721A CN1521376A CN 1521376 A CN1521376 A CN 1521376A CN A031137210 A CNA031137210 A CN A031137210A CN 03113721 A CN03113721 A CN 03113721A CN 1521376 A CN1521376 A CN 1521376A
Authority
CN
China
Prior art keywords
hollow
slab beam
hollow slab
construction
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA031137210A
Other languages
Chinese (zh)
Inventor
吴学文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA031137210A priority Critical patent/CN1521376A/en
Publication of CN1521376A publication Critical patent/CN1521376A/en
Pending legal-status Critical Current

Links

Images

Abstract

The present invention provides one new kind of hollow plate girder and its construction process, and aims at solving the difficult problems of hollow plate girder in demolding and reusing hollow inside mold. The hollow plate girder has opened inside space. The construction process of the hollow plate girder includes: setting stuffing in the place corresponding to the hollow part inside the hollow plate girder, depositing concrete and taking out the stuffing to form the hollow structure. The stuffing may be formed with local material and reused. The said construction process is simple, economic and suitable for the construction of different hollow concrete plate girders.

Description

A kind of hollow slab beam and filling construction method
Technical field
The present invention relates to building structure, particularly the construction of reinforced concrete hollow slab, beam.
Background technology
Concrete core unit, beam have from heavy and light, materials economize, the bearing capacity advantages of higher, its shortcoming is that hollow internal mold can't the demoulding, the construction technology complexity.Because constructional difficulties, the hollow form of hollowcore slab, beam generally also can only adopt circle, and the construction form is generally only prefabricated, and is seldom cast-in-place.
As adopt other hollow form cast-in-place, then must adopt disposable hollow loose tool (as filling hardboard, faggot core, giving and bury hollow box etc.), because hollow mould can't can only disposablely use in the demoulding, thereby the cost of construction is higher, and the scene is cast-in-place construction seldom.
One of reason that causes existing hollow slab beam cast-in-place construction difficulty is that the cavity in the existing hollow slab beam is the space of a sealing.
Summary of the invention
Can't the demoulding in order to overcome existing hollow body construction internal mold, hollow mould can not a reusable difficult problem.The invention provides a kind of new hollow slab beam and job practices thereof, this hollow slab beam, its inner cavity is the space of an opening, adopt new job practices simultaneously, this method is built at hollowcore slab grain can take out packing material after finishing easily, packing material can be reused, and the function of use according to floor requires autotelic selection packing material to fill and enclosed cavity simultaneously.
Specific embodiments of the present invention are: the hollow part in hollow slab beam, earlier with packing material installation in position (fillings), wait fluid concrete to finish after, thereby in hollow slab beam formation structure hollow body.
Entity is filled construction method, the hollow part in hollow slab beam, earlier with entity packing material installation in position (filling), wait fluid concrete after.By the hole on the plate-girder with all or part of taking-up of packing material, thereby in hollow slab beam, form cavity.
The entity packing material can use various solid materials, for example whole bulk material (as the foams of lighter weight etc.), disperses bulk material, discrete material, flexible material, fluent material.Discrete material is selected natural sandstone, saw foam, earth, ash etc.; Also industrial goods be can select, quarrel, baton round etc. abandoned as industry and life; Bulk material such as light-weight brick, hollow pot, also can be faggot core etc.; , fluent material such as water, mud, mud liquid etc.
The selection of packing material should consider to gather materials on the spot in principle and the construction facility (recovery) and require autotelic selection packing material to fill according to the function of use of floor.For example the heat preservation and soundproof floor of having relatively high expectations should select for use heat-insulating and noise-insulating material to do packing material (seeing embodiment for details)
The way of recycling of packing material is a lot, can be tear open, take out, dig, get, mode such as dissolving.
Cement paste flows into packing material or produces reaction during for fear of fluid concrete, simultaneously also for the convenience of the demoulding.Should establish separation layer in entity packing material outside, insolated layer materials has a lot, as plastic paper, mineral wool board etc.
Hollow body is filled construction method, in the hollow part of hollow slab beam, earlier with packing material (hollow body) installation in position (filling), wait fluid concrete after.Thereby in hollow slab beam, form cavity.
The shape of hollow body can be determined as required, can be pipe, basin, polyhedron isometric(al) body.The material of hollow body can be gathered materials on the spot.
Hollow body is characterised in that it is non-enclosure space.The cavity that hollow body forms in hollow slab beam has specific purposes.
Hollow body also can be the semiclosed empty van of sheet material assembly unit, by underfloor (on) hole of face takes out packing material, thereby form hollow body in hollow slab beam.
Capsules is filled construction method, in the hollow part of hollow slab beam, will inflate (water) Capsules material installation in position (filling) earlier, wait fluid concrete after.Capsules is taken out the cavity up and down by hollow slab beam, thereby in hollow slab beam, form the structure hollow body.Capsules has a plurality of independent air bags.
A kind of hollow slab beam: it is made up of upper plate, lower plate and intermediate connector and cavity.It is characterized in that: in hollow slab beam upper face or lower face perforate, the enclosed cavity in the hollow slab beam is opened the space that makes it to become an opening, the space of being convenient to form removal and using cavity body.
Connector can be various, can be floor, or column.Finish and to cover at hollow slab beam upper face or lower face perforate construction, also can give over to decorate and use.
Compared with prior art, the present invention has following advantage.
1, discrete material filling construction method is a kind of very easy, economic hollow slab beam job practices.It is applicable to the reinforced concrete hollow slab beam construction that any form is hollow.Discrete material can be gathered materials on the spot, and reuses.Construction still is effective to municipal bridge (case beam).
2, the floor higher to the heat preservation and soundproof performance requirement, it is effective more economically to adopt a prose style free from parallelism to fill construction method.
3, the construction technology that adopts hollow box body to fill the construction hollow slab beam is a kind of very easy, hollow slab beam job practices of using.And can guarantee the compactness of lower plate concrete pouring.
4, adopt phoenix pipe and steel pipe to fill the construction technology of construction hollow slab beam, promptly can save indoor headroom significantly, realize that a plate uses more again.
Description of drawings
The present invention is further illustrated below in conjunction with drawings and Examples:
Fig. 1 is a hollow beam cross-sectional structure schematic diagram; Fig. 2 is the A-A sectional drawing of Fig. 1.
Fig. 3 is a hollowcore slab cross-sectional structure schematic diagram; Fig. 4 is the A-A sectional drawing of Fig. 3.
Fig. 5 is for adopting prose style free from parallelism packing material, pouring into a mould hollowcore slab Concrete Construction process schematic representation at twice; Fig. 6 is the hollow slab beam structure schematic diagram after this worker's method construction is finished;
Fig. 7 fills construction hollowcore slab process schematic representation for adopting container splendid attire prose style free from parallelism packing material.Fig. 8 is the hollow slab beam structure schematic diagram after this worker's method construction is finished;
Fig. 9 fills construction hollow slab beam construction technology schematic diagram for adopting the hollow body material.
Figure 10 fills construction hollow slab beam construction technology schematic diagram for adopting the hollow insulating airduct.
Figure 11 is for adopting the construction technology schematic diagram of block packing material construction hollow slab beam.Figure 12 is the hollow slab beam structure schematic diagram after this worker's method construction is finished;
Figure 13 fills the construction technology schematic diagram of construction hollow slab beam for adopting hollow steel pipe.Figure 14 is the A-A sectional drawing of Figure 13.
Figure 15 fills the construction technology schematic diagram of construction hollow slab beam for adopting hollow box body.Figure 14 is the A-A sectional drawing of Figure 13.
Figure 16 is for adopting the construction technology schematic diagram of inflation (water) capsule construction hollow slab beam.
Figure 17 is many air chambers Capsules structural representation.
1 expression top plate among the figure, 2 expression lower plywoods, 3 expression connectors, 5 presentation-entity inserts are boxed out in giving of being provided with on the 4 expression lower plywoods, 6 are illustrated in the separation layer of laying on the entity inserts, 7 are illustrated in to give on the connector and stay steel bar end, the hollow obturator of 8 expressions, 9 expression scaffold support systems, 10 expression spray arms, 11 expression split bolts.12 expression capsules, 13 expression glue overcoats, the air chamber in the 14 expression capsules are (following all with) at interval.
Embodiment describes in detail
Fig. 1, Fig. 2 are respectively hollow beam, plated construction schematic diagram, and Fig. 3, Fig. 4 are respectively the A-A sectional drawing of Fig. 1, Fig. 2.Top plate, lower plywood and middle connector are formed hollow-core construction, and giving of being provided with on the lower plywood 2 boxed out, and is mainly used in the construction of hollowcore slab, girder construction, treat that the structure construction back available water cement mortar that finishes is floating, also can give over to decorate and use.
