CN1244745C - Telescoping construction platform - Google Patents

Telescoping construction platform Download PDF

Info

Publication number
CN1244745C
CN1244745C CN 200310103379 CN200310103379A CN1244745C CN 1244745 C CN1244745 C CN 1244745C CN 200310103379 CN200310103379 CN 200310103379 CN 200310103379 A CN200310103379 A CN 200310103379A CN 1244745 C CN1244745 C CN 1244745C
Authority
CN
China
Prior art keywords
construction platform
dumper
guide rail
car body
scalable construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200310103379
Other languages
Chinese (zh)
Other versions
CN1540118A (en
Inventor
陈传为
韩长广
李洁如
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jie an architectural scaffolding Co., Ltd.
Zhongtian Construction Group Co Ltd
Original Assignee
JIEAN ARCHITECTONICAL FRAMING SCAFFOLD CO Ltd BEIJING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIEAN ARCHITECTONICAL FRAMING SCAFFOLD CO Ltd BEIJING filed Critical JIEAN ARCHITECTONICAL FRAMING SCAFFOLD CO Ltd BEIJING
Priority to CN 200310103379 priority Critical patent/CN1244745C/en
Publication of CN1540118A publication Critical patent/CN1540118A/en
Application granted granted Critical
Publication of CN1244745C publication Critical patent/CN1244745C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a telescopic construction platform which comprises a base, wherein the base is provided with two guide ways in parallel along a transverse direction. The upper surface of each guide way is respectively provided with a group of lifting and fixing devices; both of the two guide ways are provided with grooves, wherein the openings of which are opposite to each other. A material carrying vehicle is arranged between the two grooves; both sides of the material carrying vehicle are respectively provided with wheels which respectively correspond to the grooves of the two guide ways. When the present invention is used, the two guide ways are arranged in the mode of facing to the outside of a building; the two groups of lifting and fixing devices are respectively abutted on a top plate of a floor and the two guide ways; then, the material carrying vehicle is pushed out of the building along the two guide ways to be used as a construction platform, and is pulled back into the building after materials are put on the material carrying vehicle. Therefore, the telescopic construction platform of the present invention has the characteristics of convenient use and enhanced work efficiency of construction. The purpose of the present invention is to provide a telescopic construction platform with convenient use and enhanced work efficiency of construction.

