CN1327921C - Golf conveying appliance of golf training gymnasium - Google Patents

Golf conveying appliance of golf training gymnasium Download PDF

Info

Publication number
CN1327921C
CN1327921C CNB031494137A CN03149413A CN1327921C CN 1327921 C CN1327921 C CN 1327921C CN B031494137 A CNB031494137 A CN B031494137A CN 03149413 A CN03149413 A CN 03149413A CN 1327921 C CN1327921 C CN 1327921C
Authority
CN
China
Prior art keywords
ball
golf
mentioned
conveying device
collection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB031494137A
Other languages
Chinese (zh)
Other versions
CN1565685A (en
Inventor
金时明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB031494137A priority Critical patent/CN1327921C/en
Publication of CN1565685A publication Critical patent/CN1565685A/en
Application granted granted Critical
Publication of CN1327921C publication Critical patent/CN1327921C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Handcart (AREA)

Abstract

The present invention relates to a golf ball collecting, cleaning and vertically conveying device used for automatically supplying golf balls again after the golf balls which are struck out by golf athletes in a multi-layer golf training course are recovered and cleaned. In particular, the present invention can not only save the needed manufacture cost and the installing cost, but also be a golf ball conveying device which is integrally composed of a once ball collecting cylinder, a washer and a secondary ball collecting cylinder in the golf training course, wherein the once ball collecting cylinder is used for collecting golf balls which are struck out, the washer is used for washing the collected balls, and the secondary ball collecting cylinder is used for collecting the washed balls to convey the golf balls to a vertical conveying part.

Description

The golf ball conveying apparatus in golf training shop
Technical field
The present invention relates to a kind of ball that the golfer is got in the golf training shop of multilayer and be recovered to the Machine Room, clean, automatically golf is supplied to the golf ball conveying apparatus of each layer again, especially, can save the expense of making needed expense and being produced with installation, 1 collection ball tube that will compile on the other hand, the ball of getting, the cleaning machine of the ball that compiles with cleaning, and 2 collection ball tubes that compile the ball that cleaned in order to be transported to vertical transport portion are made the golf ball collecting device and vertical ball feeding device to each layer conveying in the golf training shop of one.
Background technology
Generally speaking, the golf training shop of multilayer can automatically supply to each layer with golf as shown in Figure 1, and is as follows to its a series of procedure declaration:
Accommodated golf in the ball collection box 5 and passed each inflow entrance 6a towards the vertically disposed vertical transport of each layer portion 6, supply to its inside, pass inflow entrance 6a and enter into ball in the vertical transport portion 6, be loaded on oscilaltion in vertical transport portion 6, and be arranged in the suspension bucket (being provided with continuously) of the chain of trade shape along chain, if suspension bucket rises along chain, arrive the top of vertical transport portion 6, then make ball drop into input port 6b.Drop into the ball of input port 6b continuously, pass the horizontal feed device 7 of each layer, supply to the position of respectively playing ball.
In addition, the ball of getting in the position of respectively playing ball via recovery approach 1 → ball collection box 2 → cleaning machine 3 → drying machine 4, is pooled in the above-mentioned ball collection box 5, through process as previously discussed, supplies to each layer once more.In said process, in vertical transport portion 6 inside, chain is made trade shape, and from the bottom to top, rotate repeatedly to the bottom from top, a plurality of suspension buckets constitute trade shape along chain, and are connecting side by side.
The vertical transport portion of existing training building as previously discussed, portion vertically is provided with the bearing support of the steel construction of the ceiling that connects ground and each layer within it, and chain is arranged on this bearing support, at the outer setting cover of bearing support.In this occasion, the problem of existence is, because above-mentioned bearing support and cover have improved the expense of making needed expense and being produced with installation.
And, accommodated golf in the ball collection box 5 and passed each inflow entrance 6a towards the vertically disposed vertical transport of each layer portion 6, supply to its inside, pass inflow entrance 6a and enter into ball in the vertical transport portion 6, be installed in vertical transport portion 6 oscilaltion and be arranged in the suspension bucket of conveyer of trade shape, suspension bucket rises along conveyer, if arrive the top of vertical transport portion 6, then makes ball drop into input port 6b.Drop into the ball of input port 6b continuously, pass the horizontal feed device 7 of each layer, supply to the position of respectively playing ball.
Though the ball of getting in the position of respectively playing ball, respectively via the ramp or the collection box 1 → ball collection box 2 → cleaning machine 3 → drying machine 4 that are provided with respectively, be pooled in the above-mentioned ball collection box 5, through process as previously discussed, supply to each layer once more, but, in said process, if ball supplied to 1 vertical conveying device of cleaning machine or cleaning machine 3 breaks down or cleaning machine 3 runs into the phenomenon of workload excess load, then at 1 ball collection box 2, the staff must derive ball by handwork, shift to ball collection box 52 times, very inconvenient.In addition, though the ball of getting can reclaim with cleaner state, but, in order to clean such ball one by one, some power and water power can be consumed very lavishly, on the other hand, above-mentioned ball collection box 2, cleaning machine 3, ball collection box 5 are provided with respectively, improved the expense of making needed expense and being produced with installation, owing to need very big fabricating yard, so also there is uneconomic problem.
The present invention considers that situation as previously discussed proposes, its purpose is to provide a kind of can save the expense of making needed expense and being produced with installation, on the other hand, will compile 1 collection ball tube of the ball beaten and clean the cleaning machine of the ball that compiles and compile 2 times of the ball that cleaned in order to be transported to vertical transport portion and collect the ball tubes and make the golf ball conveying apparatus in the golf training shop of one.
Summary of the invention
In order to reach purpose as previously discussed, the invention provides the golf ball conveying apparatus in a kind of golf training shop, golf can be supplied to each layer in the golf training shop that constitutes by multilayer, the upper support body and the lower support body of rectangle framework are set on the ground of above-mentioned each layer and Machine Room, on the other hand, on its exterior face, cover is set, last, be provided with the driven axle and the driving shaft of pair of sprocket on the lower support body, on above-mentioned sprocket wheel, chain is set, simultaneously, the suspension bucket of a plurality of dress golf is set on this chain, on the other hand, the golf ball conveying apparatus in a kind of golf training shop is provided, the ball warp of getting in the position of respectively playing ball in the golf training shop that is made of multilayer is by the ball recovery approach, and be cleaned clean, supply to each layer once more, be connected with passage with the vertical transport portion that ball is supplied to above-mentioned each layer, on the other hand, one side of 2 collection ball tubes that form at the cylindrical shell by regular hexahedron with opened upper end is inner to be formed 1 time of packing into via the ball of above-mentioned recovery approach and collects the ball tube, formation will collect in the vertical conveying device that this 1 time ball in the collection ball tube vertically is transported to top, simultaneously, form ramp and cleaning machine in the one side.
Description of drawings
Fig. 1 is a stereogram of representing the structure in existing golf training shop briefly.
Fig. 2 is the side view of vertical conveying device of representing the golf ball conveying apparatus in golf training of the present invention shop briefly.
Fig. 3 A is the stereogram of upper support body of the 1st embodiment of expression vertical conveying device of the present invention.
Fig. 3 B is the stereogram of upper support body of the 2nd embodiment of expression vertical conveying device of the present invention.
Fig. 4 A is the stereogram of lower support body of the 1st embodiment of expression vertical conveying device of the present invention.
Fig. 4 B is the stereogram of lower support body of the 2nd embodiment of expression vertical conveying device of the present invention.
Fig. 5 A is the cutaway view that golf ball conveying apparatus is set on the upper support body of Fig. 3 A.
Fig. 5 B is the cutaway view that golf ball conveying apparatus is set on the upper support body of Fig. 3 B.