Fig. 5 is for adopting prose style free from parallelism packing material, pouring into a mould hollowcore slab Concrete Construction process schematic representation at twice, and packing material is selected middle rough sand for use.Sequence of construction: behind the steel concrete of first formwork erection construction lower plywood 2 and connector 3, remove the template of connector, give on the connector and stay steel bar end, so that link to each other when building with top plate.Cavity is filled with discrete material 5, directly is filled to top plate bottom surface absolute altitude, lays separation layer on discrete material, and colligation upper strata floor bar and fluid concrete on separation layer are then extracted discrete material out by giving of the lower floor's floor hole of boxing out with vacuum pump.
The hollow slab beam structure schematic diagram that Fig. 6 finishes for this worker's method construction.After concrete pouring was finished, separation layer 6 was pasted together with upper strata floor 1, and separation layer should be selected cheap materials such as plastic paper.When floor inhale (every) when sound was had relatively high expectations, separation layer can adopt mineral wool board or other damping materials, after concrete pouring was finished, heat-preservation cotton (or mineral wool board) can be pasted together with the upper strata floor, thereby had improved the heat preservation and soundproof performance of floor.
Fig. 7 fills construction hollowcore slab process schematic representation for adopting container splendid attire prose style free from parallelism packing material.Sequence of construction: container 8 installation in position that will install prose style free from parallelism packing material 5 earlier, on discrete material, lay separation layer 7, colligation upper strata floor bar and fluid concrete on separation layer are then extracted discrete material out by giving of the lower floor's floor hole of boxing out with vacuum pump.
Fig. 8 is the hollow slab beam structure schematic diagram after this worker's method construction is finished.After concrete pouring was finished, separation layer 7 was pasted together with upper strata floor 1.
Fig. 9 fills construction hollow slab beam construction technology schematic diagram for adopting the hollow body material.The hollow body material can be various materials, as plastic pipe.In construction, be out of shape and fragmentation for fear of body, can fill bodys 8 by lightweight discrete material (sawdust) 5.Construction finishes, and lightweight discrete material (sawdust) is regained.
Figure 10 fills construction hollow slab beam construction technology schematic diagram for adopting the hollow insulating airduct.The hollow body material directly adopts air chimney 8.The airduct that processes is directly imbedded in the hollow slab beam, in construction, be out of shape, can fill with lightweight discrete material (sawdust) 5 for fear of airduct.Concrete construction finishes, and lightweight discrete material (sawdust) is regained.
Figure 11 is for adopting the construction technology schematic diagram of block packing material construction hollow slab beam.Packing material adopts foam block 5.Concrete construction finishes, and with solvent the foam block dissolving is regained.Figure 12 is the hollow slab beam structure schematic diagram after this worker's method construction is finished;
Figure 13 fills the construction technology schematic diagram of construction hollow slab beam for adopting hollow steel pipe.Packing material adopts hollow steel pipe, and for example with the fire-fighting spraying pipe 8 that processes, pressure testing finishes and directly imbeds in the hollow slab beam, gives on being responsible for and stays an interface tube 10.Figure 14 is the A-A sectional drawing of Figure 13.
Figure 15 fills the construction technology schematic diagram of construction hollow slab beam for adopting hollow box body, and Figure 14 is the A-A sectional drawing of Figure 13.Packing material adopts hollow box body 8, uses between hollow box body and the hollow box body drawing screw 11 fixing.Its characteristics are: concrete pouring finishes, and before initial set, adopts artificial by hole 4 that the concrete of lower plate 2 is floating or mend slurry.Hollowcore slab construction finishes, and the sheet material piecemeal of hollow box body 8 is split out.
Figure 16 is for adopting the construction technology schematic diagram of inflation (water) capsule construction hollowcore slab.With adhesive plaster overcoat 13 two (or more than two) inflation (water) capsule 12 is nested together.After concrete pouring finishes, Capsules venting back is taken out by following cavity 4.
Figure 17 is many independent air chambers Capsules structural representation.Design aerated capsule with square or other shapes, just Capsules must be designed to many air chambers hollow-core construction, as figure 17 cities, design has a plurality of air chambers 12 at interval in the capsule, adhesive tape 14 at interval is non-telescoping, and inflation back Capsules is a square structure like this.The venting back we can utilize negative pressure that Capsules is dwindled taking-up.
Purpose with several independent air chambers of design in the capsule, size and dimension and weight after being to regulate the air pressure (or hydraulic pressure) of each independent air chamber and then regulating the aerated capsule inflation, determine the part independent air chamber is inflated according to the construction dimensional requirement like this, establish the adhesive plaster overcoat in the aerated capsule outside as required during construction.
Figure 18 is many independent air chambers Capsules structural representation.