Description

Scalable construction platform
Technical field
The present invention relates to a kind of building operations device, relate in particular to a kind of scalable construction platform.
Background technology
In the work progress of multistory building and highrise building, after each floor structure typing, also need to continue to carry various constructional materialss to each floor, tower crane then is a preferred unit of carrying constructional materials expeditiously to each floor.But owing to can't directly constructional materials be delivered to each floor with tower crane.Now normally take a fixed building platform that protrudes from building to be set respectively at each floor, at needs when certain floor is carried constructional materials, can utilize tower crane that constructional materials is winched on the construction platform that each floor sets up in advance earlier, constructional materials be drawn in the building from construction platform by the constructor again.But because the many places construction operation point of each floor all might need constructional materials, and be positioned at the fixed building platform of top floor owing to be to protrude from outside the building, will certainly influence the floor of below, it can't be provided with simultaneously or can't the fixed building platform be set, thereby reduced the operating efficiency of building operations in best place.
Summary of the invention
In order to solve problems of the prior art, the object of the present invention is to provide a kind of easy to usely, and can improve the scalable construction platform of building operations operating efficiency.
A kind of scalable construction platform, comprise pedestal, described pedestal is along laterally being provided with two guide rails abreast, and the upper surface of every guide rail is respectively equipped with at least two liftable columns, adopts pull bar to link to each other between each liftable column, two guide rails have groove, the opening of two grooves is provided with dumper between two grooves toward each other, and the both sides of dumper are respectively equipped with wheel, the wheel of both sides matches with the sidewall of two grooves respectively, and described dumper is provided with antijoyride device.
Scalable construction platform of the present invention, wherein said antijoyride device comprises the locating hole that is located on the car body, is fitted with locating shaft in the locating hole, and match with locating sleeve in the lower end of locating shaft, and locating sleeve is installed in the rear and front end of described pedestal respectively.
Scalable construction platform of the present invention, wherein said dumper comprises car body, and the plane is fixed on the H shape longeron of the car body left and right sides up, the every interior rear end of longeron outer side slot is respectively equipped with two described wheels, the wheel face of two wheels pass longeron on, lower plane, match with the upper side and the downside of described groove respectively, the front end of each groove can be provided with limited roller respectively rotationally, limited roller is provided with semi-circular groove, it is semicircular rail that upper side in each described outer side slot is provided with cross section, and the semi-circular groove of each limited roller matches with rail respectively.
Scalable construction platform of the present invention, wherein said liftable column comprises upper plate and lower roof plate, the inner end of upper plate and lower roof plate is connected with threaded lifting pin respectively, lifting pin is provided with the jacking nut, section is inserted into respectively in the jacking cover in each lifting pin, and described pull bar links to each other with the jacking cover.
Scalable construction platform of the present invention, the cross section of wherein said lower roof plate is a shape, and its soffit is fixed with alignment pin, and the upper surface of described guide rail is provided with dowel hole, described lower roof plate pastes mutually with the upper surface and the lateral surface of guide rail, and described alignment pin is inserted in the described dowel hole.
Scalable construction platform of the present invention, wherein the cross section of every described guide rail is a H shape.
Scalable construction platform of the present invention, the front end of wherein said car body are provided with two breast boards, and breast board is inserted in the pin-and-hole cover, and the left and right sides of described car body is respectively equipped with three baffle plates, and each baffle plate adopts hinge to install.
Scalable construction platform of the present invention, wherein the upper surface of every described guide rail is respectively equipped with 2~6 described liftable columns.
The advantage and the good effect of scalable construction platform provided by the invention are: it comprises pedestal, pedestal is along laterally being provided with two guide rails abreast, the upper surface of every guide rail is respectively equipped with one group of jacking fastening devices, two guide rails have opening groove respect to one another, be provided with dumper between two grooves, the both sides of dumper are respectively equipped with wheel, and the wheel of both sides is corresponding with the groove of two guide rails respectively.Make two guide rails outside the building, arrange in use, again two groups of jacking fastening devicess are held out against top board and two guide rails of floor respectively, then just can with dumper outside two guide rails are released buildings as construction platform, retract in the building along guide rail again after putting material, so it is easy to use that it has, and can improve the characteristics of building operations operating efficiency.
