CN1485538A - Integrated hydroelectric power station - Google Patents

Integrated hydroelectric power station Download PDF

Info

Publication number
CN1485538A
CN1485538A CNA021310742A CN02131074A CN1485538A CN 1485538 A CN1485538 A CN 1485538A CN A021310742 A CNA021310742 A CN A021310742A CN 02131074 A CN02131074 A CN 02131074A CN 1485538 A CN1485538 A CN 1485538A
Authority
CN
China
Prior art keywords
water
fluid column
pressure piping
pressure
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA021310742A
Other languages
Chinese (zh)
Inventor
丁华清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA021310742A priority Critical patent/CN1485538A/en
Publication of CN1485538A publication Critical patent/CN1485538A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/16Mechanical energy storage, e.g. flywheels or pressurised fluids

Landscapes

  • Other Liquid Machine Or Engine Such As Wave Power Use (AREA)

Abstract

The invention discloses an integration type hydroelectric power station, wherein a liquid column of water inlet and a liquid column of water outlet are arranged at a same liquid level, between which n pressure conduits are connected in parallel, m water wheel generating set are connected in series along the n pressure conduits, the other end of the pressure conduit connects with the water inlet or water outlet liquid column or the hydraulic head. The apparatus in accordance with the invention can fully utilize the water resource, and change the single machine surplus water power generation into group machines integration generation.

Description

A kind of integrate hydrelectric power station
Technical field
The present invention relates to a kind of hydroelectric power facility.
Background technique
Conventional hydroelectric power plant generally all is by the interception surface runoff, builds a dam and chokes water, and raises head, and the vantage point on the dam is installed several units side by side, by the impulse water turbine group work done generating that discharges water.This kind generation mode is that unit is abandoned the water generating.Above-mentioned conventional hydroelectric power has cleanliness without any pollution, startup-shutdown is flexible, operating cost is low and manage advantages such as simple.Except that having above-mentioned advantage, conventional hydroelectric power mode exists following shortcoming: generating is subjected to the restriction of head fall, and when head fall can not satisfy generating and requires, unit just can not generate electricity.Be subjected to above-mentioned condition restriction, more remote mountain area is generally built in the power station in, and the Regional Distribution inequality, disperses and small scale.Traditional generation mode also exists the shortcoming that water waste can not be undertaken basic lotus greatly and generally.
Summary of the invention
A kind of integrate hydrelectric power station of the present invention can solve under the less same liquid level condition of storage capacity, utilizes a succession of integrated hydraulic generator unit, combines with the pressure piping that designs by fast loop structure, finishes when the problem of pressing the pumped storage generating.
A kind of integrate hydrelectric power station of the present invention, it is made of jointly pressure piping and cluster engine; It is characterized in that: under same liquid level, be provided with the water-in and water-out fluid column, between the water-in and water-out fluid column and be connected to n bar pressure piping, each pressure piping is with highly gradually low trend or level trend, is connected with in regular turn that head does not wait or equal m vertical hydrogenerator group or tubular-turbine generator group.N hydraulic generator unit in horizontal co-altitude of n bar pressure piping or co-located arrangement constitutes a generating substation; The initial station of described generating substation directly is connected with the water inlet fluid column by pressure piping, and the terminal of generating substation is to be connected with the water outlet fluid column by pumping station; On the pressure piping between described adjacent two hydraulic generator units, be vertical Vertical direction and be connected with the big also pressure pipe road of internal diameter specific pressure internal diameter of the pipeline, described each also the pressure pipe road the other end all with water inlet fluid column or water outlet fluid column in one directly be communicated with, also can the part and the water inlet fluid column, the part be communicated with respectively with the water outlet fluid column; Realize being interconnected greater than the sphere of also pressure pipe internal diameter or the three-way interface device of billiard table shape by an internal diameter between described also pressure pipe and the pressure piping; In the also pressure pipe road on sphere or billiard table shape interface, can be fixed with one or more, and spaced eck, corresponding to each eck is that waist passes eck, the float that is the I font, described float inner chamber bottom fills water, vertically floats in the water to guarantee it, and can fluctuate under the eck restriction; Be positioned at the pressure piping at generator set place, by work done pipeline and control gate valve and by-pass line and control gate valve formation in parallel; The work done pipeline of the inlet/outlet gate valve control of described pressure piping is the high speed flow section, and this segment distance should be short as much as possible, and the sphere of described pressure piping or billiard table shape three-way interface are that horn mouth flows transition section at a slow speed.
Aforesaid a kind of integrate hydrelectric power station is characterized in that: the installation total capacity of described pumping station should be more than or equal to three times generating substation terminal electric motor power.
Aforesaid a kind of integrate hydrelectric power station is characterized in that: on pressure piping, to terminal, what be arranged in order also presses the spatial capacity in the float of chamber and the ratio of water capacity by the initial station of hydroelectric power plant, should equate or cumulative.
The present invention compares with traditional hydroelectric installation, have following advantage: head with the liquid level situation under, can be with high head, fast circuit mode is finished the jumbo hydroelectric power of multicomputer, this device has undertakes basic lotus, the functions such as waist lotus, peak load, spinning reserve of holding concurrently, its become unit abandon the water generating for group's machine contact integrated generation, utilized effective water resources fully.
Description of drawings
Fig. 1 is the overall structure schematic representation of a kind of integrate hydrelectric power station of the present invention;
Fig. 2 is a kind of example structure schematic representation of a kind of integrate hydrelectric power station of the present invention;
Fig. 3 is the plan structure schematic representation of a kind of integrate hydrelectric power station of the present invention;
Fig. 4 is the sectional view along the A-A direction of Fig. 3;
Fig. 5 is another example structure schematic representation of a kind of integrate hydrelectric power station of the present invention;
Fig. 6 is a kind of integrate hydrelectric power station of the present invention and also pressure pipe road embodiment schematic representation thereof;
Fig. 7 is the water inlet fluid column and the first substation of a kind of integrate hydrelectric power station of the present invention and the structural representation of also pressing the chamber;
Fig. 8 is the structural representation that the chamber is also pressed at pressure piping, generator set and the middle part of a kind of integrate hydrelectric power station of the present invention;
Fig. 9 is the individual also structural representation of pressure pipe in water outlet fluid column, pumping station and end of a kind of integrate hydrelectric power station of the present invention;
Embodiment
Among Fig. 1, this device is the ground type integrate hydrelectric power station, it by the inlet/outlet gate valve 3 of n bar pressure piping 1, n * m platform hydraulic generator unit 2, generator set, by-pass gate 4, underground pump station 5, master, pay pump 6, the retaining upper storage reservoir 7 that is positioned at the mountain top, water-in and water-out fluid column 9,11, m ground substation 13 being made of n generator set, head 14, also pressure pipe 15 and lower storage reservoir 22 are formed.This device also comprises the water outlet 12 of the trash rack 8 that is located at water intake 10 places of water fluid column 8 into, water outlet fluid column 11, near also pressure pipe road base 20 of the also pressure chamber 16 of setting in the also pressure pipe road 15 of pressure piping 1, eck 17, relief, waist 18,19, sphere.
Described master, a pair pump can be n * 3, and select all or part of putting into operation according to the generating needs.Among Fig. 1 given also pressure chamber 16 with also between the pressure pipe road 15 for the T type is connected, wherein part also is communicated with the fluid column of intaking in pressure pipe road 15, the also pressure pipe road 15 of another part is communicated with the water outlet fluid column.Described lower storage reservoir 22 is when upper storage reservoir 7 water levels occur being lower than head line 14, replenishes the river course at water source to upper storage reservoir 7 through water outlet fluid column 11.
That Fig. 2 provides is the embodiment of water-in and water-out fluid column 9,11 by underground circulating line formation upper storage reservoir 7, and related integrate hydrelectric power station structure is same as above.
Fig. 3 has provided the plan structure figure of this device, in the figure, has utilized water sources such as river, river, lake, sea, reservoir as upper storage reservoir 7, and the water-in and water-out fluid column is all by connections such as river, river, lake, sea, reservoirs, so do not need lower storage reservoir.The position of building a station of described integrate hydrelectric power station can be that tunnel, valley etc. are located.
Fig. 4 is the sectional view along the A-A direction of Fig. 3.Each generator set among the figure is followed successively by the arrangement mode that reduces gradually.
Fig. 5 is that each substation of integrate hydrelectric power station is all-sealed, and the latent cascaded structure form that is placed in the water.In this kind mode, also the pressure pipe road can be straight-tube, and its upper oral part directly is connected with the water source.
Among Fig. 6, also the chamber of pressure is a U type structure.The described also chamber of pressure, this integrated generation station float 18 that is in operation contains free the appearance, so be fluid column equivalent head equivalent pressure, be called for short and also press maybe when pressing, the function of also pressing chamber 16 is to allow float 18 come-ups, because float inner chamber bottom is filled with water, makes it be vertical and floats, under normal operation, making floating waist 19 support eck 17 to come-up, reach the not effect of earial drainage, is that next substation unit transmits equivalent head equivalent pressure power simultaneously.The described also chamber of pressure can be one or more groups.Also press indoor float to discharge or to increase the amount of being filled with water of its inner chamber by arrangement submersible pump thereon according to the buoyancy needs.Should maintain certain free clearance between described eck 17 and the float 18, be convenient to it and float automatically up and down.In pressure piping design, the high speed flow pipeline section of generator set should be lacked, and the pressure piping large-section is flowed pipeline section at a slow speed and should be grown.
In integrate hydrelectric power station end portion, have when pressing pumped storage pumping station 5, inhale circulation to form pump, it is main, paying pump 6 total installations of generating capacity should be more than or equal to the electric motor power of three times of last substation generator set, be convenient to by turns work such as pumped storage, standby, maintain and replace, to satisfy the flow velocity requirement of n bar pressure piping at any time.
Owing to used and also pressed chamber, pumping station, make the hydraulic loss after substation unit guide vane wheel is gone up in fire hose impact, when the fire hose impacts next substation and also presses the chamber, just recovered the equivalent pressure power of this substation fluid column equivalent head naturally, so just guaranteed the fire hose in different ought depressing in order forward, impact force is unattenuated.Pumping station is ceaselessly being discharged circulating water water outlet fluid column mouth when depressing, and is reduced to upper storage reservoir cooling recirculation and uses.
Embodiment one
Referring to Fig. 1, be Di Nuoweike (ground type) integrate hydrelectric power station, form by the clear Tianjin of Austria, Antonio Pacenza sieve, former, big flat, beautiful former, difficult to understand lucky open country, natural pond, Mo Tuochuan, Hermes and nine substations of Di Nuoweike (13) and pumping station (5) set, have storage capacity 3 * 106m at 550 meters high ridges 3Tianchi (7), cycle period 2 hours/time, clear Tianjin (13) difficult to understand, initial station is built in fluid column 490m (14) the base arc underground power house (13) on every side, and the Antonio Pacenza sieve substation (13) from fluid column head 495m is ground substation (13), substation 100m at interval up and down, gradient 5%-6%, last substation Di Nuoweike (13) equivalent head 537.5m (14), nine substations (13), article six, pressure piping (1), flow is 65.0m 3/ s, 54 units (2) can put into operation simultaneously during peak load.Pumping plant (5) has n * 12 main pump (6), flow 32.5m 3/ s, other has 6 * 3 to pay pump (6), flow 10.8m 3/ s is all in the underground oval pump house (5) under 545m head (14), when pressing the pumped storage circulating water of taking turns.Also have 4 standby multistage pumps (6) in the pump house (5), can be used for extracting the other river (22) of factory at any time, replenish upper storage reservoir (7) evaporating loss water.
At first whole unit (2) entery and delivery port gate valves (3) on closing pressure pipeline (1) line are opened unit (2) by-pass gate (4) completely, and pumping station (5) starts (6) 12 on water pump, this moment, water was from upper storage reservoir (7), pass drain grating (8), go into into water fluid column (9), enter pressure piping (1) water intake (10), the fire hose passes pressure piping (1) completely, by water pump (6), enter water outlet fluid column (11) at last, through fluid column water outlet (12), reduction upper storage reservoir (7), cooling recirculation is used.Meanwhile, treat that pressure piping (1) flow velocity reaches 65.0m 3During/s, promptly close initial station clear Tianjin substation (13) bypass lock difficult to understand and close (4), open station difficult to understand (13) unit (2) entery and delivery port gate valve (3) simultaneously, allow station unit difficult to understand (2) be with the load generating in good time; Afterwards, the fire hose seals in Antonio Pacenza sieve substation (13), also presses chamber (16), upper storage reservoir (7) Chi Shui also presses chamber eck (17), float (18), (19) by 495m fluid column head (14) and handkerchief station, ought press and pass to penstock (1) fire hose, the fire hose impacts to handkerchief station (13) unit (2) stator with 495m equivalent pressure, when reaching 65.0m 3During/s flow velocity, handkerchief station unit (2) also is with the load generating, next close the former substation in natural pond (13) gate valve (4), open station, natural pond gate valve (3), the fire hose is scurried into station, natural pond (13) from handkerchief station (13) tail water and is also pressed chamber (16), the fire hose is promptly used the equivalent pressure power of 501m head (14), continues to impact to station, natural pond (13) unit (2) stator.What the fire hose impacted 507m head (14) successively divides station (13) unit (2) greatly equally, the beautiful former substation (13) of 513m head (14), the difficult to understand lucky wild substation (13) of 519m head (14), the not holder river substation (13) of 525m head (14), the Hermes substation (13) of 531m head (14) and the last substation Di Nuoweike (13) of 537.5m head (14), the last fire hose by the water pump group (6) of pumping station (5) at 545m fluid column head (14) when depressing, pumped storage is discharged water outlet fluid column mouth (12) by turns, reduction upper storage reservoir (7), enter recirculation after the cooling ... in order to keep the often fair head line (14) of upper storage reservoir (7) water level, the standby multistage pump of pumping plant (5) (6) extracts other river course (22), power station water under the mountain to upper storage reservoir (7) off and on, replenishes upper storage reservoir (7) atmospheric evaporation losses water.
When beginning to try out, central control chamber is also pressed float (18), (19) in the chamber (16) to six pipelines of exerting oneself (1) circuit, monitors debugging automatically, i.e. draining inflation before the load, increase buoyancy, make not earial drainage of eck (17), allow on pressure piping (1) line all units (2) flow consistent.Treat that unit (2) all is with back (18), (19) the water-filling exhaust again of loading and operate steadily on pressure piping (1) line, subtract floating supercharging, make (18), (17) equilibrium phase paste not earial drainage, each substation head (14) is maximum value when pressure, all units (2) are maximum output on pressure piping (1) line, promptly enter normal operating phase.
Before integrated, Di Nuowei restrains the pumped storage power station of all substations (13) for disperseing, exerting oneself loses more than gain, after integrated, can undertake basic lotus, waist lotus, peak load and spinning reserve, have holidays by turns, keep in repair, (54) platform unit (2) can all put into operation during peak load, except that pumping plant (5) the power consumption 3200mw of factory, Di real output 13000mw that stands accounts for 80% of this collection station power.
In the above substation, substation 1 (clear Tianjin difficult to understand) single-machine capacity is 28.1 ten thousand kilowatts, substation 2 (Antonio Pacenza sieve) single-machine capacity is 290,000 kilowatts, substation 3 (natural pond is former) single-machine capacity is 29.4 ten thousand kilowatts, substation 4 (big flat) single-machine capacity is 29.7 ten thousand kilowatts, substation 5 (beautiful former) single-machine capacity is 300,000 kilowatts, substation 6 (difficult to understand lucky wild) single-machine capacity is 30.4 ten thousand kilowatts, substation 7 (Mo Tuochuan) single-machine capacity is 30.8 ten thousand kilowatts, substation 8 (Hermes) single-machine capacity is 31.1 ten thousand kilowatts, substation 9 (Di Nuoweike) single-machine capacity is 31.5 ten thousand kilowatts, and the pumping station single-machine capacity is 210,000 kilowatts.Described pumping station should be installed 12 * 3 main pumps, pays pump for 6 * 3, pays pump power and should be 70,000 kilowatts.
Embodiment two
See Fig. 3, Fig. 4, be Bart's small stream (underground type) integrate hydrelectric power station, former by south, the pulling eye mountain, the card Stark, gill is won Ah, the Mosso that, gentle winter moral, Ka Binxi, carat agree and nine substations (13) such as Bart's small stream and pumping station (5) are gathered and formed, at a river course (22) bend place, 1.5 found the factory in kilometer long tunnel, south, initial station former (13) fluid column head 318m (14), terminal Bart small stream (13) fluid column equivalent head 368.8m (14), press 150m up and down between the substation at interval, build a station by 1/30 and 1/21 gradient, nine substations (13), six pipelines of exerting oneself (1), main, pay pump duty 95.3m 3/ 9,16.0m 3/ 9, all in the underground pump house of 379.5m fluid column head (14) lower elliptical hoop shape (5) when press taking turns pumped storage circulating water, each substation has access gallery (21) to be connected, there is an overflow dam (23) in the downstream, river course, part circulating water backflow upstream water intake (10) is exerted oneself again during dry season, and another part water overflows toward river course, downstream (22) and lets out.

Claims (3)

1. integrate hydrelectric power station, it is made of jointly pressure piping and generator set, it is characterized in that: under same liquid level, be provided with the water-in and water-out fluid column, between the water-in and water-out fluid column and be connected to n bar pressure piping, each pressure piping is with highly gradually low trend or level trend, is connected with in regular turn that head does not wait or equal m vertical hydrogenerator group or tubular-turbine generator group.N hydraulic generator unit in horizontal co-altitude of n bar pressure piping or co-located arrangement constitutes a generating substation; The initial station of described generating substation directly is connected with the water inlet fluid column by pressure piping, and the terminal of generating substation is to be connected with the water outlet fluid column by pumping station; On the pressure piping between described adjacent two hydraulic generator units, be vertical Vertical direction and be connected with the big also pressure pipe road of internal diameter specific pressure internal diameter of the pipeline, described each also the pressure pipe road the other end all with water inlet fluid column or water outlet fluid column in one directly be communicated with, also can the part and the water inlet fluid column, the part be communicated with respectively with the water outlet fluid column; Realize being interconnected greater than the sphere of also pressure pipe internal diameter or the three-way interface device of billiard table shape by an internal diameter between described also pressure pipe and the pressure piping; In the also pressure pipe road on sphere or billiard table shape interface, can be fixed with one or more, and spaced eck, corresponding to each eck is that waist passes eck, the float that is the I font, described float inner chamber bottom fills water, vertically floats in the water to guarantee it, and can fluctuate under the eck restriction; Be positioned at the pressure piping at generator set place, by work done pipeline and control gate valve and by-pass line and control gate valve formation in parallel; The work done pipeline of the inlet/outlet gate valve control of described pressure piping is the high speed flow section, and this segment distance should be short as much as possible, and the sphere of described pressure piping or billiard table shape three-way interface are that horn mouth flows transition section at a slow speed.
2. a kind of integrate hydrelectric power station as claimed in claim 1 is characterized in that: the installation total capacity of described pumping station should be more than or equal to three times generating substation terminal electric motor power.
3. a kind of integrate hydrelectric power station as claimed in claim 1 is characterized in that: on pressure piping, to terminal, the spatial capacity in the float that is arranged in order and the ratio of water capacity should equate or cumulative by the initial station of hydroelectric power plant.
CNA021310742A 2002-09-28 2002-09-28 Integrated hydroelectric power station Pending CN1485538A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA021310742A CN1485538A (en) 2002-09-28 2002-09-28 Integrated hydroelectric power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA021310742A CN1485538A (en) 2002-09-28 2002-09-28 Integrated hydroelectric power station

Publications (1)

Publication Number Publication Date
CN1485538A true CN1485538A (en) 2004-03-31

Family

ID=34144770

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA021310742A Pending CN1485538A (en) 2002-09-28 2002-09-28 Integrated hydroelectric power station

Country Status (1)

Country Link
CN (1) CN1485538A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1828042B (en) * 2006-03-10 2010-04-21 清华大学 Runner of opposite-rotating through flow turbine capable of bidirectionally generating electricity
CN102434359A (en) * 2011-11-04 2012-05-02 上海瑞华(集团)有限公司 Semi-submersible type power generating set floating on water and suitable for stream flows in river channel and using method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1828042B (en) * 2006-03-10 2010-04-21 清华大学 Runner of opposite-rotating through flow turbine capable of bidirectionally generating electricity
CN102434359A (en) * 2011-11-04 2012-05-02 上海瑞华(集团)有限公司 Semi-submersible type power generating set floating on water and suitable for stream flows in river channel and using method
CN102434359B (en) * 2011-11-04 2013-11-27 上海瑞华(集团)有限公司 Semi-submersible type power generating set floating on water and suitable for stream flows in river channel and using method

Similar Documents

Publication Publication Date Title
US8231327B2 (en) River high pressure energy conversion machine
WO1995010706A1 (en) System for conversion of sea wave energy
JP6873444B2 (en) A system that uses the energy storage pipes of multiple high-rise buildings to generate electricity
EP4065832B1 (en) Energy generation and water conservation
CN105502752A (en) Mountain area rainwater potential energy recycling and purification and reutilization integrated system and rainwater recycling and purifying method
CA2458286C (en) A system for generating power
CN103556611A (en) Plunge pool water filling and discharging system capable of generating electricity
CN102808398A (en) Reverse osmosis seawater desalination and coastal storage power station linking method and desalination system
CN1485538A (en) Integrated hydroelectric power station
JPS5862378A (en) Hydraulic power generating system in multistage dam
KR20200002084A (en) The non-power eletric pumping water and small hydropower system
CN109944301A (en) A kind of clear water reserviors absorbing well, absorption well system and application method
CN115126643A (en) Tidal wave air energy storage power generation system
CN203362382U (en) Hydropower generation system
WO2003050411A1 (en) Over-bridging device of hydroelectric power plant lake
Ramos et al. Small hydro as one of the oldest renewable energy sources
CN2233468Y (en) Atmospheric pressure, vacuum suction synchronous flow hydroelectric generator set
WO2020235842A1 (en) Building-type pumped storage power generation system
CN1065319C (en) Synchronous flow hydroelectric generator set utilizing atmosphere pressure and vacuum suction
RU2002888C1 (en) Pressure derivation cascade for hydro-electric power station
EP4382672A1 (en) Hydrokinetic chamber and chamber for generating hydrokinetic energy pertaining to the energy-generating module of a floating hydroelectric power plant
SU901424A1 (en) Gravity and siphon system for producing water supply to water power units
CN101029482A (en) Circulating hydraulic electric-power generation station
JPS61106980A (en) Forced water feeding hydroelectric power generation system
WO2016079657A1 (en) Hydroelectricity and compressed-air power plant system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication