Pile jacking in method is lifted in novel PHC stake and water qi of chong channel ascending adversely
Technical field:
The present invention relates to a kind of novel PHC stake and water qi of chong channel ascending adversely and lift pile jacking in method.
Background technology:
In the building pile foundation engineering of city, because of producing noise, hammer piling is unfavorable for environmental protection, in recent years extensively adopted static pressure sinking PHC piling method, this method is applicable to the soft foundation that does not have sand or crushed gravel hard interbedded layer, to ground and sharp sand or the crushed gravel ground that sand or crushed gravel hard formation are arranged in the soft foundation, excessive to penetrating resistance because of sand stone layer, static pressure PHC stake can't be passed through sand or crushed gravel layer, this method is just of no use, and this moment, pile sinking just became an insurmountable difficult problem.
In the soft foundation, often run under sand or the crushed gravel hard formation and to also have weak soil layer, the building that load is big or important, because of settling amount and differential settlement strict, its foundation pile not only will pass through sand stone layer, also will pass the weak soil layer under it, and the stake end is placed darker desirable bearing stratum.At this point under the matter condition,, only use quality instead and be not so good as the PHC stake and high the dashing of cost (brill) hole pouring pile because of static pressure PHC stake can't pass sand stone layer.Same engineering adopts towards (brill) hole pouring pile than adopting PHC stake cost will increase by 40~50%, in view of two kinds of stake type cost difference great disparities and workmanship needs, urgent need works out the method for PHC stake by sand or crushed gravel hard formation, and the short PHC stake of super quality and competitive price duration being substituted dash (brill) hole pouring pile is the hot subject of current pile foundation engineering.
Summary of the invention:
The invention solves the above-mentioned difficult problem of existing in prior technology, provide a kind of and can use the novel PHC stake of PHC sunk pile and water qi of chong channel ascending adversely to lift pile jacking in method easily and fast, at low cost.
Technical scheme of the present invention is as follows:
1, pile jacking in method is lifted in the water qi of chong channel ascending adversely, it is characterized in that:
The first step, ground surface weak soil layer pile sinking adopt static pressure to bury, and static pressure is not to till a stake pressure is sunk with maximum pile driving pressure;
Second step, the stake point sinks when reaching sand or crushed gravel layer, insert the aqueous vapor compound tube from the stake top to hollow cavity, after the aqueous vapor compound tube sinks and reaches a point, import water under high pressure and compressed air respectively to water-supply-pipe and appendix, water under high pressure penetrates from stake point weep hole, and the sand and the crushed gravel that directly wash away a crack tip form the sandstone mixing water; The nationality gas lift method is discharged the sandstone mixing water from bottom to top along the hollow cavity of stake from the stake top, just can sink to stake sand and crushed gravel layer with less pile driving pressure this moment, Yi Bian import water under high pressure and compressed air thus, Yi Bian add static pressure, sand stone layer passed in stake;
The 3rd step after the stake point passes sand and crushed gravel layer, when arriving the weak soil layer, stopped jetting, and only the nationality static pressure is passed weak soil with stake and sunk to design elevation; Perhaps, to there not being the sand stone layer ground pile sinking of weak soil under sand and the crushed gravel layer, pile sinking stops jetting to last 1~2 meter of sand stone layer, and pure static pressure is to design elevation.
2, novel PHC stake: a kind of novel PHC stake with hollow cavity is characterized in that: be provided with the stake point of hollow back taper the end in the stake of PHC stake, have weep hole at the front end of stake point, partly have backwater hole at the awl body of stake point; Be equipped with weep hole piston and the backwater hole piston that complements one another with it at weep hole and backwater hole place, in hollow cavity, be provided with the aqueous vapor compound tube.
The present invention has following advantage:
(1) method is easy, cost is low, and easy operating uses, and can effectively reduce penetrating resistance, makes stake pass sand smoothly and the crushed gravel layer sinks to design elevation always.
(2), the same engineering pile sinking method that adopts PHC stake of the present invention dashes (brills) hole pouring pile and saves cost 40~50% than adopting, the former is more more superior than the latter for while workmanship, duration and environmental protection aspect.
(3), sand or crushed gravel ground pile sinking are had unique effect, stake can penetrate any covering layer, the stake end can be sunk quickly reach desirable bearing stratum.
Description of drawings:
Fig. 1 is the structure sectional view of an embodiment of the present invention.
Fig. 2 is the structure for amplifying sectional view of stake point.
Fig. 3 is the local enlarged side view of Fig. 1.
Fig. 4 is the jetting nozzle of water conveyance steel tube and gas transmission pipe.