Description of drawings
Fig. 1 is the front view of the structural representation of scalable construction platform provided by the invention;
Fig. 2 is the lateral view of Fig. 1;
Fig. 3 is the vertical view of Fig. 1;
Fig. 4 is the partial enlarged view of limited roller;
Fig. 5 is the partial enlarged view between wheel and the groove upper side;
Fig. 6 is the partial enlarged view between wheel and the groove downside;
Fig. 7 is the front view of the structural representation of strut and liftable column junction.
The specific embodiment
Referring to Fig. 1, Fig. 2 and Fig. 3, scalable construction platform of the present invention comprises pedestal 1, and pedestal 1 is along laterally being provided with two guide rails 2 abreast, and the cross section of every guide rail 2 is a H shape, and every guide rail 2 planar ends are fixed on the pedestal 1 up.The upper surface of every guide rail 2 is respectively equipped with four liftable columns 3, two guide rails 2 have groove 5, two grooves 5 opening toward each other, be provided with dumper 4 between two grooves 5, the both sides of dumper 4 are respectively equipped with wheel 6, the wheel 6 of both sides matches with the sidewall of two grooves 5 respectively, and described dumper 4 is provided with antijoyride device (not drawing among the figure).
Antijoyride device comprises the locating hole that is located on the car body 11, is fitted with locating shaft in the locating hole, matches with locating sleeve in the lower end of locating shaft, and locating sleeve is installed in the rear and front end of described pedestal 1 respectively.Antijoyride device can be used for fixedly dumper 4, when dumper 4 moves to the floor outside, the lower end of locating shaft can be inserted to the locating sleeve that is positioned at the outer end, fix dumper 4 after, again on dumper 4 loading, loading finishes, extract locating shaft, again dumper 4 is drawn in floor inside, the lower end of locating shaft is inserted to the locating sleeve that is positioned at the inner end, after fixing dumper 4, again from dumper 4 unloadings.
Referring to Fig. 1 and Fig. 7, adopt pull bar 10 to link to each other between each liftable column 3 with jacking cover 9, liftable column 3 comprises upper plate 18 and lower roof plate 19, the inner end of upper plate 18 and lower roof plate 19 is connected with threaded lifting pin 20 respectively, lifting pin 20 is provided with jacking nut 21, section is inserted into respectively in the jacking cover 9 in each lifting pin 20, rotates jacking nut 21, just can adjust lifting pin 20 and overlap the length that leans out in 9 from jacking.
The cross section of lower roof plate 19 is a shape, its soffit is fixed with alignment pin (not drawing among the figure), the upper surface of guide rail 2 is provided with dowel hole (not drawing among the figure), and lower roof plate 19 pastes mutually with the upper surface and the lateral surface of guide rail 2, and alignment pin is inserted in the dowel hole simultaneously.
Referring to Fig. 1, Fig. 2, Fig. 4, Fig. 5 and Fig. 6, dumper 4 comprises car body 11, and the plane is fixed on the H shape longeron 8 of car body 11 left and right sides up, every longeron 8 outer side slots 5 ' interior rear end is respectively equipped with two wheels 6, the wheel face of two wheels 6 pass longeron 8 on, lower plane, match with the upper side and the downside of groove 5 respectively, the front end of each groove 5 can be provided with limited roller 7 respectively rotationally, limited roller 7 is provided with semi-circular groove 17, it is semicircular rail 16 that each outer side slot 5 ' interior upper side is provided with cross section, and the semi-circular groove 17 of each limited roller 7 matches with rail 16 respectively.
Front end at car body 11 is provided with two breast boards 12, and breast board 12 is inserted in the pin-and-hole cover, is respectively equipped with three baffle plates 13 in the left and right sides of car body 11, and each baffle plate 13 adopts hinge 15 to install.Breast board 12 and baffle plate 13 are set prevent that the goods landing from going out, and can improve the quantity of car body 11 lades.The time spent can not extracted the back folding and unfolding with two breast boards 12 in the pin-and-hole cover at ordinary times, simultaneously each baffle plate 13 is fallen onboard.
Scalable construction platform of the present invention in use, can on carrying the floor of floor of constructional materials, needs lay pedestal 1, and two guide rails 2 are arranged outside the building, and then eight liftable columns 3 are erected on the upper surface of every guide rail 2 in uniform way, rotate jacking nut 21 again, adjust each lifting pin 20, make it in jacking cover 9, lean out, hold out against top board and two guide rails 2 of floor respectively until upper plate 18 and lower roof plate 19, connect the pull bar 10 between each liftable column 3 again, then just can with dumper 4 outside two guide rails 2 are released buildings as construction platform, retract in the building along guide rail 2 again after putting material.
Embodiment recited above is described preferred implementation of the present invention; be not that design of the present invention and scope are limited; do not breaking away under the design philosophy prerequisite of the present invention; common engineers and technicians make technical scheme of the present invention in this area various modification and improvement; all should fall into protection scope of the present invention; the technology contents that the present invention asks for protection, whole.Be documented in claims.

Claims (8)

1. scalable construction platform, comprise pedestal (1), it is characterized in that: described pedestal (1) is along laterally being provided with two guide rails (2) abreast, the upper surface of every guide rail (2) is respectively equipped with at least two liftable columns (3), adopt pull bar (10) to link to each other between each liftable column, two guide rails (2) have groove (5), the opening of two grooves (5) toward each other, be provided with dumper (4) between two grooves (5), the both sides of dumper (4) are respectively equipped with wheel (6), (59 sidewall matches the wheel of both sides (6), and described dumper (4) is provided with antijoyride device with two grooves respectively.
2. according to the described scalable construction platform of claim 1, it is characterized in that: described antijoyride device comprises the locating hole that is located on the car body (11), being fitted with locating shaft in the locating hole, matches with locating sleeve in the lower end of locating shaft, and locating sleeve is installed in the rear and front end of described pedestal (1) respectively.
3. according to the described scalable construction platform of claim 2, it is characterized in that: described dumper (4) comprises car body (11), and the plane is fixed on the H shape longeron (8) of car body (11) left and right sides up, rear end in the outer side slot (5 ') of every longeron (8) is respectively equipped with two described wheels (6), the wheel face of two wheels (6) pass longeron (8) on, lower plane, upper side and downside with described groove (5) matches respectively, the front end of each groove (5) can be provided with limited roller (7) respectively rotationally, limited roller (7) is provided with semi-circular groove (17), it is semicircular rail (16) that upper side in each described outer side slot (5 ') is provided with cross section, and the semi-circular groove (17) of each limited roller (7) matches with rail (16) respectively.
4. according to the described scalable construction platform of claim 3, it is characterized in that: described liftable column comprises upper plate (18) and lower roof plate (19), the inner end of upper plate (18) and lower roof plate (19) is connected with threaded lifting pin (20) respectively, lifting pin (20) is provided with jacking nut (21), section is inserted into respectively in the jacking cover (9) in each lifting pin (20), and described pull bar (10) links to each other with jacking cover (9) respectively.
5. according to the described scalable construction platform of claim 4, it is characterized in that: the cross section of described lower roof plate (19) is a shape, its soffit is fixed with alignment pin, the upper surface of described guide rail (2) is provided with dowel hole, described lower roof plate (19) pastes mutually with the upper surface and the lateral surface of guide rail (2), and described alignment pin is inserted in the described dowel hole.
6. according to the described scalable construction platform of claim 5, it is characterized in that: the cross section of every described guide rail (2) is a H shape.
7. according to the described scalable construction platform of claim 6, it is characterized in that: the front end of described car body (11) is provided with two breast boards (12), breast board (12) is inserted in the pin-and-hole cover, the left and right sides of described car body (11) is respectively equipped with three baffle plates (13), and each baffle plate (13) adopts hinge (15) to install.
8. according to any one described scalable construction platform in the claim 1 to 7, it is characterized in that: the upper surface of every described guide rail (2) is respectively equipped with 2~6 described liftable columns (3).
CN 200310103379 2003-10-29 2003-10-29 Telescoping construction platform Expired - Fee Related CN1244745C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200310103379 CN1244745C (en) 2003-10-29 2003-10-29 Telescoping construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200310103379 CN1244745C (en) 2003-10-29 2003-10-29 Telescoping construction platform

Publications (2)

Publication Number Publication Date
CN1540118A CN1540118A (en) 2004-10-27
CN1244745C true CN1244745C (en) 2006-03-08

Family

ID=34333269

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200310103379 Expired - Fee Related CN1244745C (en) 2003-10-29 2003-10-29 Telescoping construction platform

Country Status (1)

Country Link
CN (1) CN1244745C (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2306549B1 (en) * 2005-08-04 2009-09-16 Israel Herrero Cuesta DEVICE FOR THE TRANSPORT OF MATERIALS IN CONSTRUCTION WORKS.
NO325802B1 (en) * 2006-09-04 2008-07-21 Jan Martin Kleppe Device for running rail
WO2011134500A1 (en) * 2010-04-27 2011-11-03 Abb Technology Ag An energy storage device for a power compensator and a method for control thereof
CN102926529B (en) * 2011-08-11 2014-11-26 北京建筑工程学院 Self-elevating scaffold provided with telescoping platforms for building construction
CN103206076B (en) * 2012-01-12 2015-12-02 佛山市南海保达建筑机械设备有限公司 A kind of packaged type building loading/unloading platform and moving method
CN103104103A (en) * 2013-01-30 2013-05-15 天津大学 Height adjustable novel building support
CN105971299A (en) * 2016-07-04 2016-09-28 天津职业技术师范大学 Automatic crawling robot for elevator shaft and safety protection platform mechanism
CN106499196A (en) * 2016-10-31 2017-03-15 中国冶集团有限公司 High building material transfer device
CN107842194B (en) * 2017-10-13 2023-11-21 中国建筑第八工程局有限公司 Form device of deformation joint and construction method thereof
CN110965761A (en) * 2019-12-31 2020-04-07 广西建工集团第五建筑工程有限责任公司 Scaffold suitable for multilayer assembled shear wall and construction method thereof

Also Published As

Publication number Publication date
CN1540118A (en) 2004-10-27

Similar Documents

Publication Publication Date Title
CN1244745C (en) Telescoping construction platform
CN111894621B (en) Tunnel disease restores platform truck fast
CN202768014U (en) Lining trolley for emergency parking strip
EP2114810B1 (en) Drive for a elevator car that can be serviced from said elevator car
CN107964840A (en) A kind of telescopic way traffic laterally withdraws multifunction operation vehicle elevation and application method
CN105967118A (en) Vehicle-mounted multifunctional maintenance lifting platform
CN111422014A (en) Highway-railway dual-purpose high-voltage cable paying-off operation vehicle and operation method thereof
CN2649696Y (en) Retractable building platform
CN105967116B (en) The scissor aerial work platform of forerunner's front steering
CN212447000U (en) Dual-purpose high tension cable unwrapping wire operation car of highway-railway
CN105000513A (en) Aerial work platform with easily-operated platform locking structure
CN211034837U (en) Be applied to sedan-chair frame structure of taking single set of safety tongs on big load goods lift
CN102921994B (en) Ship stern boring platform
CN211874373U (en) Vehicle-mounted workover rig driller operating platform ladder stand
CN207348782U (en) A kind of light rail car for assembling of ascending a height
CN202966475U (en) Trailer platform
CN211201115U (en) Detachable scaffold frame lift guide holder
CN2765734Y (en) Portable tool stand
CN2813776Y (en) Automatic steering up-down large wall board mounting vehicle
CN208380038U (en) A kind of reinforcement installation trolley
CN105752177A (en) Special trailer for conveying prefabricated panels
CN217975276U (en) Lifting support for building engineering construction
CN219449116U (en) Derailment restorer of tunnel construction rail transport vehicle
CN204938884U (en) There is the high-altitude operation platform of hole hole fender guard and easy entry type handrail door
CN210888950U (en) Tunnel construction trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BEIJING JIE AN ARCHITECTURAL SCAFFOLDING LIMITED;

Free format text: FORMER OWNER: BEIJING JIE AN ARCHITECTURAL SCAFFOLDING LIMITED

Effective date: 20080201

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20080201

Address after: Beijing City, Chaoyang District Guanzhuang Township Guanzhuang Village (Beijing Road North Road) zip code: 100024

Co-patentee after: Tian Zhong Construction Group Co., Ltd.

Patentee after: Beijing Jie an architectural scaffolding Co., Ltd.

Address before: Beijing City, Chaoyang District Guanzhuang Township Guanzhuang Village (Beijing Road North Road) zip code: 100024

Patentee before: Jiean Architectonical Framing Scaffold Co., Ltd., Beijing

C56 Change in the name or address of the patentee

Owner name: BEIJING JIE AN ARCHITECTURAL SCAFFOLDING LIMITED;

Free format text: FORMER NAME OR ADDRESS: BEIJING JIE AN ARCHITECTURAL SCAFFOLDING LIMITED; TIANZHONG CONSTRUCTION GROUP CO., LTD.

CP03 Change of name, title or address

Address after: Beijing City, Chaoyang District Guanzhuang Township Guanzhuang Village (Beijing Road North Road) zip code: 100024

Co-patentee after: Zhongtian Construction Group Co., Ltd.

Patentee after: Beijing Jie an architectural scaffolding Co., Ltd.

Address before: Beijing City, Chaoyang District Guanzhuang Township Guanzhuang Village (Beijing Road North Road) zip code: 100024

Co-patentee before: Tian Zhong Construction Group Co., Ltd.

Patentee before: Beijing Jie an architectural scaffolding Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20060308

Termination date: 20151029

EXPY Termination of patent right or utility model