Fig. 6 A is the cutaway view that golf ball conveying apparatus is set on the lower support body of Fig. 4 A.
Fig. 6 B is the cutaway view that golf ball conveying apparatus is set on the lower support body of Fig. 4 B.
Fig. 7 is the side view of the tension-adjusting gear of golf ball conveying apparatus of the present invention.
Fig. 8 is the stereogram of the sprocket wheel of golf ball conveying apparatus of the present invention.
Fig. 9 is the stereogram of the suspension bucket of golf ball conveying apparatus of the present invention.
Figure 10 A is the vertical view that expression is arranged on the vibration-proof structure among the 1st embodiment of vertical conveying device of the present invention.
Figure 10 B is the vertical view that expression is arranged on the vibration-proof structure among the 2nd embodiment of vertical conveying device of the present invention.
Figure 10 C is the stereogram that expression is arranged on the vibration-proof structure among the 2nd embodiment of vertical conveying device of the present invention.
Figure 11 is a vertical view of representing ball collection box of the present invention briefly.
Figure 12 is the side sectional view of the internal structure of expression ball collection box of the present invention.
Figure 13 is the front section view of the internal structure of expression ball collection box of the present invention.
The specific embodiment
Below, particularly embodiments of the invention are described with reference to the accompanying drawings.
As shown in Figure 2, the golf vertical conveying device 120 of the golf ball conveying apparatus in golf training of the present invention shop, the suspension bucket 17 that to contain golf continuously is arranged on makes vertical trade shape, and from the bottom to top, from top on a pair of chain 14b of bottom lifting, above-mentioned chain 14b is arranged between lower support body 13 and the upper support body 12, only on the exterior face of above-mentioned upper support body 12 and lower support body 13, be respectively equipped with the cover 12c that has input port and inflow entrance respectively, 13c, wherein, above-mentioned lower support body 13 is arranged on the ground of Machine Room, and above-mentioned upper support body 12 is arranged on the floor 10 of each layer.
Above-mentioned upper support body 12 is made the framework (with reference to Fig. 3 A and Fig. 3 B) of the regular hexahedron with certain altitude.
Be the 1st embodiment of above-mentioned upper support body 12 shown in Fig. 3 A, four "  " shape iron plates that are commonly referred to angle steel form pillar with sustained height, on the other hand, form conveying device the 12a of portion is set.Above-mentioned conveying device is provided with the 12a of portion, and to make two angle steel be a pair of, and subtend is provided with in this conveying device on the medial end portions of the 12a of portion mutually, forms the fixed part 12b of the level of promising rectangle frame body.That is, the fixed part 12b of rectangle framework is placed on the ground of building floor 10, fixing with foundation bolt etc., therefore, the framework of above-mentioned regular hexahedron-upper support body 12 erectly is fixed on the floor 10.
Be the 2nd embodiment of above-mentioned upper support body 12 shown in Fig. 3 B, be configured to make two iron plates that bend to " ㄈ " shape of sustained height to stand facing each other mutually, constitute pillar, form this conveying device the 12a ' of portion is set.That is, the fixed part 12b ' of rectangle framework is placed on the ground of building floor 10, fixes, erectly framework-upper support the body 12 of above-mentioned regular hexahedron is fixed on the floor 10 thus with foundation bolt etc.
As above-mentioned the 2nd embodiment, even the occasion using two to bend to the iron plate formation upper support body 12 of " ㄈ " shape because the area of iron plate is big, and the mounting portion is many, also can be provided with axle at an easy rate and waits other parts.In addition, need be on the large tracts of land of iron plate the handwork of boring is bored a hole one by one with using, welding etc., can exactly parts be arranged on the position of regulation with lifter.
The top of the 12a of portion, 12a ' is set in above-mentioned conveying device, shown in Fig. 5 A and Fig. 5 B, driven axle 16 is arranged to level, and in the both sides of this driven axle 16, as shown in Figure 8, sprocket wheel 14a is arranged on the axle with standing facing each other mutually, chain 14b parts are set on each sprocket wheel 14a, suspension bucket 17 and plate 19 are set on the carriage 14c of this chain 14b continuously.
Promptly, at the integrally formed carriage 14c of a side of above-mentioned chain 14, the both sides fixed head 17a of suspension bucket 17 that will be as shown in Figure 9 with bolt is connected on this carriage 14c, and the plate 19 that will make plate body with bolt is connected the bottom of suspension bucket 17, continuously above-mentioned suspension bucket 17 is connected the bottom of this plate 19.
On above-mentioned suspension bucket 17, as shown in Figure 9, be provided with can abundant side by side golf 17c accommodating groove 17b, be formed with the fixed head 17a on the carriage 14c that can be fixed by bolts to above-mentioned chain 14b in both sides.
Above-mentioned lower support body 13 is made the framework (with reference to Fig. 4 A and Fig. 4 B) of the regular hexahedron of certain altitude.
Be the 1st embodiment of above-mentioned lower support body 13 shown in Fig. 4 A, four "  " shape iron plates that are commonly referred to angle steel form pillar with sustained height, on the other hand, be formed with conveying device the 13a of portion is set.Above-mentioned conveying device is provided with the 13a of portion, and to make two angle steel be a pair of, and subtend mutually is provided with the bottom of the 13a of portion in this conveying device, forms the fixed part 13b of the level of promising rectangle frame body.That is, the fixed part 13b of rectangle framework is placed on the ground of a side of ball collection box 5, fixing with foundation bolt etc., therefore, the framework of above-mentioned regular hexahedron--lower support body 13 erectly fixes on the ground.
Be the 2nd embodiment of above-mentioned lower support body 13 shown in Fig. 4 B, be configured to make two iron plates that bend to " ㄈ " shape of sustained height to stand facing each other mutually, constitute pillar, form this conveying device the 13a ' of portion is set.Form the fixed part 13b ' of the level of promising rectangle frame body in the bottom that above-mentioned conveying device is provided with the 13a ' of portion.That is, the fixed part 13b ' of rectangle framework is placed on the ground of a side of ball collection box 5, fixing with foundation bolt etc., therefore, the framework of above-mentioned regular hexahedron-lower support body 13 erectly fixes on the ground.
Shown in above-mentioned the 2nd embodiment, two iron plates that bend to " ㄈ " shape in use constitute the occasion of lower support body 13, can not only be easy to wait other parts to be arranged on the large-area iron plate on axle, and, can use lifter that parts are set exactly.
Shown in Fig. 6 A and Fig. 6 B, the bottom of the 13a of portion, 13a ' is set in above-mentioned conveying device, driving shaft 15 is arranged to level, as shown in Figure 8, both sides at this driving shaft 15, sprocket wheel 14a is arranged on the axle with standing facing each other mutually, chain 14b parts are set on each sprocket wheel 14a, suspension bucket 17 and plate 19 are set on the carriage 14c of this chain 14b continuously.
Above-mentioned driving shaft 15 or driven axle 16 use adjustable plate 20 to regulate the tension force of chain 14b as shown in Figure 7, and above-mentioned adjustable plate 20 usefulness bolt 20b make its upper and lower moving, and 20a moves up and down along guide rail.
In addition, golf vertical conveying device 120 of the present invention possesses chain frame 21,21 ' (with reference to Figure 10 A and Figure 10 B) that prevents chain 14b vibration.
As above-mentioned the 1st embodiment, the occasion of above-mentioned upper and lower part supporting mass 12,13 is set with four "  " shape iron plate posts, shown in Figure 10 A, be fixed on chain frame among the 10a of hole portion of each layer with carriage 210, have the chain frame 21 of " ㄈ " shape groove in this setting, make its supporting be arranged on the chain 14b of 2 layers or 3 layers.Every layer possesses four above-mentioned chain frames 21, supporting 2 row's chain 14b.
As above-mentioned the 2nd embodiment, the occasion of above-mentioned upper and lower part supporting mass 12,13 is set at the iron plate post with " ㄈ " shapes of two face-offs, shown in Figure 10 B and Figure 10 C, with whole chain frame 21 with " ㄈ " shape groove ' along conveying device the 12a ' of portion, 13a ' are set to fix supporting chain 14b.
Resemble vertical conveying device 120 actions that constitute the above making, when golf 17c was carried on top, golf 17c dropped into the space between the suspension bucket 17 sometimes, was positioned at sprocket wheel 14a top.Can hinder driving shaft 15 rotations owing to fall the golf 17c of sprocket wheel 14a top, suspension bucket 17 is depressed, so, the phenomenon that whole suspension bucket 17 falls appears continually.
Misoperation in order to prevent to fall to producing owing to such golf 17c on golf vertical conveying device 120 of the present invention, is provided with the anti-fall plate 18 of the golf 17c on driving shaft 15 tops that can accommodate between the suspension bucket 17 that drops to above-mentioned lifting.Above-mentioned anti-fall plate 18 has various ways such as " V " shape, " ㄈ " shape.
The vertical conveying device of the present invention of such formation, if with reference to Fig. 2, then be the top that upper support body 12 is arranged on the 10a of hole portion of each layer, on the other hand, cover 12c is arranged on the face of its underpart, is arranged side by side lower support body 13 on the ground, and on 1 layer floor 10, form three 10a of hole portion side by side, on 2 layers floors 10, form two, on 3 layers floors 10, form one.Therefore, at 1 layer chain 14b is set directly on lower support body 13 and the upper support body 12,2 layers with chain 14b via being arranged on lower support body 13 and the upper support body 12 at the hole of the 1 layer of formation 10a of portion, 3 layers with chain 14b via being arranged on lower support body 13 and the upper support body 12 at the hole of 1 layer and the 2 layers formation 10a of portion.In addition, above-mentioned chain frame 21 is set on the 10a of portion of the hole of above-mentioned 1 layer and 2 layers formation, prevents chain 14b vibration.
In said apparatus, the action of the motor that is possessed by a side at lower support body 13, chain 14b is along the sprocket wheel 14a on the driven axle 16 of driving shaft 15 that is arranged on lower support body 13 and upper support body 12, keep on and on top, rise again the action that downward subordinate falls, golf 17c is loaded in the suspension bucket 17 that is arranged on the chain 14b, go 1 layer ball to feed to 1 layer, go 2 layers ball to feed to 2 layers, go 3 layers ball to feed to 3 layers.
Unaccounted label 14 expression sprocket body in the accompanying drawing.
Shown in Figure 11 is the one-piece type golf ball collection box A5 of interior dress cleaning machine of the present invention, forms 1 collection ball tube A12 and cleaning machine A15 of the ball that compiles recovery and collect ball tube A16 for 2 times on this ball collection box A5.
Above-mentioned 2 collection ball tube A16 make the big cylindrical shell of the regular hexahedron of opened upper end, are formed with the passage A6d that is connected with the cover A13c of vertical transport portion in a side.In above-mentioned cover A13c, portion is provided with conveyer respectively within it, with supplying to the ball of passage A6d, as shown in Figure 2, feeds to each layer, the quantity of such cover A13c is arranged to identical with the number of plies in golf training shop.
Above-mentioned 1 collection ball tube A12 is the cylindrical shell that collects in the ball that each layer get for the first time, and in a side and its formation one of above-mentioned 2 collection ball tube A16, other wall of the critical partition wall A12a aspect ratio of ball tube A16 is low with collecting for 2 times.And, on above-mentioned 1 collection ball tube A12, be provided with golf ball conveying apparatus-vertical conveying device A12b as shown in Figure 12, be provided with a plurality of suspension buckets 17 on this vertical conveying device A12b, packing into is pooled to the ball of 1 collection ball tube A12, is sent to the ramp A13 with 1 collection ball tube A12 adjacency.
The ball that is sent to above-mentioned ramp A13 can be sent to cleaning machine A15 while roll along the inclined plane of ramp A13.Be provided with a plurality of brushes on above-mentioned cleaning machine A15, the driving by motor makes its action, and the ball via the brush of this cleaning machine A15 to have removed the state attached to its lip-deep foreign matter, is sent to above-mentioned 2 collection ball tube A16.
If describe again, then be in inside one side for 2 collection ball tube A16 of the big cylindrical shell of regular hexahedron, be provided with 1 collection ball tube A12 integratedly into little cylindrical shell, on this 1 time collection ball tube A12, be provided with the vertical conveying device A12b that vertically carries golf, side at this vertical conveying device A12b, be provided with ramp A13 and cleaning machine A15, the golf the 1st time that is pooled to 1 collection ball tube A12 supplies to the cover A13c of vertical transport portion via vertical conveying device A12b → ramp A13 → cleaning machine A15 → 2 time collection ball tube A16 → passage A6d.
On the other hand, if cleaning machine A15 breaks down, or in order to omit cleaning step, do not make the words of golf ball conveying apparatus-vertical conveying device A12b action, in being pooled to the golf that collects for 1 time among the ball tube A12, accumulate in the above ball of height of partition wall A12a, can directly spill into collection ball tube A16 2 times, feed to the cover A13c of vertical transport portion via passage A6d.
Unaccounted label A14 represents water for cleaning is supplied to the water tank of above-mentioned cleaning machine A15 in the accompanying drawing.
As previously discussed, according to the present invention, owing to the upper and lower part supporting mass is arranged on the ground and each layer floor of Machine Room, on the other hand, only on its exterior face, cover is set, so, the expense of making needed expense and being produced can be saved effectively with installation.
In addition, owing to 1 collection ball tube that will compile the golf got with clean the cleaning machine that compiled ball and compile 2 times of the ball that cleaned and collect the ball tubes and make one in order to be sent to vertical transport portion, so, also can save the expense of making needed expense and being produced effectively with installation.

Claims (2)

1. the golf ball conveying apparatus in a golf training shop, the ball warp of getting in the position of respectively playing ball in the golf training shop that is made of multilayer is by ramp and ball recovery approach (1) and be cleaned totally, makes it supply to each layer once more, it is characterized in that:
Connection supplies to ball in the cover (A13c) and the passage (A6d) of the vertical transport portion of above-mentioned each layer, on the other hand, one side of 2 the collection ball tubes (A16) that form at the passage by regular hexahedron with opened upper end is inner to be formed 1 time of packing into via the ball of above-mentioned ramp and recovery approach (1) and collects ball tube (A12), formation will collect in the vertical conveying device (A12b) that ball in this 1 time collection ball tube (A12) vertically is transported to top, simultaneously, connect ramp (A13) and cleaning machine (A15) in the one side, be made into one.
2. according to the golf ball conveying apparatus in the golf training shop of claim 1, it is characterized in that: go up to form lower and 2 critical partition walls (A12a) of collection ball tube (A16) at above-mentioned 1 collection ball tube (A12), the ball that collects in above the height of this partition wall (A12a) can directly be spilt in 2 collection ball tubes (A16).
CNB031494137A 2003-06-20 2003-06-20 Golf conveying appliance of golf training gymnasium Expired - Fee Related CN1327921C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB031494137A CN1327921C (en) 2003-06-20 2003-06-20 Golf conveying appliance of golf training gymnasium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB031494137A CN1327921C (en) 2003-06-20 2003-06-20 Golf conveying appliance of golf training gymnasium

Publications (2)

Publication Number Publication Date
CN1565685A CN1565685A (en) 2005-01-19
CN1327921C true CN1327921C (en) 2007-07-25

Family

ID=34472534

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB031494137A Expired - Fee Related CN1327921C (en) 2003-06-20 2003-06-20 Golf conveying appliance of golf training gymnasium

Country Status (1)

Country Link
CN (1) CN1327921C (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100653131B1 (en) * 2006-02-01 2006-12-04 시 명 김 Lifting device for sending vertically golf-ball
CN104815429A (en) * 2015-04-21 2015-08-05 云大纯 Golf ball management system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05146534A (en) * 1991-04-24 1993-06-15 Hakodate Seimo Sengu Kk Method and device for collecting ball in golf training field
JPH08107953A (en) * 1994-10-07 1996-04-30 Tatsuro Yano Golf ball collector
CN1248476A (en) * 1998-09-23 2000-03-29 金时明 Golf ball delivery device for golf training field

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05146534A (en) * 1991-04-24 1993-06-15 Hakodate Seimo Sengu Kk Method and device for collecting ball in golf training field
JPH08107953A (en) * 1994-10-07 1996-04-30 Tatsuro Yano Golf ball collector
CN1248476A (en) * 1998-09-23 2000-03-29 金时明 Golf ball delivery device for golf training field

Also Published As

Publication number Publication date
CN1565685A (en) 2005-01-19

Similar Documents

Publication Publication Date Title
JP5371006B2 (en) Amusement machine island
CN1327921C (en) Golf conveying appliance of golf training gymnasium
KR20130012359A (en) Washing maching and method for assembling weight balance thereof
CN208197140U (en) Pre-stress rail plate continuous production complete set of equipments
JPH11235462A (en) Game machine installing island
CN105850555A (en) Stereoscopic greening box
CN105013762B (en) Rare metal and its alloy detritus material rotating cage type ultrasonic cleaning equipment and method
KR100473655B1 (en) Lifting device for sending vertically golf-ball
JP5165910B2 (en) Island where game machines are installed
CN113319061A (en) Ultrasonic cleaner with prevent string liquid function
JP5165911B2 (en) Island where game machines are installed
CN205393060U (en) Silk flosssilk wadding washs uses spray set
CN215523968U (en) Drying box structure of bearing
CN111990733A (en) Automatic threading device for jewelry
JP3821864B2 (en) Amusement media storage tanks at Amusement Machine Island
CN221433825U (en) Cleaning, screening and weighing device
CN212498264U (en) Precast unit concrete cloth system
CN220344311U (en) Cleaning apparatus
KR20120006564U (en) Improvement carrying frame for saplings box
CN216334608U (en) Whole part transportation system and supporting factory building
CN217963834U (en) Ultrasonic cleaner with prevent string liquid function
CN111958803A (en) Precast unit concrete cloth system
CN111703815B (en) Ore storage yard discharge system
JP2014033942A (en) Game island
JP2003071099A (en) Pachinko ball storing and conveying mechanism

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070725