Fig. 5 is the structural representation of gas outlet.
Label declaration: at the bottom of 1 pile body, 2 tops, 3, the bend pipe of 4 points, 5 weep holes, 6 backwater holes, 7 weep hole pistons, 8 backwater hole pistons, 9 hollow cavitys, 10 water conveyance steel tubes, 10` water delivery hose, 11 gas transmission pipes, 11` airline hose, 12 water deliverys and gas transmission pipes, 13 aqueous vapor compound tube joints, 14 gas outlets, 15 flap valve, 16 jetting nozzles, 17 sharp reinforcing ribs.
The specific embodiment:
Shown in Fig. 1-5: PHC stake of the present invention is a kind of novel PHC stake with hollow cavity 9, it is characterized in that: the stake in the PHC stake is provided with hollow back taper stake point 4 in an end 3, has weep hole 5 at the front end of stake point 4, partly has backwater hole 6 at the awl body of stake point 4; Be equipped with weep hole piston 7 and the backwater hole piston 8 that complements one another with it at weep hole 5 and backwater hole 6 places, in hollow cavity 9, be provided with the aqueous vapor compound tube, the aqueous vapor compound tube is fused by aqueous vapor compound tube joint 13 by water conveyance steel tube 10 and gas transmission pipe 11 and forms, the water inlet end of water conveyance steel tube 10 and gas transmission pipe 11 and inlet end are provided with the bend pipe 12 of water delivery and gas transmission pipe, water inlet end at the bend pipe 12 of water delivery and gas transmission pipe is connected water delivery hose 10` and airline hose 11` respectively with inlet end, in the water side of water conveyance steel tube 10 jetting nozzle 16 is housed, the jetting nozzle 16 of water conveyance steel tube 10 is near the weep hole 5 of PHC stake, in the outlet side of gas transmission pipe 11 gas outlet 14 is housed, on the outside wall surface of stake point 4, is provided with the sharp reinforcing rib 17 of stake.Pile body 1 connects into a pile or by the stake of number joint and saves stake from becoming a pile according to the pile length needs, and corresponding aqueous vapor compound tube also is made up of a number pipe joint or a pipe joint.
Embodiment 1:
The first step, ground surface weak soil layer pile sinking adopt static pressure to bury.Static pressure is not to till a stake pressure is sunk with maximum pile driving pressure.The heavy end face that reaches sand or crushed gravel layer of stake this moment point.
In second step, the stake point sinks when reaching sand or crushed gravel layer, inserts the aqueous vapor compound tube from stake top 2 to hollow cavity 9, as shown in Figure 1.The aqueous vapor compound tube is imported water under high pressure and compressed air respectively to water delivery hose and airline hose after sinking and reaching a point, and water under high pressure penetrates from stake point weep hole, and the sand and the crushed gravel that directly wash away a crack tip form the sandstone mixing water; The nationality gas lift method is discharged the sandstone mixing water from bottom to top along the hollow cavity of stake from the stake top, behind water discharge sandstone, penetrating resistance subtracts greatly, and just can sink to stake sand and crushed gravel layer with less pile driving pressure this moment.Import water under high pressure and compressed air on one side thus,, just can successfully stake be passed sand and crushed gravel layer Yi Bian add static pressure.
The 3rd step after the stake point passes sand and crushed gravel layer, when arriving the weak soil layer, stopped jetting, and only the nationality static pressure is passed weak soil with stake and sunk to design elevation.
To there not being the sand stone layer ground pile sinking of weak soil under sand and the crushed gravel layer, its pile sinking operation lacked for the 3rd step, but pile sinking stops jetting to last 1~2 meter, and pure static pressure is to design elevation.
About pile sinking equipment
Pile sinking equipment of the present invention: except that static pile press, high-pressure hydraulic pump, air compressor and aqueous vapor compound tube etc. are arranged.
Stake sharp weep hole 5 and backwater hole 6 places set out water hole piston 7 and backwater hole piston 8, see shown in Figure 2ly, and purpose prevents that in the first step pile driving process earth from entering the hollow cavity 9 of stake, helps the heavy smoothly stake point that reaches of aqueous vapor compound tube.When second step, pile sinking began jetting, nationality jetting pressure was discharged piston 7 and 8 outside the pile body.Jetting nozzle and gas outlet place is provided with flap valve 15, sees shown in Figure 4ly, and purpose is in the jetted pile process, and barrier is cut off the water and stopped the supple of gas or steam for some reason, prevents that sandstone from pouring in the aqueous vapor pipe, avoids pipeline blockage.