Claims (10)

1, a kind of hollowcore slab, beam, it is made up of upper plate, lower plate and intermediate connector and cavity body.It is characterized in that:, the enclosure space in the hollow slab beam is opened the cavity that makes it to become an opening in the peripheral perforate of hollow slab beam.
2, hollow slab beam job practices according to claim 1, feature also is: the hole in the perforate of hollow slab beam periphery has specific purposes, as is used to reclaim packing material or plays decoration function etc.
3, entity is filled construction method, it is characterized in that: in the hollow part of hollow slab beam, earlier with solid material installation in position (filling), wait fluid concrete after.Thereby in hollow slab beam, form the structure hollow body.
4, entity according to claim 3 is filled and is received construction method, and feature also is: by above the hollow slab beam or following hole with all or part of taking-up of packing material, and in hollow slab beam, form hollow body.
5, entity according to claim 3 is filled and is received construction method, and feature also is: solid material is discrete material, bulk material, fluent material etc.Separation layer is established in outside at packing material.
6, hollow body fill to be received construction method, it is characterized in that: in the hollow part of hollow slab beam, earlier with hollow body material installation in position (filling), wait fluid concrete after.Thereby in hollow slab beam, form the structure hollow body.
7, hollow body according to claim 6 is filled construction method, and feature also is: hollow volumes is the space of an opening.For example the hollow body material is the open hollow body with the sheet material assembly unit.
8, Capsules is filled construction method, it is characterized in that: in the hollow part of hollow slab beam, will inflate (water) Capsules material installation in position (filling) earlier, wait fluid concrete after.By above the hollow slab beam or following hole packing material is taken out, thereby in hollow slab beam, form the structure hollow body.
9, hollow body according to claim 8 is filled construction method, and feature also is: a plurality of gas (water) capsule is arranged in the obturator.
10, a kind of inflation (water) capsule of the hollow slab beam that is used to construct is characterized in that: have a plurality of air chambers at interval and independent gas (water) chamber.
CNA031137210A 2003-01-30 2003-01-30 Hollow slab beam and filling construction method therefor Pending CN1521376A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA031137210A CN1521376A (en) 2003-01-30 2003-01-30 Hollow slab beam and filling construction method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA031137210A CN1521376A (en) 2003-01-30 2003-01-30 Hollow slab beam and filling construction method therefor

Publications (1)

Publication Number Publication Date
CN1521376A true CN1521376A (en) 2004-08-18

Family

ID=34283784

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA031137210A Pending CN1521376A (en) 2003-01-30 2003-01-30 Hollow slab beam and filling construction method therefor

Country Status (1)

Country Link
CN (1) CN1521376A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1318711C (en) * 2005-01-28 2007-05-30 刘国模 Construction of steel bar reinforced hollow concrete floor cast-in-situs
CN100422461C (en) * 2004-11-22 2008-10-01 邱则有 Precast cavity structural member with reinforcing bar concrete
CN100429366C (en) * 2004-11-22 2008-10-29 邱则有 Cavity structural member for hollow concrete slab
CN100439621C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN100439623C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN100439624C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN100439622C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN1854432B (en) * 2005-04-20 2010-12-29 孙长顺 Building template
CN101457565B (en) * 2004-11-22 2011-04-27 湖南邱则有专利战略策划有限公司 Cavity member for concrete hollow slab
CN102168425A (en) * 2010-11-12 2011-08-31 张永忠 Water bag isolation body
CN104652250A (en) * 2015-02-04 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Hollow slab beam and preparation method thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100422461C (en) * 2004-11-22 2008-10-01 邱则有 Precast cavity structural member with reinforcing bar concrete
CN100429366C (en) * 2004-11-22 2008-10-29 邱则有 Cavity structural member for hollow concrete slab
CN101457565B (en) * 2004-11-22 2011-04-27 湖南邱则有专利战略策划有限公司 Cavity member for concrete hollow slab
CN100439621C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN100439623C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN100439624C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN100439622C (en) * 2004-11-23 2008-12-03 邱则有 Precast member for lightweight board
CN1318711C (en) * 2005-01-28 2007-05-30 刘国模 Construction of steel bar reinforced hollow concrete floor cast-in-situs
CN1854432B (en) * 2005-04-20 2010-12-29 孙长顺 Building template
CN102168425A (en) * 2010-11-12 2011-08-31 张永忠 Water bag isolation body
CN104652250A (en) * 2015-02-04 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Hollow slab beam and preparation method thereof

Similar Documents

Publication Publication Date Title
CN1521376A (en) Hollow slab beam and filling construction method therefor
CN1280502C (en) Concrete filled shuttering member
CN101041980A (en) Lightweight plaster wall and integral pouring procedure thereof
RU2006139806A (en) MULTI-LAYERED WALL PANEL, METHOD FOR ITS MANUFACTURE AND METHOD FOR BUILDING AN EXTERNAL WALL OF A MONOLITHIC-FRAME BUILDING FROM MULTILAYERED WALL PANELS
WO2006050665A1 (en) A filling mould and the sandwich and hollow structure thereof
CN1070711A (en) Anti-seismic heat-preservation building blocks and manufacturing thereof
CN2592751Y (en) Light reinforced concrete dense-rib sandwich board
CN1206429C (en) Wall module of well walls and method for building wall bodies of well walls by using module
CN1445422A (en) Gas-filled type tube mold for cast-in-situ concrete hollow floor
CN1955397A (en) Hollow mould
CN1637217A (en) Hollow floor slab with small dense ribs and its production process
CN2603151Y (en) Lightened precasting concrete wall panel or salb
CN1270038C (en) Hollow cavity shuttering member
CN101152731B (en) Method for manufacturing cavity formwork member
CN1075444A (en) Construction process
CN1148505C (en) Construction method for air permeable and heat exhausting wall
CN1847553A (en) In-situ cast hollow concrete slab
CN1847541A (en) In-situ cast hollow concrete slab
CN1304709C (en) Cast-in-place concrete hollow cavity shuttering member
CN101096876B (en) Cavity formwork member
CN1236170C (en) A hollow component for concrete
CN1940230A (en) Cavity mold-shell constructural component for cast-in-situs concrete
CN1320234C (en) Light stuffing mould component for concrete poured-in-situs
CN101096877B (en) Cavity formwork member
CN101096871B (en) Cavity formwork member

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication